Professional Documents
Culture Documents
Report Record
Quarter Report No. 2
Release Date & Cut of date 1 - Jan - 2021
1. PROJECT CHARTER........................................................................................................................................................... 3
2. LOCATION........................................................................................................................................................................ 4
3. PRELIMINARILY LAYOUT................................................................................................................................................... 5
4. PROJECT PROGRESS SUMMARY WITH S-CURVE................................................................................................................ 7
4.1. TOTAL (OVERALL) PROJECT PROGRESS SUMMARY (DEVELOPED & EPC PROJECT)...............................................................................7
4.2. TOTAL (OVERALL) PROJECT PROGRESS SUMMARY (DEVELOPED & EPC PROJECT)...............................................................................8
4.3. OVERALL DEVELOP WORK (PERMITS & MOU) PROGRESS SUMMARY..............................................................................................9
4.4. OVERALL DEVELOP WORK S - CURVE (PERMITS & MOU) PROGRESS SUMMARY.............................................................................10
4.5. OVERALL EPC MDF PROJECT PROGRESS SUMMARY...................................................................................................................11
4.6. OVERALL EPC MDF PROJECT PROGRESS S- CURVE ...................................................................................................................12
4.7. OVERALL SIEMPELKAMP SCOPE PROGRESS.................................................................................................................................13
4.8. OVERALL SIEMPELKAMP SCOPE PROGRESS S- CURVE`.................................................................................................................14
4.9. OVERALL PETROJET SCOPE PROGRESS....................................................................................................................................15
4.10. OVERALL WORK – PETROJET SCOPE PROGRESS S-CURVE......................................................................................................16
4.11. OVERALL FORECAST PROGRESS SUMMARY.............................................................................................................................17
4.12. OVERALL FORECAST WORK S CURVE..................................................................................................................................18
4.13. OVERALL SK FORECAST PROGRESS WORK...........................................................................................................................19
4.14. OVERALL SK FORECAST WORK S CURVE.............................................................................................................................20
4.15. OVERALL PTJ FORECAST WORK PROGRESS.........................................................................................................................21
4.16. OVERALL PTJ FORECAST WORK........................................................................................................................................22
5. OVERALL MAIN MILESTONE............................................................................................................................................ 23
6. PROGRESS STATISTICS.................................................................................................................................................... 24
6.1. SIEMPELKAMP ENGINEERING DOCUMENTS................................................................................................................................24
6.2. SIEMPELKAMP PURCHASE ORDER ISSUANCE...............................................................................................................................26
6.3. SIEMPELKAMP SHIPMENT ARRIVED.......................................................................................................................................... 27
6.4. PETROJET ENGINEERING DOCUMENTS.......................................................................................................................................28
7. TOTAL BREAKDOWN BUDGET FOR THE PROJECT............................................................................................................. 29
7.1. OVERALL S CURVE FOR TOTAL PROJECT.....................................................................................................................................30
7.2. OVERALL S CURVE FOR SIEMPELKAMP.......................................................................................................................................31
7.3. OVERALL S CURVE FOR PETROJET.............................................................................................................................................32
7.4. CASH FLOW FORECAST SUMMARY............................................................................................................................................33
7.5. BREAK DOWN FOR THE PROJECT - PTJ SCOPE............................................................................................................................34
7.6. SUMMARY FOR THE PROJECT...................................................................................................................................................35
8. SIEMPELKAMP ENGINEERING WORK NOTES AND PROGRESS ASSUMPTION............................................36
8.1. SIEMPELKAMP ENGINEERING WORK - CONTRACTUAL PREMISES....................................................................................................36
8.2. CONTRACT DEFINITION...........................................................................................................................................................36
8.3. CLASSIFICATION OF ENGINEERING DOCUMENTS AS PER CONTRACT................................................................................................36
