MINUTES OF MEETING
Document No:
Document Type: MOM Rev:00 Date: 07.01.2024 Page: 1-5
22098-2999-RT-0275-0036
Certificate of Participants
Note: This Attendance sheet is considered an official document from FYPC MP /LAB#4 Date:
to approve the participation of the project employees in this session: 07.01.2024
Subject: Type
Weekly HSE Meeting Workshop Training Meeting Toolbox talk
EPC-SUBCON √
S. No Name Designation Organization
1 Retheesh Kumar HSE Lead MP -FYPC
2 Zhao Const. Manager WISON
3 Muhammad Ashraf HSE Manager WISON
4 Sajid Khan HSE Supervisor WISON
5 Wang HSE Engineer WISON
6 Mohammad Thouseef HSE DCC WISON
7 Ismail Zabi HSE Trainer WISON
8 Shoaib Equipment Inspector WISON
9 Shahid Const. Manager RMCO
10 Qadeer HSE Manager RMCO
11 Atta ur rehman HSE Officer CPECC
Document No:
Document Type: MOM Rev:00 Date: 07.01.2024 Page: 1-5
22098-2999-RT-0275-0036
Legend:
FAT Fatality FI Fire Incident
LTI Lost Time Injury HIPO High Potential (Situation & Incident)
RWC Restricted Work Case NM Near Miss
MTC Medical Treatment Cases VA Vehicle Accidents
FAC First Aid Case LSR Lifesaving Rules
PD Property Damages ENV Environment Incidents
Item
Minute/Description Total No: Responsible Status
no:
III Traffic and Security 0 Contractor
Document No:
Document Type: MOM Rev:00 Date: 07.01.2024 Page: 1-5
22098-2999-RT-0275-0036
ACTION ITEMS
The contractor is to obtain the vehicle stickers from FYPC
for contractor vehicles to drop off and pick up the
employees from the site. All buses shall drop the
1. Info Ongoing
employees at gate -1 for brown field and Gate -3 for MOC, WISON
nobody is allowed to walk in the plant premises to reach to
the LAB#4 area.
FYPC informed contractor and subcontractor to arrange WISON 26.11.23
red color shirt for the onsite HSE staff. 03.12.23
2. Open
10.12.23
17.12.23
FYPC informed contractor to ensure an official notification
3. has been sent to FYPC if any extended or holiday activities WISON 10.12.23
Info
take place.
FYPC informed contractor to mobilize required Permit
4. WISON 17.12.23
issuers to the site as per the site activities and increased Open
permits.
FYPC informed contractor and Sub-con to take strict action WISON 17.12.23
5. Info
on hard barricading around the deep excavation area.
Document No:
Document Type: MOM Rev:00 Date: 07.01.2024 Page: 1-5
22098-2999-RT-0275-0036
EQUIPMENT
SCAFFOLDING
FYPC informed contractor to mobilize competent Open
1. scaffolding supervisor/Foreman at site. WISON 31.12.23
TRAINING
FYPC informed contractor to add in the training slide about WISON 31.12.23
1. the FYPC alarm testing notification which has set on every Info
Wednesday from 10:00 to 10:30am
FYPC informed contractor to send training notification for WISON 31.12.23
2. the training schedule. Info
ENVIRONMENT
Document No:
Document Type: MOM Rev:00 Date: 07.01.2024 Page: 1-5
22098-2999-RT-0275-0036
RMCO
Contractor informed RMCO to submit all site safety related RMCO 12.11.23
documents without delay including 03.12.23
1. 10.12.23 Info
1. TMP 15.12.23
17.12.23
Contractor informed RMCO to arrange the site necessary 12.11.23
welfare facilities soon RMCO 26.11.23
03.12.23
2. 1.Smoking shelter 10.12.23 Closed
15.12.23
17.12.23
FYPC informed contractor/Sub-Contractor to mobilize a
RMCO 10.12.23 Open
3. safety supervisor to the site as per the increased
17.12.23
manpower ratio.
Contractor informed Sub-Contractor to send weekly 10.12.23
/monthly deliverable as well as site observation tracking RMCO 17.12.23
4. Closed
record.
CPECC
FYPC informed Sub-contractor (CPECC) to submit the Scope CPECC 17.12.23
1. of work on the related activities. Open