Detailed Summary of Work done in the month of November 2022

1. Steel Fixing & Concrete of Bed + Chamfer walls of Connection Channel from RD 204 to 224 complete

2. Dressing & Levelling & Lean Concrete of Connection Channel from RD 0+110 TO 0+170 is complete

2. Steel Fixing & Concreting of HRC D/S site From RD 3+150 to 3+180 & RD 3+260 to 3+300 Bed +
Chamfer walls is complete.

3. Steel Fixing & Concreting of Walls & Top Slab of HRC U/S site From RD 0+180 to 0+210 is complete

3. Steel Fixing & Concreting of Forebay Bed Panel C-D Grid 1/2 & 3/4 is complete

4. Sand trap walls Grid D-E from Construction joint upto top & F-G R/S & G-H L/S, H-J B/S up to
Construction Joint Complete

5. Excavation of HRC D/S site From RD 2+300 to 2+990 is in progress and it is complete in some areas
and some area is remaining because of Hard Rock

6. Excavation of Power House is started