You are on page 1of 17

` NASSER S AL HAJRI CORPORATION

SAUDI ARAMCO ONSHORE MAINTAIN POTENTIAL PROGRAM- NA1A


CONTRACT # 6600033948
NSH-SAOMPP-CMS-PI-008 METHOD STATEMENT FOR PAINTING & COATING
Rev-00 Date: 22 FEB. 2015

CATEGORY QUALITY CONSTRUCTION PROCEDURE

TITLE METHOD STATEMENT FOR PAINTING & COATING

DOCUMENT REFERENCE NSH-SAOMPP-CMS-PI-008

TABLE OF CONTENTS

1.0 SCOPE

2.0 PURPOSE

3.0 REFERENCES

4.0 DEFINITION

5.0 RESPONSIBILITIES

6.0 PROCEDURE

7.0 DOCUMENTATION

8.0 SAFETY ACTION PLAN

0 22/02/2015 For Approval Harikumar Yohannan Chacko Bobby Paul


Revision Date Description Prepared By Reviewed By Approved By
REVISION HISTORY

Copies with no seal are Uncontrolled copies. Page 1 of 17


` NASSER S AL HAJRI CORPORATION
SAUDI ARAMCO ONSHORE MAINTAIN POTENTIAL PROGRAM- NA1A
CONTRACT # 6600033948
NSH-SAOMPP-CMS-PI-008 METHOD STATEMENT FOR PAINTING & COATING
Rev-00 Date: 22 FEB. 2015

1.0 SCOPE:

1.1 The scope of this procedure is to provide a systematic method of performing


Surface Preparation and Painting works.

1.2 To ensure that all required inspection and tests have been performed during
construction and the work complies with all project specification and drawing
requirements.

2.0 PURPOSE:

2.1 This procedure applies for all Surface Preparation and Painting works to be
carried out by NSH and its sub-contractors.

3.0 REFERENCES:

3.1 The following documents are referenced.


SAES-H-001 Coating Selection and Application Requirements for
Industrial Plants and Equipment
SAES-H-002 Internal and external coating of steel pipelines and piping
SAES-H-101V Approved Saudi Aramco Data Sheets - Paints and
Coatings
SAES-H-002 V Approved Saudi Aramco Data Sheets for the Pipeline and
Piping Coatings
SAES-H-102 Safety Requirements for Coating Applications
SAEP-316 Qualifications of coating personnel
SAES-L-350 Construction of Plant Piping
SAES-L-450 Construction of On-Land and Near-Shore Pipelines

SAUDI ARAMCO TYPICAL INSPECTION PLAN


SATIP-H-100-01 Paint Application of Liquid Coating System for Industrial
Facilities
SATIP-L-450-04 Cross Country Buried Pipeline

Copies with no seal are Uncontrolled copies. Page 2 of 17


` NASSER S AL HAJRI CORPORATION
SAUDI ARAMCO ONSHORE MAINTAIN POTENTIAL PROGRAM- NA1A
CONTRACT # 6600033948
NSH-SAOMPP-CMS-PI-008 METHOD STATEMENT FOR PAINTING & COATING
Rev-00 Date: 22 FEB. 2015

4.0 DEFINITIONS
SAOMPP - Saudi Aramco Onshore Maintain potential Program.
NSH - Nasser S. Al-Hajri Corporation
Subcontractor - Authorized enterprise to carryout construction
activities on behalf of Contractor)
Supplier (or Vendor) - Any person, firm, partnership, company corporation or
combination thereof with which the BUYER has sent
the QUOTATION REQUEST or placed the
PURCHASEORDER.
Supply - All material, equipment and services to be provided
whether. Expressly or by implication under the
PURCHASE ORDER.
FBE - Fusion Bond Epoxy.
APCS - Aramco Paint and Coating Specification.

5.0 RESPONSIBILITIES:

5.1 Project Manager

Project Manager shall be responsible for the overall implementation of the


company safety & Quality plan and ensure efficient execution of works in
accordance with project specifications.

5.2 Site Construction Manager

Site Construction Manager is responsible for all construction related piping


activities including fabrication accordance with the specified Engineering
Design; Standard, in order to coordinate with all discipline’s activities for comply
with the Specified Project Requirements including safety & Quality. Site
Construction Manager will report to Project Manager.

