R-760

CT - N2 Lifting
Date: From 30-Mar-24 to 01-Apr-24

R-760
Pumping Service
End of Well Report

SOR No./29077
CT -Stimulation Program

OiLTECH
SIU-CTS-ROO-C-60032

Prepared by: Ali Saeed


WS Final Intervention Report Template
Date: 4-Apri-24 Checked by: Lolav Majeed
ROO- Wells-WS-TEM-167-A0
Approved by: Haroon Allawi
R-760
CT - N2 Lifting
Date: From 30-Mar-24 to 01-Apr-24

Contents
1. EXECUTIVE SUMMARY:.................................................................................................................3
1.1 HS&E INCIDENTS:.................................................................................................................3
1.2 OBJECTIVE:...........................................................................................................................3
1.3 WELL HISTORY AND OBJECTIVE:.............................................Error! Bookmark not defined.
1.4 INTERVENTION OUTCOME:..................................................................................................3
1.5 MANAGEMENT OF CHANGE / DISPENSATION:.....................................................................5
1.6 OTHER SERVICES INVLOVED IN ACHIEVING SOR OBJECTIVES...............................................5
2. INTERVENTION INFORMATION:....................................................................................................5
2.1 INTERVENTION DATA:..........................................................................................................5
2.2 DAILY OPERATIONS SUMMARY:...........................................................................................6
2.3 Well Schematic:....................................................................................................................7
2.4 BHA DETAILS:..........................................................................Error! Bookmark not defined.
2.5 CHEMICAL (MATERIAL) CONSUMPTION:............................................................................10

Prepared by: Ali Saeed


WS Final Intervention Report Template
Date: 4-Apri-24 Checked by: Lolav Majeed
ROO- Wells-WS-TEM-167-A0
Approved by: Haroon Allawi
R-760
CT - N2 Lifting
Date: From 30-Mar-24 to 01-Apr-24

1. EXECUTIVE SUMMARY:
1.1 HS&E INCIDENTS:
 There were zero HSE incidents during this intervention.

1.2 OBJECTIVE:
The program aims to improve the injectivity of Dammam wells by stimulating the open hole
using an HCl acid system to dissolve and bypass any damage present.

 KEY SOR OBJECTIVES:

Achieved Comments
Objective
(Yes/No) (Why objective not achieved?)
Main Objective Yes
Lifting N/A
Other N/A

1.3 INTERVENTION OUTCOME:

 30-Mar-24:
- The Permit to Work (PTW) was printed out, and the team is waiting for the OAA to isolate the well. They
also started spotting the EQU , CT unit , Flow back requirements .

- Continued rigging up and conducted the weekly pressure test for BOP (LP 300- HP 5000 Psi) along with the
Pull Test CT Connector (16 K).
- Completed BOP and Pull tests, confirming all systems are in good condition and ready for operations.
 31-Mar-24:

Pressure Testing and Well Status:

- Executed pressure tests for all equipment ( Inlet FB line, DS, US, SSV) for 5 minutes each, following
the Standard Operating Procedure (SOP).

Open the well


- A series of operations occurred in sequence: the well was opened with specific pressures for TBG Shit, A,
and Ann B; conduct a Pre-injectivity test after holding a TBT session with the crew, followed by opening the
well, recording shut-in pressures, performing the Pre-job Injectivity test at specific rates and pressures,
completing the test successfully, and initiating CT (coiled tubing) RIH operations to tag the HUD with
pumping Brine at specific depths while ensuring proper CT handling procedures were followed. CT was
tagged at 815 meters HUD, raised by 1meter, and flagged before repeating the process.
Following these steps, pumping of brine and a 10% Mud Solvent (MS) mixture commenced once the nozzle
start stage was reached. Pumping was stopped after completion, and the CT was pulled out of the hole to
the surface at a maximum rate of 2.3 bpm. Subsequently, the CT was held to allow for soaking time before
starting the injectivity test. After the completion of the injectivity test, CT was run in the hole to 1 meter
above the HUD depth (814 meters) with brine pumped at a minimum rate. Once the CT reached the target

Prepared by: Ali Saeed


WS Final Intervention Report Template
Date: 4-Apri-24 Checked by: Lolav Majeed
ROO- Wells-WS-TEM-167-A0
Approved by: Haroon Allawi
R-760
CT - N2 Lifting
Date: From 30-Mar-24 to 01-Apr-24

depth, acid (15% Hydrochloride Acid + 10% Mutual Solvent) was pumped to pass through the depth
interval.The pumping of acid was completed, followed by displacing the acid with brine at 1.5 times the CT
volume. The process involved maintaining specific parameters such as a maximum pumping rate of 2.3
bpm, a total volume of 250 barrels, TBG at 93 psi, A Ann at 64 psi, and a maximum circulating pressure of
4880 psi. Finally, the CT was pulled out of the hole, brought to the surface, and left to soak before further
operations. Finally preform post-injecttivity test.

