R-426

CT - N2 Lifting
Date: From 23-Mar-24 to 31-Mar-24

R-426
Pumping Service
End of Well Report

SOR No./28980
CT - WELL KILL, WHM AND N2 LIFT

OiLTECH
SIU-CTS-ROO-C-60032

Prepared by: Ali Saeed


WS Final Intervention Report Template
Date: 20-Mar-24 Checked by: Lolav Majeed
ROO- Wells-WS-TEM-167-A0
Approved by: Haroon Allawi
R-426
CT - N2 Lifting
Date: From 23-Mar-24 to 31-Mar-24

Contents
1. EXECUTIVE SUMMARY:.................................................................................................................3
1.1 HS&E INCIDENTS:.................................................................................................................3
1.2 OBJECTIVE:...........................................................................................................................3
1.3 WELL HISTORY AND OBJECTIVE:.............................................Error! Bookmark not defined.
1.4 INTERVENTION OUTCOME:..................................................................................................3
1.5 MANAGEMENT OF CHANGE / DISPENSATION:.....................................................................4
1.6 OTHER SERVICES INVLOVED IN ACHIEVING SOR OBJECTIVES...............................................4
2. INTERVENTION INFORMATION:....................................................................................................4
2.1 INTERVENTION DATA:..........................................................................................................4
2.2 DAILY OPERATIONS SUMMARY:...........................................................................................6
2.3 Well Schematic:....................................................................................................................7
2.4 BHA DETAILS:..........................................................................Error! Bookmark not defined.
2.5 CHEMICAL (MATERIAL) CONSUMPTION:..............................................................................9

Prepared by: Ali Saeed


WS Final Intervention Report Template
Date: 20-Mar-24 Checked by: Lolav Majeed
ROO- Wells-WS-TEM-167-A0
Approved by: Haroon Allawi
R-426
CT - N2 Lifting
Date: From 23-Mar-24 to 31-Mar-24

1. EXECUTIVE SUMMARY:
1.1 HS&E INCIDENTS:
 There were zero HSE incidents during this intervention.

1.2 OBJECTIVE:
The main objectives of the well program are to perform a well kill, install an Autonomous Valve
Lockout (AVLO), conduct Mechanical Integrity Tests (MIT) on the B and C annulus, and utilize
CT/N2 lift to restore the well to production.

 KEY SOR OBJECTIVES:

Achieved Comments
Objective
(Yes/No) (Why objective not achieved?)
Main Objective Yes
Lifting Yes
Other N/A

1.3 INTERVENTION OUTCOME:

 23-Mar-24:
- The Permit to Work (PTW) was printed out, and the team is waiting for the OAA to isolate the well.
OILTECH team also started spotting the EQU , CT unit , MPF , NPF , and the well testing flare less package.
- Completed BOP and Pull tests, confirming all systems are in good condition and ready for operations.

 24-Mar-24:
- OILTECH crew was standby due to bad condition of the location and they waiting civil work

 25-Mar-24

Pressure Testing and Well Status:

- Start Rig Up Injector Head On Wellhead


- Executed High and low pressure tests for all equipment (Flare line, Inlet SP line, DS, US, SSV) for 5
minutes each, following the Standard Operating Procedure (SOP).
- the pressure in the system was bled off, and the N2 unit (200Gal) was cooled down. The line up to the flare
pit for CT purge was performed. The well was then opened and shut-in with specific pressure
conditions: TBG=688 psi, Aann=1630 psi, B=0 psi, C=Zero.
- A line up from TBG to FL tanks via SP was conducted, resulting liquid at the surface. , the main activities
include bleeding off A Annulus and Tubing (TBG) pressures, transitioning to pumping 1.01 SG brine for a
well kill operation via circulation from A Annulus to FB tanks through SEP, returning oil and gas, setting the
choke to 40"/64, followed by pumping 600 bbl of brine as per coordinator instructions. Subsequently,
restarting pumping of 1.01 SG brine for another circulation well kill, and finally, pumping 1.01 SG brine
through A Annulus while closing the choke as directed by the coordinator.