5.3 QA/QC Manager

QA/QC Manager is responsible for the implementation of all required


construction works and Assured on Quality, in order to meet the project
requirement including Fabrication accordance with the project specified

Copies with no seal are Uncontrolled copies. Page 3 of 17


` NASSER S AL HAJRI CORPORATION
SAUDI ARAMCO ONSHORE MAINTAIN POTENTIAL PROGRAM- NA1A
CONTRACT # 6600033948
NSH-SAOMPP-CMS-PI-008 METHOD STATEMENT FOR PAINTING & COATING
Rev-00 Date: 22 FEB. 2015

engineering & Standards etc. and to control for the specified Piping activities
including test and inspection etc. for this particular job. He will coordinate will all
discipline heads for this related activity & report to General Manager.

5.4 Piping Manager

The Piping Manager is responsible for the total piping fabrication works as per
the project related approved documents at site/shop and plan for the weekly
work schedule and controlling for all the piping works comply with the project
requirement including safety & Quality . He will report to Site Construction
Manager.

5.5 Piping Superintendent

The Piping Superintendent coordinates with personnel at Shop & Site to Plan for
the fabrication of daily, weekly piping works as per baseline schedule, and
allocates the job to the concerned supervisors, and control the piping works
including daily monitoring etc. in all the areas accordance with safety, Quality
and Productivity respectively. He will report to Piping Manager.

5.6 QC Engineer

The QC Engineer will be responsible for the necessary inspections and tests at
shop and specified place and to be carried out for all the activities involved in
the above ground piping fabrication works as per the specified Inspection & Test
Plan (ITP). He will report to QA/QC Manager.

5.7 Piping Inspector

Piping Inspector is responsible to inspect all the piping materials related the
specified areas he will do the dimension check, Grade, etc. as per IFC prior to
fabrication. He will inspect the beveled ends and giving clearance for fit-up etc.
He is also responsible for Calibration of all testing instruments/machineries and
using necessary precision tools etc. to meet accordance with the Quality on
specified piping works He will report to QA/QC Manager.

Copies with no seal are Uncontrolled copies. Page 4 of 17


` NASSER S AL HAJRI CORPORATION
SAUDI ARAMCO ONSHORE MAINTAIN POTENTIAL PROGRAM- NA1A
CONTRACT # 6600033948
NSH-SAOMPP-CMS-PI-008 METHOD STATEMENT FOR PAINTING & COATING
Rev-00 Date: 22 FEB. 2015

5.8 Welding Inspector

The Welding Inspector inspects the joint after fit-up and gives clearance for
welding. Once welding is completed, visual inspection will be done and non-
destructive inspection shall be carried out as required by the specification. The
welding report shall be prepared by QC Inspector and submitted to SAOMPP.
He will report to QA/QC Manager.

5.9 Site Supervisor

The Site Supervisor will be directly involved in the planning and execution of the
activities involved in the fabrication works. He will be responsible for the
preparation of fabrication plan, Safety Action Plan, Safe Work Plan and work
permits if required prior to commence of any activities. He should raise Request
for Inspection (RFI's) to the QC dept. at appropriate stages of the work as
detailed in the ITP. He will report to piping Manager.

5.10 Foreman

The Piping Foreman will be responsible for the direct execution of works
involved in the fabrication process according to the plan and will directly control
and issue instructions to the working personnel. He will provide written
instructions to welders by issuing "Welding Instruction Sheets" that cover the
fundamental requirements of the Welding Procedure Specification (WPS). He
will also ensure that works are performed with proper tools/equipment and good
housekeeping around the working area. He will report to Piping Manager.

5.11 Safety Manager / Supervisor

Safety Manager / Supervisor will make sure that all the safety requirements are
fulfilled prior to start of the job. Job Safety Analysis/Safety Task Assignments
will be strictly implemented by daily basis in order to avoid any loss of time.

