Industry & Facilities Division Page: 1/1

NON CONFORMANCE REPORT N°01

BV Job nr:: 0447 /GMS / 2022/1P

PROJECT: Ref:N/A
The Construction of the Hot Leaching Compaction Plant

BV Client:Petrojet P/o Nr: 0447 /GMS / 2022


(client to BV)

Manufacturer:petrojet IPO Ref (If applicable):N/A


(BV internal P/o)
Inspection requested by: Petrojet

SUPPLY / SUBJECT OF INSPECTION ITEM/TAG Nr QTY

Surveillance and witnessing fabrication daily activities related Project: 3C22 1


The Construction of the Hot Leaching Compaction Plant 3C30 1
5C36 1

1 – DESCRIPTION AND LOCATION


OF THE NON CONFORMITY : 3 – CORRECTIVE ACTION VERIFIED (i.e. NCR closed)
During our survey today 24/11/2022 at the occurrence
The time it was noted that Petrojet shipped the subject
items(3C22,3C30,5C36) without final visual inspection
as well as the shipping process occurred when the paint
was not dry to handle and was still tacky which it's not
able to be handled or checked the thickness of the full
paint system as per data sheet, this is not acceptable as
per paint procedure PTJ-HLP-PCD-s-sss-002 item 7 as
well as PTJ-HLP-ITP-s-sss-001 item 6.6 and 6.8

Comments
Paint shall be cured to check DFT and dry to handle
before any process for shipping see attached photo 1

2 – MANUFACTURER PROPOSAL :

INSP 003 En
GM SI 101 Copyright Bureau Veritas 04/2011
Paint not dry to handle(see Photo1)

Originated by: Closed by:


Checked by: Checked by:

Name: Ahmed Gamil Signature:… Name: l … Signature:…


Name:… Signature:… Name:… Signature:…

Date of issue: 24 Nov.2022… Date of issue:…


BV STAMP
Inspection centre: BV Suez………… Inspection centre: BV ……………

Distribution: BV CLIENT MANUFACTURER Distribution: BV CLIENT MANUFACTURER

INSP 003 En
GM SI 101 Copyright Bureau Veritas 04/2011