Prepared by: Ali Saeed


WS Final Intervention Report Template
Date: 20-Mar-24 Checked by: Lolav Majeed
ROO- Wells-WS-TEM-167-A0
Approved by: Haroon Allawi
R-426
CT - N2 Lifting
Date: From 23-Mar-24 to 31-Mar-24

 26-Mar-24
the operations involved monitoring TBG and A Annulus pressures, as well as B and C Annulus pressures while
awaiting Well Head Maintenance (WHM) in the early morning to change a valve. After completion of the
maintenance and holding the Tool Box Talk (TBT) with the crew to prepare for rigging up again, the well was
opened with TBG at 362 psi, A Annulus at 70 psi, B Annulus at 0 psi, and C Annulus at 0 psi. MIT was then
conducted on the B Annulus by gradually increasing pressure to 250 psi, observing a pressure drop of 2-3 psi
before completing the test and bleeding off pressure to zero. Subsequently, MIT was performed on the C
Annulus with pressure gradually increased to 50 psi and monitored for 10 minutes, followed by a 30-minute
pressure monitoring where only a 6 psi drop was observed after pumping a total volume of 0.64 bbl. After
completing MIT on both B and C Annulus, the well was reopened with TBG at 525 psi, A Annulus at 116 psi, B
Annulus at 0 psi, and C Annulus at 0 psi, preparing for running in the hole with Coiled Tubing (CT). Continuing to
Run In Hole (RIH) with CT while pumping N2, the well was lined up from TBG to FB via SEP with a choke size of
32"/64, resulting in only gas at the surface. On site, the Coiled Tubing (CT) was parked at a depth of 2150 m
while pumping N2, with the well lined up from Tubing Head (TBG) to Flowback (FB) via the Surface Equipment
Package (SEP) and a choke size of 72"/64". Following the instructions from the Rig Operator Observer (ROO)
coordinator, the flow was switched to the A Annulus.

 27-Mar-24
As per ROO coordinator POOH to surface after that CT at surface Stop pumping N2 , well lined up from TBG to
FB via SEP, choke size 44"/64'' As Per Coordinator instraction shut the well because DGS Team do not accept
pumping Oil to DGS.

 28-Mar-24
The well no flowing got instruction from ROO coordinator pumping the oil in the FBTs to DGS
then 'shut-in the well because DGS Team do not accept pumping Oil to DGS and standby.

 29-Mar-24
Well natural flowing on progress, line up from TBG to FB tanks via separator, Return= oil & gas
Start RIH CT, well line up from TBG to FB tanks via seperator, Return= oil & gas ,start cooldown N2 unit.

 31-Mar-24
'POOH CT to surface while pumping N2, line up from A ann to FB tanks via seperator, Return= Oil and brine
'Well lined up to DGS , choke size 46"/64'' TBG =270 psi WHT= 48C , DSP =182psi A ann= 520 psi B ann
=490ps

 1-Apr-24
Rig Down Instruction and Crew Activity:
 Received instruction from ROO WSC to commence rig down the equipment.
 OT crew held a TBT with all crew members for flushing and rig down.
 - Continue R/D and move to next well

Prepared by: Ali Saeed


WS Final Intervention Report Template
Date: 20-Mar-24 Checked by: Lolav Majeed
ROO- Wells-WS-TEM-167-A0
Approved by: Haroon Allawi
R-426
CT - N2 Lifting
Date: From 23-Mar-24 to 31-Mar-24

1.4 JOB CHART


Well Kill through A ann

Prepared by: Ali Saeed


WS Final Intervention Report Template
Date: 20-Mar-24 Checked by: Lolav Majeed
ROO- Wells-WS-TEM-167-A0
Approved by: Haroon Allawi
R-426
CT - N2 Lifting
Date: From 23-Mar-24 to 31-Mar-24

Well Kill through TGB

Prepared by: Ali Saeed


WS Final Intervention Report Template
Date: 20-Mar-24 Checked by: Lolav Majeed
ROO- Wells-WS-TEM-167-A0
Approved by: Haroon Allawi
R-426
CT - N2 Lifting
Date: From 23-Mar-24 to 31-Mar-24