5.12 Planning Department


Planning dept. will receive all the drawings from Document Controller and the
same will be kept updating as per the latest revisions. Weld maps will be
prepared. As per the latest drawings, Bill of Materials & Material Take Off
(BOM/MTO) will be prepared which will be forwarded to materials department

Copies with no seal are Uncontrolled copies. Page 5 of 17


` NASSER S AL HAJRI CORPORATION
SAUDI ARAMCO ONSHORE MAINTAIN POTENTIAL PROGRAM- NA1A
CONTRACT # 6600033948
NSH-SAOMPP-CMS-PI-008 METHOD STATEMENT FOR PAINTING & COATING
Rev-00 Date: 22 FEB. 2015

prior to Make PR etc. Preparation of weekly, monthly and overall schedule will
be done and the same will be monitored on daily basis accordance with the
baseline schedule and will monitor the daily/weekly/monthly delay concern etc.
he will report to Site Construction Manager & Project Manager.
5.13 Materials Department

The materials Dept. is responsible for shifting all materials from store yard to
fabrication yard as per material requisition made by fabrication supervisor. Also
the fabrication completed spools shifted to erection site. All the documents and
records in connection with materials shall be maintained for traceability. Records
will be made as per isometrics for material shifting and an updated status of
materials stock and transfer to site will be done on daily basis. Material
department will report to Material Manager.

6.0 PROCEDURE

All fabricated A/G Piping work shall be prepared, primed and painted in accordance with
SAES-H-001.

Guard-rails shall be painted with APCS-22 in accordance with SAES-H-101V, in yellow


and black bands (150 mm alternating).

All below grade surfaces except the bottom one, on all concrete foundation, buried
concrete thrust anchors and pipe supports shall be coated in accordance with APCS-10
to an elevation of 300 mm above finish grade.

All kilometer marker posts shall be painted yellow in accordance with SAES-H-101V &
APCS-22.

All welded structure shall be grit blasted using abrasive grit to obtain minimum
cleanliness and surface profile requirements as per the paint data sheet. Abrasive used
shall be dry and free of contaminants.

External FBE coat, sections of Pipeline 8 meter beyond the point of exit from the ground
if the exit angle is 45 degree or less and for camel/road crossings and 1 meter beyond
the point of exit from ground if the exit angle is 46 degree or more.

Copies with no seal are Uncontrolled copies. Page 6 of 17


` NASSER S AL HAJRI CORPORATION
SAUDI ARAMCO ONSHORE MAINTAIN POTENTIAL PROGRAM- NA1A
CONTRACT # 6600033948
NSH-SAOMPP-CMS-PI-008 METHOD STATEMENT FOR PAINTING & COATING
Rev-00 Date: 22 FEB. 2015

Anchor bolts shall be painted with APCS-1C or shall be galvanized. The paint shall be
applied up to the bottom of the thread.

Abrasive blasting shall be carried out only when the steel is at least 3 deg. C above dew
Point.

6.1 General Requirements for External Coating

6.1.1 All buried onshore pipes shall be externally coated.


6.1.2 Pipes in all subsea services shall be externally coated.
6.1.3 Plant piping and other above grade pipelines in industrial or marine
exposure shall be externally coated.
6.1.4 All onshore buried and subsea coated pipes shall be 100% holiday free
and all holidays shall be repaired prior to burial. If the pipe is bent, it
should be holiday tested again to determine any damage to the coating
during bending.
6.1.5 All transition areas (buried to above ground pipe sections, including
camel and road crossings) shall be protected with the buried service
coating and supplemented with an approved protective laminate/
Wrapping system. This system shall start at least 1m below ground and
extend above ground as follows:
a) For sharp angles (46 to 90 degrees), the laminate coating shall
extend at least 1 m above ground.
b) For shallow angles (45 degrees or less), the laminate coating
shall extend at least 8 m above ground. If a support on an
existing pipe is encountered at a distance less than 8 m along the
pipe, and it cannot be removed, the laminate coating shall
terminate at the support. In-active sand control, pipeline coating
may stop at the first weld, provided that the pipe is 3-pipe
diameter above the grade level where the plant coating will take
over. (Above-ground portions of APCS-105 and APCS-115 must
be protected from direct sunlight. See the APCSs for details.)
6.1.6 Hand-applied tapes of all types shall not be used except for the PVC
outer wrap of APCS-113C.

