R-171

CT - N2 Lifting
Date: From 01-Mar-24 to 05-Mar-24

R-171
Pumping Service
End of Well Report

SOR No./28001
CT -Stimulation Program

OiLTECH
SIU-CTS-ROO-C-60032

Prepared by: Ali Saeed


WS Final Intervention Report Template
Date: 9-Mar-24 Checked by: Lolav Majeed
ROO- Wells-WS-TEM-167-A0
Approved by: Haroon Allawi
R-171
CT - N2 Lifting
Date: From 01-Mar-24 to 05-Mar-24

Contents
1. EXECUTIVE SUMMARY: ...................................................................................................................3
1.1 HS&E INCIDENTS: ................................................................................................................... 3
1.2 OBJECTIVE: ............................................................................................................................. 3
1.3 WELL HISTORY AND OBJECTIVE: ............................................. Error! Bookmark not defined.
1.4 INTERVENTION OUTCOME: ....................................................................................................3
1.5 MANAGEMENT OF CHANGE / DISPENSATION: ..................................................................... 5
1.6 OTHER SERVICES INVLOVED IN ACHIEVING SOR OBJECTIVES ............................................... 5
2. INTERVENTION INFORMATION: ..................................................................................................... 5
2.1 INTERVENTION DATA: ............................................................................................................5
2.2 DAILY OPERATIONS SUMMARY: ............................................................................................ 6
2.3 Well Schematic: ..................................................................................................................... 6
2.4 BHA DETAILS: .......................................................................... Error! Bookmark not defined.
2.5 CHEMICAL (MATERIAL) CONSUMPTION: ...............................................................................9

Prepared by: Ali Saeed


WS Final Intervention Report Template
Date: 9-Mar-24 Checked by: Lolav Majeed
ROO- Wells-WS-TEM-167-A0
Approved by: Haroon Allawi
R-171
CT - N2 Lifting
Date: From 01-Mar-24 to 05-Mar-24

1. EXECUTIVE SUMMARY:
1.1 HS&E INCIDENTS:
 There were zero HSE incidents during this intervention.

1.2 OBJECTIVE:
Conduct acid perf wash across Mhf4 (2212-2252) mMD, aiming to achieve a jetting pressure of
1500 psi. And Implement N2L to unload the well, with the final setting point for tubing at
120/64".

 KEY SOR OBJECTIVES:

Achieved Comments
Objective
(Yes/No) (Why objective not achieved?)
Main Objective Yes
Lifting Yes
Other N/A

1.3 INTERVENTION OUTCOME:

 01-Mar-24:
- The Permit to Work (PTW) was printed out, and the team is waiting for the OAA to isolate the well. They
also started spotting the EQU , CT unit , MPF , NPF , and the well testing flare less package.

- Continued rigging up and conducted the weekly pressure test for BOP (300-5000 Psi) along with the Pull Test
CT Connector (15 K).
- Completed BOP and Pull tests, confirming all systems are in good condition and ready for operations.
 02-Mar-24:
Pressure Testing and Well Status:

- Executed pressure tests for all equipment (Flare line, Inlet SP line, DS, US, SSV) for 5 minutes each,
following the Standard Operating Procedure (SOP).

 03-Mar-24:

- A series of operations occurred in sequence: the well was opened with specific pressures for TBG Shit, Ann
A, and Ann B; a MIT pressure test at 500 psi for 30 minutes was initiated, and after the test failed, the
pressure was dropped to 26 psi, then Ann A pressure was increased again to 500 psi to complete the MIT;
the CT string volume was displaced by 23 bbl of brine, the well was lined up to the flare pit in preparation
to start CT RIH, CT started RIH while pumping and tagged at a depth of 1561m, the weight was slackened
off from 6k to 2k, followed by the POOH 50m above the tag to straighten the pipe and attempt to pass the
tag again, another attempt to pass the tag was made, and instructions were awaited after stopping
pumping, CT tagged at the same depth, and instructions were received to POOH to the surface, add a
knuckle joint, change the nozzle, and add 2 straight bars.

Prepared by: Ali Saeed


WS Final Intervention Report Template
Date: 9-Mar-24 Checked by: Lolav Majeed
ROO- Wells-WS-TEM-167-A0
Approved by: Haroon Allawi
R-171
CT - N2 Lifting
Date: From 01-Mar-24 to 05-Mar-24

 04-Mar-24:
On March 4, the following operations took place:
- RIH was ongoing, and the well was lined up from TBG to FB tanks with a choke size of 40/64", where only
gas was present at the surface, with a WHT of 30°C, 0 ppm H2S, 0% CO2, and a TL of 90bbl.

- CT was parked at a depth of 2252m and proceeded with perf wash, starting pumping (15%HCl) + 10%MS
through CT, and then lining up the well from TBG to FB tanks with a choke size of 64/64", with no return at
the surface. The acid reached the nozzle, and CT reciprocated the interval from 2252m to 2210m.