1.5 MANAGEMENT OF CHANGE / DISPENSATION:

 N/A
1.6 OTHER SERVICES INVLOVED IN ACHIEVING SOR OBJECTIVES
Date Service Service provider Details/Comments

2. INTERVENTION INFORMATION:
2.1 INTERVENTION DATA:
Wellbore Clearance Fish left in hole:
Depth OD: Details of BHA left in hole: Depth OD
HUD 2245.5 m 7”
EOT 2142 m 3.5”
Depth ID:
Restriction 2.99

Zonal Isolation (Cement Squeeze) Details


Reservoir isolated Top Bottom Cement Type Fluid Loss Leak off test result
N/A

Zonal Isolation (Mech Plug/Cement Plug) Details


Reservoir isolated Top Bottom Plug Type Plug depth Plug tagged/ MIT results
N/A

Perforating Details
Reservoir Top Bottom Thickness Gun type Gun SPF Double Perfs
size
Mishrif N/A m N/A N/A N/A

Stimulation Details
Stimulation Type Fluid type Rate Pressure Comment
NA

Logging Details

Prepared by: Ali Saeed


WS Final Intervention Report Template
Date: 20-Mar-24 Checked by: Lolav Majeed
ROO- Wells-WS-TEM-167-A0
Approved by: Haroon Allawi
R-426
CT - N2 Lifting
Date: From 23-Mar-24 to 31-Mar-24

Logging Type Bottom Top Interpretation summary (Comment)

Wellhead Pressures
As Found: As Left: Flowing Parameters:
Well Status: Shut-in Flowing
THP 0 psi 220 psi Choke size 46/64" S.G water 1.013
A Ann 10 psi 520psi USP 220 Salinity 76%
128
B Ann 0 psi 0 psi DSP S.G oil 0.86

C Ann 0 psi 0 psi BSW 15% H2S 0

Well Integrity Details


Integrity items Status:
Xmas tree valves TBG closed, Ann A closed, Ann B & C are closed.
Wellhead valves
MIT Details

2.2 DAILY OPERATIONS SUMMARY:

Date Daily Summary

23-Mar-24 'Waiting for Day light to print out the PTW

24-Mar-24 'standby due to the location muddy and need to civil work.

25-Mar-24 Spot equipment & rig up & pressure test

Continue Rig up and Pressure Test, CT purge . Open the well and it is naturally flow then
26-Mar-24 'Instruction From WSC3 To Start Rigging Down CT and FB Stack

27-Mar-24 'Site visit Form ROO tow personn check all the location and peper work and certaficat

28-Mar-24 'shutted the well because DGS Team do not accept pumping Oil to DGS.

29-Mar-24 'shutted the well because DGS Team do not accept pumping Oil to DGS and standby.

30-Mar-24 'Well natural flowing on progress, line up from TBG to FB tanks via seperator, Return= oil & gas

'POOH CT to surface while pumping N2, line up from A ann to FB tanks via seperator, Return=
31-Mar-24
Oil, brine and gas at surface

Prepared by: Ali Saeed


WS Final Intervention Report Template
Date: 20-Mar-24 Checked by: Lolav Majeed
ROO- Wells-WS-TEM-167-A0
Approved by: Haroon Allawi
R-426
CT - N2 Lifting
Date: From 23-Mar-24 to 31-Mar-24

1-Apr-24 Continue RD and start mobilize the equipment

2.3 Well Schematic:

Prepared by: Ali Saeed


WS Final Intervention Report Template
Date: 20-Mar-24 Checked by: Lolav Majeed
ROO- Wells-WS-TEM-167-A0
Approved by: Haroon Allawi
R-426
CT - N2 Lifting
Date: From 23-Mar-24 to 31-Mar-24

2.4 BHA Details

Prepared by: Ali Saeed


WS Final Intervention Report Template
Date: 20-Mar-24 Checked by: Lolav Majeed
ROO- Wells-WS-TEM-167-A0
Approved by: Haroon Allawi
R-426
CT - N2 Lifting
Date: From 23-Mar-24 to 31-Mar-24

2.5 CHEMICAL (MATERIAL) CONSUMPTION:

N/A