Copies with no seal are Uncontrolled copies. Page 7 of 17


` NASSER S AL HAJRI CORPORATION
SAUDI ARAMCO ONSHORE MAINTAIN POTENTIAL PROGRAM- NA1A
CONTRACT # 6600033948
NSH-SAOMPP-CMS-PI-008 METHOD STATEMENT FOR PAINTING & COATING
Rev-00 Date: 22 FEB. 2015

6.1.7 The APCS-113C can also be used over an existing coating that is
sound and has good adhesion on the steel substrate. This procedure is
normally applicable on isolated steel valves, spools and fittings that are
not protected with either cathodic protection or galvanic anode.
6.1.8 Ditch preparation and sand padding requirements for onshore buried
pipe are given in SAES-L-350 and SAES-L-450.
6.1.9 At road crossings, the minimum allowable surface preparation prior to
coating shall be near white metal Sa 2.5 except for APCS-113C.
6.1.10 Cast iron pipe that has been shop-coated with enamel (or similar) does
not require additional external coating prior to burial. Bare cast iron pipe
shall be externally coated prior to burial.
6.1.11 Buried stainless steel lines shall be externally coated with halide-free
liquid coating or visco-elastic coating APCS-113C depending on
operating temperature.
6.1.12 Pipes to be thrust bored shall be coated with APCS-104A or APCS-
104B first layer and APCS-113A top layer. For open cut excavation,
APCS-113C can be used over APCS-104A or APCS-104B.
6.1.13 When external coating is required, the selection table given in
paragraph 5.4 & 5.6 of SAES-H-002 shall be used.
6.1.14 Coating systems listed in paragraphs 5.4 through 5.6 of SAES-H-002
shall not be used under conditions that violate service limitations or
other requirements given in the applicable APCS data sheets. Only
approved products shall be used.
6.1.15 Preheating pipe prior to FBE coating application on the internal girth
welds shall be done by heat induction coils only.
6.1.16 Wellhead components shall be coated in accordance to SAES-H-001
and SAES-H-004.

6.2 General Requirements for Internal Coatings

6.2.1 Internal coating is required when there is a potential problem with


corrosion that could have an impact in the process such as for water,

Copies with no seal are Uncontrolled copies. Page 8 of 17


` NASSER S AL HAJRI CORPORATION
SAUDI ARAMCO ONSHORE MAINTAIN POTENTIAL PROGRAM- NA1A
CONTRACT # 6600033948
NSH-SAOMPP-CMS-PI-008 METHOD STATEMENT FOR PAINTING & COATING
Rev-00 Date: 22 FEB. 2015

gas, condensate and crude oil. When internal coating is required, the
selection table given in paragraph 5.3 of SAES-H-002 shall be used.
6.2.2 Internal coatings used in potable water service must meet Food and
Drugs Administration (FDA), National Sanitation Foundation (NSF) or
equivalent requirements for suitability for use in contact with drinking
water. The certificate shall be renewed every 24 months.
6.2.3 Application of phenolic primer prior to the application of FBE shall not
be controlled manually. A machine shall be used to ensure that the
travel of application is constant and that the DFT will not exceed one mil
(25 microns) in all areas. One mil is exceeded if the “peaks” of steel
substrate are no longer visible.
6.2.4 For onshore application, the robotic crawler machine (consisting of
blasting and coating equipment, dry film thickness gauge and holiday
detector) shall be used for internal field girth welds of pipe strings with
diameters ranging from 8 to 36". If isotope is used as the girth weld
locator, it should be backed up with a video camera for real time
inspection to ensure that blast cleaning and coating application are
done in the girth weld area. For pipe diameters larger than 36", the
coating application can be done manually by qualified contractors with
the approval of CSD/Coatings Team.
6.2.5 In the offshore, a semi-robotic system shall be used in the application of
specialty liquid coating on internal girth welds by qualified and
experienced contractors. This is applicable for sub-sea pipelines with
diameters ranging from 8" and above.
6.2.6 For sour gas and Wasia water services, field application of FBE shall
not be used for internal protection of girth welds for both onshore and
offshore pipelines.
6.2.7 All Blasting and Coating Personnel shall be certified by SAUDI
ARAMCO in accordance with the requirements of SAEP-316

Copies with no seal are Uncontrolled copies. Page 9 of 17


` NASSER S AL HAJRI CORPORATION
SAUDI ARAMCO ONSHORE MAINTAIN POTENTIAL PROGRAM- NA1A
CONTRACT # 6600033948
NSH-SAOMPP-CMS-PI-008 METHOD STATEMENT FOR PAINTING & COATING
Rev-00 Date: 22 FEB. 2015

6.3 The painting QC Inspector will be using the following instruments to


control the paint process:

 Anchor pattern measurement device


 Wet film thickness gauge
 Dry film thickness gauge
 Thermometer for air temperature
 Humidity gauge
 Contact thermometer for metal temperature
 Sharp Knife

All these instrument shall be duly calibrated

The work will be coordinated with the coating Inspector who will initiate each step
of the painting process.

