CT - N2 Lifting
Date: From 7-Jan-24 to 11-Jan-24
R-216
Pumping Service
End of Well Report
SOR No./28231
CT - N2 Lifting
OiLTECH
SIU-CTS-ROO-C-60032
Contents
1. EXECUTIVE SUMMARY: ...................................................................................................................3
1.1 HS&E INCIDENTS: ................................................................................................................... 3
1.2 OBJECTIVE: ............................................................................................................................. 3
1.3 WELL HISTORY AND OBJECTIVE: ............................................. Error! Bookmark not defined.
1.4 INTERVENTION OUTCOME: ....................................................................................................3
1.5 MANAGEMENT OF CHANGE / DISPENSATION: ..................................................................... 5
1.6 OTHER SERVICES INVLOVED IN ACHIEVING SOR OBJECTIVES ............................................... 5
2. INTERVENTION INFORMATION: ..................................................................................................... 5
2.1 INTERVENTION DATA: ............................................................................................................5
2.2 DAILY OPERATIONS SUMMARY: ............................................................................................ 6
2.3 Well Schematic: ..................................................................................................................... 7
2.4 BHA DETAILS: .......................................................................... Error! Bookmark not defined.
2.5 CHEMICAL (MATERIAL) CONSUMPTION: .............................................................................10
1. EXECUTIVE SUMMARY:
1.1 HS&E INCIDENTS:
There were zero HSE incidents during this intervention.
1.2 OBJECTIVE:
To put the ceased well back online through flow back and contingency nitrogen lifting via
coiled tubing
Achieved Comments
Objective
(Yes/No) (Why objective not achieved?)
Main Objective Yes
Lifting Yes
Other N/A
8-Jan-24:
- Continued rigging up and conducted the weekly pressure test for BOP (300-5000 Psi) along with the Pull Test
CT Connector (15 K).
- Completed BOP and Pull tests, confirming all systems are in good condition and ready for operations.
Unloaded tubing by initiating CT RIH, started pumping N2 at 2220m with a flow rate of 300 SCFM. Well was
lined up from TBG to FL tanks via SP, with no return at the surface and WHP =50 , Tubing P = 168 psi and
Circulation pressure = 2220 psi
CT reached a depth of 2220m with a pumping rate of 300 SCFM and gradually increase pumping rate to
400scf/m as ROO WSL Coordinator instruction, observing ONLY GAS return at the surface .
While pumping N2 at a rate of 400 SCFM, the coiled tubing (CT) was parked at a depth of 2220m, with the
well lined up from Tubing Head (TBG) to Flow Back (FB) through the Separator. Subsequently, the flow
was diverted from TBG to A Ann, and the N2 rate was increased to 500 SCFM as instructed by the
coordinator.
9-jun-24
pumping N2 at a rate of 500 SCF/min, the coiled tubing was parked at a depth of 2220m, with the well
flowing from A.Ann to FB tanks via the separator. At the surface, the liquid and gas content indicated
an emulsion of 12%, CO2 level of 1.5%, H2S concentration of 1200 ppm, and a liquid rate per hour of
90 bbl.
10-jun-24
On 10th June 2024, coiled tubing (CT) was pulled out of the hole to the surface while pumping N2 at a
rate of 500 SCFM. Liquid and gas were returned during this process. Pumping of N2 was stopped
before reaching the end of the tubing, and the pull-out-of-hole (POOH) operation was continued to
flow back the well.
Upon reaching the surface, instructions were received from the coordinator to divert the well to the
DGS with a chock size of 32/64 .
11-jun-24
Rig Down Instruction and Crew Activity:
Received instruction from ROO WSC to commence rig down the equipment.
OT crew held a TBT with all crew members for flushing and rig down.
- Continue R/D and move to next well
2. INTERVENTION INFORMATION:
2.1 INTERVENTION DATA:
Wellbore Clearance Fish left in hole:
Depth OD: Details of BHA left in hole: Depth OD
HUD 2309.33 m 7”
EOT 2166 m 3.5”
Depth ID:
Restriction 2.66”
Perforating Details
Reservoir Top Bottom Thickness Gun type Gun SPF Double Perfs
size
Mishrif 2247 2301 N/A N/A 1 11/16 4
Stimulation Details
Stimulation Type Fluid type Rate Pressure Comment
NA
Logging Details
Logging Type Bottom Top Interpretation summary (Comment)
Wellhead Pressures
As Found: As Left: Flowing Parameters:
Well Status: Shut-in Shut-in
THP 0 psi 1125 psi Choke size 32/64" S.G water 1.013
A Ann 10 psi 360 psi USP 360 Salinity 90%
140
B Ann 0 psi 0 psi DSP S.G oil N/A
11-Jan-24 Continue Rig up and Pressure Test, CT purge , RIH for N2 lift
12-jan-24 N2 lift operation, POOH to surface, monitor the well , Rig Down