Professional Documents
Culture Documents
CT - N2 Lifting
Date: From 9-Mar-24 to 12-Mar-24
RU-357
Pumping Service
End of Well Report
SOR No./29131
CT - N2 Lifting
OiLTECH
SIU-CTS-ROO-C-60032
Contents
1. EXECUTIVE SUMMARY:.................................................................................................................3
1.1 HS&E INCIDENTS:.................................................................................................................3
1.2 OBJECTIVE:...........................................................................................................................3
1.3 WELL HISTORY AND OBJECTIVE:.............................................Error! Bookmark not defined.
1.4 INTERVENTION OUTCOME:..................................................................................................3
1.5 MANAGEMENT OF CHANGE / DISPENSATION:.....................................................................5
1.6 OTHER SERVICES INVLOVED IN ACHIEVING SOR OBJECTIVES...............................................5
2. INTERVENTION INFORMATION:....................................................................................................5
2.1 INTERVENTION DATA:..........................................................................................................5
2.2 DAILY OPERATIONS SUMMARY:...........................................................................................6
2.3 Well Schematic:....................................................................................................................7
2.4 BHA DETAILS:..........................................................................Error! Bookmark not defined.
2.5 CHEMICAL (MATERIAL) CONSUMPTION:............................................................................10
1. EXECUTIVE SUMMARY:
1.1 HS&E INCIDENTS:
There were zero HSE incidents during this intervention.
1.2 OBJECTIVE:
The objective of the final Well program is to regain production of ceased Producers by initiating
the well through a coiled tubing Nitrogen lift.
Achieved Comments
Objective
(Yes/No) (Why objective not achieved?)
Main Objective Yes
Lifting Yes
Other N/A
- - PTW not Approved Due To SC not Available In Station and OT team relocated to the site, and all
Equipment Arrived to the new location.OILTECH team waiting for Day light to print out the PTW.
10-Mar-24:
- The Permit to Work (PTW) was printed out, and the team is waiting for the OAA to isolate the well.
OILTECH team also started spotting the EQU , CT unit , MPF , NPF , and the well testing flare less package.
- Completed BOP and Pull tests, confirming all systems are in good condition and ready for operations.
11-Mar-24
- the pressure in the system was bled off, and the N2 unit (200Gal) was cooled down. The line up to the flare
pit for CT purge was performed. The well was then opened and shut-in with specific pressure
conditions: TBG=400 psi, Aann=900 psi, B=0 psi, C=Zero.
- A line up from TBG to FL tanks via SP was conducted, resulting liquid at the surface. RIH process was not
initiated because the well naturally flow . The return oil at the surface, with a choke size of 64/64”, BSW of
1%, emulsion, and a density of 0.880 @ 27C.
- Upon receiving instructions from the ROO WSL coordinator to divert flow to DGS,, followed by lining up the
well from TBG to DGS with a choke size of 64/64", and preparing to start rig-down to the equipment
12-Mar-24
Rig Down Instruction and Crew Activity:
Received instruction from ROO WSC to commence rig down the equipment.
OT crew held a TBT with all crew members for flushing and rig down.
- Continue R/D and move to next well
N/A
1.6 OTHER SERVICES INVLOVED IN ACHIEVING SOR OBJECTIVES
Date Service Service provider Details/Comments
2. INTERVENTION INFORMATION:
2.1 INTERVENTION DATA:
Wellbore Clearance Fish left in hole:
Depth OD: Details of BHA left in hole: Depth OD
HUD 2394 m 7”
EOT 2278 m 3.5”
Depth ID:
Restriction 2.99
Perforating Details
Reservoir Top Bottom Thickness Gun type Gun SPF Double Perfs
size
Mishrif 2332 m 2344 N/A N/A
Stimulation Details
Stimulation Type Fluid type Rate Pressure Comment
NA
Logging Details
Logging Type Bottom Top Interpretation summary (Comment)
Wellhead Pressures
As Found: As Left: Flowing Parameters:
Well Status: Shut-in Shut-in
THP 0 psi 1125 psi Choke size 32/64" S.G water 1.013
A Ann 10 psi 360 psi USP 360 Salinity 90%
140
B Ann 0 psi 0 psi DSP S.G oil N/A
Continue Rig up and Pressure Test, CT purge . Open the well and it is naturally flow then
11-Mar-24
'Instruction From WSC3 To Start Rigging Down CT and FB Stack