6.4 Quality Control Records

5.4.1 Quality Control Equipment Check Sheet (SATR-H-2004)

This form shall be completed prior to job start-up. It shall be completed


and signed by the coating contractor supervisor and then signed by the
SAUDI ARAMCO Inspector. No work is allowed until this form is
completed.

5.4.2 Daily Job Log

The coating contractor supervisor shall fill out a log, on a daily basis,
recording all problem areas, delays, non-compliances, and corrective
actions taken for SAUDI ARMCO inspector witnessing and
surveillance.

5.4.3 In-process Inspection Sheet (SATR-H-2006)

This form shall be completed and signed every work-day by the


contractor supervisor. The SAUDI ARAMCO inspector shall initial each
item marked with an asterisk before work is allowed to begin on
subsequent items.
Copies with no seal are Uncontrolled copies. Page 10 of 17
` NASSER S AL HAJRI CORPORATION
SAUDI ARAMCO ONSHORE MAINTAIN POTENTIAL PROGRAM- NA1A
CONTRACT # 6600033948
NSH-SAOMPP-CMS-PI-008 METHOD STATEMENT FOR PAINTING & COATING
Rev-00 Date: 22 FEB. 2015

5.4.4 Coatings and Equipment Log

This form shall be completed and signed by the coating contractor


supervisor and verified and signed by the SAUDI ARAMCO inspector.

5.4.5 Final Acceptance Report

The final acceptance report shall include the 4 quality control


documents described above.

In addition, Quality Control Daily Check List mentioned in Attachment A of SAES-


H-001 shall be completed prior to job start-up. It shall be completed and signed
by the coating contractor supervisor and then signed by the SAUDI ARAMCO
Inspector.

Prior to blasting, rough welds and cut-off shall be ground to small radius and
weld spatter shall be removed by grinding or chipping.

Compressed air supply shall be free of oil, moisture and contamination. This shall
be checked by QC Inspector by holding blotter paper attached to clip board
approximately 45-60 cm. In front of blast nozzle during air flow only with nozzle
pressure of 50 PSIG for approximately 1minute.

The result will be considered acceptable if no water or oil contamination on the


blotter. This test shall be done every day prior start of blasting and midpoint of
each 8 hours period.

After blasting abrasive, materials shall be removed from cleaned external surface
by dry brushing or blowing down with clean dry compressed air.

Abrasive cleaned surface shall be primed before the surface condition degrades
below the specified cleanliness level.

Paint and thinner shall be stored in well-ventilated area earmarked for SAUDI
ARAMCO project material.

Date of manufacture shall be clearly visible on container paints which have


exceed shelf life given in Saudi Aramco Data Sheet shall be discarded.

Paint shall not be used from container which shows sign of leakage.

Copies with no seal are Uncontrolled copies. Page 11 of 17


` NASSER S AL HAJRI CORPORATION
SAUDI ARAMCO ONSHORE MAINTAIN POTENTIAL PROGRAM- NA1A
CONTRACT # 6600033948
NSH-SAOMPP-CMS-PI-008 METHOD STATEMENT FOR PAINTING & COATING
Rev-00 Date: 22 FEB. 2015

Paint which have gelled shall not be used and any paint skin must be cut and
removed before application.

All paints shall be thoroughly mixed before application. For quantities above 5
liters power stirrer shall be used. If sludge has formed a bottom of container
mixing shall be continued until the paint is homogenous.

If the thinner is required, the type and quantity to be added shall be given in
SAUDI ARAMCO Data Sheet.

QC Inspector will verify that painting is not performed when:

 The surface temp. is less 10 deg. C. or more than 50 deg. C.


