Location:- Date :
Sr.N Activity
Type of Hazard Risk Involved Risk Control measures
o. Name
Only inspected sccafold having ledger on 500-500 mm distance for the access.
The ground shall be make level. Provide base plate while errecting on non concreting surface &
Uneven approch,
Errection of Fall of person, fall provide adjustable jacks while errecting on uneven surface to adjust level.
uneven level,
8 Beam,Rafter on of scafold, fall of Ensure that the sccafold should be erect in plumb & maintain the base height ratio 1:4 .
inadequate working
colomn material Provide top rail ,middle rail & scaffold should be inpected before start the activity.
platform
Provide Green & red tag. Planks should be provide for working platform tied at both ends .
Materials i.e. hand tools should be shifted with the help of rope.
No any loose material i.e nut bolt kept on working platform.Errection periphery area should be soft
barricated & no any person stand below suspended load.
Only inspected handtools should be used & ensure that the beam should be adequarely fitted with bolting.
loose materials, Personal injury,
Errection of
9 loose bolting, faulty fall of person, Sling should be not removed until the beam adequately fitted with column by nut bolt.
Beam,
handtools stuck to person Wire rope sling loosed in such a way that the sling come near scaffold so the person can easily de-sling the
wire rope
Only trained person deployed for errection work .
Work should be done under continous supervision.
Ensure Night work permit before work
Work During Fall of person,
10 Darkness Proper illumination should be provide during night work.
Night personal injury
Emergency evacution plan should be explain to all workers.
Name & Signature of Site Engineer / Supervisor :_________ Name & Signature of Site In-charge :___________
Name & Signature of Project In-charge :__________ Name & Signature of HSE Officer : ______