A temporary shelter has been in use for Mess hall, rest 28-02-2024
6 XXII L RMCO LAYDOWN On-Going Feb-17-2024
shelter and Prayer hall, which should be separated ETC date
Damaged green mesh shall be replaced around from Belongs to “West Lines” They already
7 XXII L RMCO REST SHELTER Feb-17-2024 18-02-2024
the shelter removed the shelter
An excavation with shoring provided not suitable for Rmco Provided Scaffolding to protect the
8 XI M RMCO UTILITY AREA Feb-17-2024 18-02-2024
withstanding the soil erosion Soil erosion
9 Laydown area shall be protected with hard barrier II L RMCO UTILITY AREA Provided soft barriers till scaffolders get their Feb-17-2024 25-02-2024
ajeer.
On-Going 28-02-2024
10 Waste skip not available to dispose the site waste XVI L RMCO UTILITY AREA Feb-17-2024
ETC date
Multiple excavation beside the road has been observed Rmco Provided additional Blinking Lights
11 XIX L RMCO SLEEPER AREA on the road side Feb-17-2024 18-02-2024
with no blinking lights
Rebar caps not provided for the extended protruding Rmco Provided Rebar caps
12 XI L RMCO SLEEPER AREA Feb-17-2024 18-02-2024
rebars
Improper materials arrangement observed in multiple FIRE STATION
13 XXI L RMCO Wison Feb-17-2024
areas which shall be stored properly. AREA