 The surface contains oil, grease, dirt and loose rust.
 The surface temp. is less than 3 deg. C above dew point.
 Adverse weather conditions like strong wind blowing sand on the surface
being painted.
 Strong wind causing dry spray.

Primer, intermediate coat and top coat shall be of contrasting colors.

Welds edges shall be given a brush applied stripe coat prior to normal painting.

Recoating shall not be carried out until the earlier coat has completely cured.

The finishing coating shall be generally free of runs, Sags, drips, dry spray or
foreign matter.

Paint to be sprayed shall be filtered through a 30 to 60 mesh screen prior to use


and shall be continuously agitated with low speed stirrer.

Upon completion of the paint application, the dry film thickens shall be checked.

All the areas where the dry film thickness are below the above minimum values
need to be build-up.

6.5 Repair Works

Defective areas will be initially cleaned by solvent or detergent.

Copies with no seal are Uncontrolled copies. Page 12 of 17


` NASSER S AL HAJRI CORPORATION
SAUDI ARAMCO ONSHORE MAINTAIN POTENTIAL PROGRAM- NA1A
CONTRACT # 6600033948
NSH-SAOMPP-CMS-PI-008 METHOD STATEMENT FOR PAINTING & COATING
Rev-00 Date: 22 FEB. 2015

For small areas than 0.1sq.m the paint film will be removed by means of grinding
machine using at least 80 grit disc sanders to expose the bare metal surface.
Spot blasting can also use as an alternated method.

For areas greater than 0.1sq.m the paint film shall will be blasted off to bare
metal surface.

In both cases the edge of the coating around the bare metal will be feathered up
to 50 mm.

The bare metal areas will be brushed to remove dust debris then paint will be
reapplied. For area larger than 0.1sq.m paint will be sprayed.

The paint after curing shall be checked for dry film thickness.

Note: A Painting/Coating Schedule shall be accomplished as shown below on the


basis of Release Purchase Order (PO) issued by SAUDI ARAMCO.

7.0
Item No Item Description Painting System Color Manufacture

U/G EXT. GIRTH Approved Saudi Aramco


1 APCS-XXX XXXX
WELDS Paint Manufacturer

SAFETY ACTION PLAN:

7.1 Tool Box/ Safe Work Plan

 The safe work plan to be prepared by the site supervisor.


 Tool box talks to be observed before starting the work shift to discuss the
Safe Work Plan and other safety concerns for the task.
 Tool box talk shall be conducted by the site supervisor with the HSE
officer assisting and submitting the attendance sheet.
 Work can only start when all the provisions in the safe work plan are fully
complied, to include all safety precautions required.

Copies with no seal are Uncontrolled copies. Page 13 of 17


` NASSER S AL HAJRI CORPORATION
SAUDI ARAMCO ONSHORE MAINTAIN POTENTIAL PROGRAM- NA1A
CONTRACT # 6600033948
NSH-SAOMPP-CMS-PI-008 METHOD STATEMENT FOR PAINTING & COATING
Rev-00 Date: 22 FEB. 2015

 All tool box talk attendance sheets must be turned over for submission to
HSE department.

7.2 General Safety Requirements

Personal Protective Equipment’s:


 All personnel (sub-contractor, contractor and client) must wear the
project mandatory PPE (long pants, long sleeve shirt/arm sleeve, hard
hat, safety dark glass, safety clear glass, safety shoes, high visibility
vest, hand gloves).
 Special PPE for face protection, noise, hand protection, dust pollution,
etc. shall be provided to all concerned workers/personnel.
 All PPE must be inspected prior to use.

Housekeeping:

 Unwanted materials/supplies shall be removed from site to ensure clear


access. Temporary material store will be located.
 Proper barricading and signage shall be implemented.
 Maintain proper access and egress for workers, equipment and for
emergency.
Work Environment:
 Drinking water to be provided in 20-liter coolers in the working area, aside
from the water stations.
 During summer months, replacement drink (juice with salt, sugar and
glucose) provided to all workers twice during morning and afternoon to
minimize impact of heat exposure.
 During high wind where visibility will hamper the operation, Construction
and Safety will advise the workers on approved actions to take.
 Dust control measure shall continue to be enforced at these times.