 1-Apr-24:
Rig Down Instruction and Crew Activity:
 Received instruction from ROO WSC to commence rig down the equipment.
 OT crew held a TBT with all crew members for flushing and rig down.
 Continue R/D and move to next well

Prepared by: Ali Saeed


WS Final Intervention Report Template
Date: 4-Apri-24 Checked by: Lolav Majeed
ROO- Wells-WS-TEM-167-A0
Approved by: Haroon Allawi
R-760
CT - N2 Lifting
Date: From 30-Mar-24 to 01-Apr-24

1.4 JOB CHART

1.5 MANAGEMENT OF CHANGE / DISPENSATION:

 N/A
1.6 OTHER SERVICES INVLOVED IN ACHIEVING SOR OBJECTIVES
Date Service Service provider Details/Comments

2. INTERVENTION INFORMATION:
2.1 INTERVENTION DATA:
Wellbore Clearance Fish left in hole:
Depth OD: Details of BHA left in hole: Depth OD
HUD 2327 m 7”
EOT 1511.5 m 2.875”
Depth ID:
Restriction 2.44

Zonal Isolation (Cement Squeeze) Details


Reservoir isolated Top Bottom Cement Type Fluid Loss Leak off test result
N/A

Zonal Isolation (Mech Plug/Cement Plug) Details

Prepared by: Ali Saeed


WS Final Intervention Report Template
Date: 4-Apri-24 Checked by: Lolav Majeed
ROO- Wells-WS-TEM-167-A0
Approved by: Haroon Allawi
R-760
CT - N2 Lifting
Date: From 30-Mar-24 to 01-Apr-24

Reservoir isolated Top Bottom Plug Type Plug depth Plug tagged/ MIT results
N/A

Perforating Details
Reservoir Top Bottom Thickness Gun type Gun SPF Double Perfs
size
Mishrif 2212 m 2325 N/A N/A

Stimulation Details
Stimulation Type Fluid type Rate Pressure Comment
Acid Stimulation (15%HCl) +10%MS) 1 bpm

Logging Details
Logging Type Bottom Top Interpretation summary (Comment)

Wellhead Pressures
As Found: As Left: Flowing Parameters:
Well Status: Shut-in Flowing
THP 25 psi 85psi Choke size N/A S.G water N/A
A Ann 180 psi 100 psi USP N/A Salinity N/A
N/A
B Ann N/A 0 psi DSP S.G oil --

C Ann N/A 0 psi BSW N/A H2S --

Well Integrity Details


Integrity items Status:
Xmas tree valves TBG closed, Ann A closed, Ann B & C are closed.
Wellhead valves
MIT Details

2.2 DAILY OPERATIONS SUMMARY:

Date Daily Summary

Prepared by: Ali Saeed


WS Final Intervention Report Template
Date: 4-Apri-24 Checked by: Lolav Majeed
ROO- Wells-WS-TEM-167-A0
Approved by: Haroon Allawi
R-760
CT - N2 Lifting
Date: From 30-Mar-24 to 01-Apr-24

1-Mar-24 Spot equipment & rig up & pressure test

2-Mar-24 Continue Rig up and Pressure Test, CT purge , RIH for acid pumping

The well was opened with specific pressures and total acid volume was pumped
3-Mar-24
Rig Down and start mobilize the equipment then PTW closed

Prepared by: Ali Saeed


WS Final Intervention Report Template
Date: 4-Apri-24 Checked by: Lolav Majeed
ROO- Wells-WS-TEM-167-A0
Approved by: Haroon Allawi
R-760
CT - N2 Lifting
Date: From 30-Mar-24 to 01-Apr-24

2.3 Well Schematic:

Prepared by: Ali Saeed


WS Final Intervention Report Template
Date: 4-Apri-24 Checked by: Lolav Majeed
ROO- Wells-WS-TEM-167-A0
Approved by: Haroon Allawi
R-760
CT - N2 Lifting
Date: From 30-Mar-24 to 01-Apr-24

2.4 BHA Details

Prepared by: Ali Saeed


WS Final Intervention Report Template
Date: 4-Apri-24 Checked by: Lolav Majeed
ROO- Wells-WS-TEM-167-A0
Approved by: Haroon Allawi
R-760
CT - N2 Lifting
Date: From 30-Mar-24 to 01-Apr-24

2.5 CHEMICAL (MATERIAL) CONSUMPTION:

Prepared by: Ali Saeed


WS Final Intervention Report Template
Date: 4-Apri-24 Checked by: Lolav Majeed
ROO- Wells-WS-TEM-167-A0
Approved by: Haroon Allawi