- CT reached a depth of 2210m and proceeded to RIH while pumping nitrified Acid N2 at a pumping rate of
300 scf/m. After all the acid was pumped, it was switched to pump brine to displace the acid, and then all
acid was pumped out of the nozzle. Pumping brine was stopped, and the well was POOH to 40m above the
TOP (top of perf.) to kick off the well.

- CT being parked at 40m above TOP, N2 lift ongoing with specific well conditions and choke size, liquid
return at the surface with specific oil and water properties, and an instruction to decrease N2 rate to 300
scf/min.
- Stoped pumping N2 and continue POOH to surface

 05-Mar-24:
Rig Down Instruction and Crew Activity:
 Received instruction from ROO WSC to commence rig down the equipment.
 OT crew held a TBT with all crew members for flushing and rig down.
 - Continue R/D and move to next well

1.4 JOB CHART

Prepared by: Ali Saeed


WS Final Intervention Report Template
Date: 9-Mar-24 Checked by: Lolav Majeed
ROO- Wells-WS-TEM-167-A0
Approved by: Haroon Allawi
R-171
CT - N2 Lifting
Date: From 01-Mar-24 to 05-Mar-24

1.5 MANAGEMENT OF CHANGE / DISPENSATION:


 N/A
1.6 OTHER SERVICES INVLOVED IN ACHIEVING SOR OBJECTIVES
Date Service Service provider Details/Comments

2. INTERVENTION INFORMATION:
2.1 INTERVENTION DATA:
Wellbore Clearance Fish left in hole:
Depth OD: Details of BHA left in hole: Depth OD
HUD 2327 m 7”
EOT 1511.5 m 2.875”
Depth ID:
Restriction 2.44

Zonal Isolation (Cement Squeeze) Details


Reservoir isolated Top Bottom Cement Type Fluid Loss Leak off test result
N/A

Zonal Isolation (Mech Plug/Cement Plug) Details


Reservoir isolated Top Bottom Plug Type Plug depth Plug tagged/ MIT results
N/A

Perforating Details
Reservoir Top Bottom Thickness Gun type Gun SPF Double Perfs
size
Mishrif 2212 m 2325 N/A N/A

Stimulation Details
Stimulation Type Fluid type Rate Pressure Comment
Acid Stimulation (15%HCl) +10%MS) 1 bpm

Logging Details
Logging Type Bottom Top Interpretation summary (Comment)

Prepared by: Ali Saeed


WS Final Intervention Report Template
Date: 9-Mar-24 Checked by: Lolav Majeed
ROO- Wells-WS-TEM-167-A0
Approved by: Haroon Allawi
R-171
CT - N2 Lifting
Date: From 01-Mar-24 to 05-Mar-24

Wellhead Pressures
As Found: As Left: Flowing Parameters:
Well Status: Shut-in Flowing
THP 660 psi 342psi Choke size 52/64" S.G water 1.013
A Ann 85 psi 1315 psi USP 324 Salinity 4%
292
B Ann 0 psi 0 psi DSP S.G oil 0.883

C Ann 0 psi 0 psi BSW 1% H2S 0

Well Integrity Details


Integrity items Status:
Xmas tree valves TBG closed, Ann A closed, Ann B & C are closed.
Wellhead valves
MIT Details

2.2 DAILY OPERATIONS SUMMARY:

Date Daily Summary

1-Mar-24 Spot equipment & rig up & pressure test

2-Mar-24 Continue Rig up and Pressure Test, CT purge , RIH for N2 lift

The well was opened with specific pressures


3-Mar-24
MIT pressure test at 500 psi for 30 minutes was initiated.
CT parked at a depth of 2252m and performed perf wash
4-Mar-24
CT reciprocated the interval from 2252m to 2210m

5-Mar-24 Rig Down and start mobilize the equipment then PTW closed

Prepared by: Ali Saeed


WS Final Intervention Report Template
Date: 9-Mar-24 Checked by: Lolav Majeed
ROO- Wells-WS-TEM-167-A0
Approved by: Haroon Allawi
R-171
CT - N2 Lifting
Date: From 01-Mar-24 to 05-Mar-24

2.3 Well Schematic:

Prepared by: Ali Saeed


WS Final Intervention Report Template
Date: 9-Mar-24 Checked by: Lolav Majeed
ROO- Wells-WS-TEM-167-A0
Approved by: Haroon Allawi
R-171
CT - N2 Lifting
Date: From 01-Mar-24 to 05-Mar-24

2.4 BHA Details

Prepared by: Ali Saeed


WS Final Intervention Report Template
Date: 9-Mar-24 Checked by: Lolav Majeed
ROO- Wells-WS-TEM-167-A0
Approved by: Haroon Allawi
R-171
CT - N2 Lifting
Date: From 01-Mar-24 to 05-Mar-24

2.5 CHEMICAL (MATERIAL) CONSUMPTION:

Prepared by: Ali Saeed


WS Final Intervention Report Template
Date: 9-Mar-24 Checked by: Lolav Majeed
ROO- Wells-WS-TEM-167-A0
Approved by: Haroon Allawi