Tools and equipment:

Copies with no seal are Uncontrolled copies. Page 14 of 17


` NASSER S AL HAJRI CORPORATION
SAUDI ARAMCO ONSHORE MAINTAIN POTENTIAL PROGRAM- NA1A
CONTRACT # 6600033948
NSH-SAOMPP-CMS-PI-008 METHOD STATEMENT FOR PAINTING & COATING
Rev-00 Date: 22 FEB. 2015

 All tools shall be inspected color coded prior to use; replace damage tools
from store.
 Electrical tools/equipment must be properly checked color coded before
using (project standard is 110 volts supply / 220 volts tools shall require
SAOMPP approval).
 Operate the tools according to the operations manual.
 Mobile equipment shall comply all safety requirements and inspected by
respective operators and drivers prior to operation.
 Flagmen shall be deployed to assist the moving equipment.
 All other non-mobile equipment shall be complied with all the safety
requirements prior to deployment.
Permit To Work:
 All permits to work required must be valid and approved before the start
of the job.
 Permit original copies must be in the site; inside the permit box.
 All conditions provided in the permit must be complied and maintained
form the start up to completion of the works.
 For night work, workers list shall be attached on all permits.
 When an unsafe condition or conditions occur, the task will be stopped for
immediate rectification of the condition.

Lifting and Rigging:

 There may be light lifting activity; contractor’s lifting and permit procedure
shall be strictly followed.
 All equipment must have valid certification and color inspection sticker.
 Operator to implement daily inspection with checklist prior to use.
 Operator must possess the valid SAG heavy driving license, 3rd party
certification and medical examination fit to work.
 Certified rigger to be available during the operation.

Copies with no seal are Uncontrolled copies. Page 15 of 17


` NASSER S AL HAJRI CORPORATION
SAUDI ARAMCO ONSHORE MAINTAIN POTENTIAL PROGRAM- NA1A
CONTRACT # 6600033948
NSH-SAOMPP-CMS-PI-008 METHOD STATEMENT FOR PAINTING & COATING
Rev-00 Date: 22 FEB. 2015

 All lifting gears, sling and tackles must have valid certification and color
coding and inspected prior to use.
 Flagman shall be available; equipped with red and green flags and
whistles.
Electricity:
 Lighting facility (tower lights & flashing lights) for night work are provided.
 All energized equipment shall be properly grounded.
 Qualified mechanic/electrician shall be deployed during the operation to
respond the need for lighting relocation, etc. and also to act as fire
watchers.
 Panel boards or extension cords used in site shall be proper checked and
color coded.
 To mitigate tripping hazard, power/electrical cables shall be either
installed in between scaffold planks or elevated in access/egress
portions.
 Lightings and generators locations shall be marked in the drawing
attached.
Road/ traffic safety:
 All vehicles and equipment in the site shall observe strict road safety; that
is follow site speed limit 30kph and 15kph in congested areas, seat belt
fastened by driver and all passengers, pedestrians are respected and
allowed to pass first all the time.
 Passing other vehicles not allowed.
 All headlights on at all times.
 Signboards for speed limit are provided (30kph site speed).
 Crossing signs are provided in entrance and exit gates.

7.3 SAOMPP Emergency Numbers

NSH Male Nurse 0536012017

Copies with no seal are Uncontrolled copies. Page 16 of 17


` NASSER S AL HAJRI CORPORATION
SAUDI ARAMCO ONSHORE MAINTAIN POTENTIAL PROGRAM- NA1A
CONTRACT # 6600033948
NSH-SAOMPP-CMS-PI-008 METHOD STATEMENT FOR PAINTING & COATING
Rev-00 Date: 22 FEB. 2015

NSH Ambulance driver 0552424080


NSH HSE Manager 0536012056
NSH Construction Manager 0536012021
NSH Project Manager 0536001178
PMT HSE Manager/Emergency 0500192109

7.4 Other Specific Safety Requirements:

a) For medical team/facility; Provide certified nurse, certified first aider,


ambulance driver, ambulance (to be parked near the Coker area during
night time).
b) Working in pair (“buddy-system”) is strictly required especially during
night works.
c) Construction to deploy Flagmen (equipped with flags and whistle) in
crossings, diversion access, Coker ramps and washing area.

END OF THE DOCUMENT

Copies with no seal are Uncontrolled copies. Page 17 of 17

You might also like