8.4. ASSUMPTION PROGRESS RELATIVE WEIGHT AND WORK STEP PERCENTAGE.....................................................................................36
8.5. ENGINEERING WORK SCHEDULE (OUTLINE) - LEVEL 2 CONTRACT SCHEDULE....................................................................................38
8.6. MODIFIED ENGINEERING WORK SCHEDULE (OUTLINE)................................................................................................................39
8.7. ASSUMPTION PROGRESS RELATIVE WEIGHT AND WORK STEP PERCENTAGE.....................................................................................40
8.8. SUGGESTED ACCELERATION SCHEDULE......................................................................................................................................41
8.9. PRELIMINARY SHIPPING SCHEDULE...........................................................................................................................................42
9. PETROJET ENGINEERING WORK NOTES AND PROGRESS ASSUMPTION............................................................................44
9.1. CLASSIFICATION OF ENGINEERING DOCUMENTS AS PER PROGRESS MEASUREMENT CONTROL...............................................................44
9.2. ASSUMPTION PROGRESS RELATIVE WEIGHT AND WORK STEP PERCENTAGE ....................................................................................44
10. PETROJET PROCUREMENT PROFESSIONAL SERVICES WORK NOTES AND PROGRESS ASSUMPTION..............................45
10.1. ASSUMPTION PROGRESS RELATIVE WEIGHT AND WORK STEP PERCENTAGE ................................................................................45
11. PETROJET MATERIAL &EQUIPMENT SUPPLY WORK NOTES AND PROGRESS ASSUMPTION...........................................45
11.1. ASSUMPTION PROGRESS RELATIVE WEIGHT AND WORK STEP PERCENTAGE ................................................................................45
12. SKYLINE REPORT FOR ENGINEERING REPORT.............................................................................................................. 46
13. SKYLINE REPORT FOR MRQ......................................................................................................................................... 47
14. SKYLINE REPORT FOR CIVIL WORK.............................................................................................................................. 48
15. ORGANIZATION CHART............................................................................................................................................... 49
16. PETROJET LEVEL 2 SCHEDUAL...................................................................................................................................... 50
WOTECH MEDIUM DENSITY FIBER BOARD (MDF) PLANT
EGYPT QUARTER SUMMARY REPORT Jan 2021
1. Project charter
Project charter
Medium-Density Fiberboard
Project name
MDF Plant
Project sponsor Sidpec,Petrojet,Echem,EGPC
Date of project approval Dec-19
Project manager Ahmed baraka
Project milestones
Effective date (Siempelkamp) 6- Jun-20
Effective date (PETROJET) 6- July-20
Start of commissioning with feed stock Feb-22
End date of the project 6- June-22
2. Location
WOTECH MEDIUM DENSITY FIBER BOARD (MDF) PLANT
EGYPT QUARTER SUMMARY REPORT Jan 2021
3. Layout
WOTECH MEDIUM DENSITY FIBER BOARD (MDF) PLANT
EGYPT QUARTER SUMMARY REPORT Jan 2021
WOTECH MEDIUM DENSITY FIBER BOARD (MDF) PLANT
EGYPT QUARTER SUMMARY REPORT Jan 2021
4.1. Total (Overall) Project Progress summary (Developed & EPC Project)
Planned Actual
No Total Variance
Discipline Accumulative Accumulative
. Weight % %
Progress % Progress %
Development
1 22.00% 100.00% 92.00% -8.00%
Work
EPC MDF
2 78.00% 16.85% 25.24% 8.39%
(Project)
Total 100.00% 35.15% 39.93% 0.23%
WOTECH MEDIUM DENSITY FIBER BOARD (MDF) PLANT
EGYPT QUARTER SUMMARY REPORT Jan 2021
4.2. Total (Overall) Project Progress summary (Developed & EPC Project)
WOTECH MEDIUM DENSITY FIBER BOARD (MDF) PLANT
EGYPT QUARTER SUMMARY REPORT Jan 2021
- Delay analysis
No Work Front can be Performed by Wotech, and all Pending activities deepened on
approval of Ministry of Defense Permeations.
Expected date for approval at the End of February.
WOTECH MEDIUM DENSITY FIBER BOARD (MDF) PLANT
EGYPT QUARTER SUMMARY REPORT Jan 2021
4.4. Overall Develop Work S - Curve (Permits & MOU) Progress Summary
WOTECH MEDIUM DENSITY FIBER BOARD (MDF) PLANT
EGYPT QUARTER SUMMARY REPORT Jan 2021
Planned Earned
No Total Weight (SV"MHR")
Discipline Accumulativ Accumulative
. % Variance%
e Progress % Progress %
Siempelkamp
1 47.12% 25.52% 46.20% 20.68%
Scope
2 Petrojet Scope 52.88% 9.13% 6.57% -2.56%
Total 100.00% 16.85% 25.24% 8.39%
WOTECH MEDIUM DENSITY FIBER BOARD (MDF) PLANT
EGYPT QUARTER SUMMARY REPORT Jan 2021
Planned Earned
Total (SV"MHR")
No. Discipline Accumulative Accumulative
Weight % Variance%
Progress % Progress %
Planned Earned
Total (SV"MHR")
No. Discipline Accumulative Accumulative
Weight % Variance%
Progress % Progress %
1 Engineering 5.00% 50.25% 32.21% -18.04%
Procurement
2 Professional 4.00% 5.33% 7.28% 1.96%
Services
Logistics (for SK
3 1.00% 0.00% 2.94% 2.94%
scope of delivery)
Material &
4 40.00% 7.25% 6.00% -1.25%
Equipment supply
Construction &
5 47.00% 7.45% 4.76% -2.69%
Pre-commissioning
Commissioning &
6 3.00% 0.00% 0.00% 0.00%
Start-Up
Total 100.00% 9.13% 6.57% -2.56%
4.9. Overall PETROJET Scope Progress
- Engineering Delay: -
Delay in issuance Architectural DWG’s related to Protonation line Building & TCF &
HSE Building & Pump Station.
Delay in issuance Civil DWG’s related to Substation Building & Gate Towers & main
security Rooms.
Delay in issuance Civil Network DWG’s related to Sewer Network Manholes& potable
water network calculation.
Delay in issuance control narrative & instrument Specs.
Delay in issuance HVAC Calculation and Specs.
Delay in issuance all Process safety & lose Prevention scope.
Delay in issuance all valves Data sheet.
Delay in issuance DWG’s related of Pressure Flow diagram & P&ID’s for some systems.
Delay in Steel Structures & platforms DWG’s related of Straw Preparation Equipment
Delay in issuance Telecommunication & CCVT & Telephone Systems DWG’s
Delay in issuance some of Single line Diagrams.
- Material & Equipment supply Delay: -
Delay in issuance RFQ of Over Head Crane (planned date 8 OCT 20).
Delay in issuance RFQ of Truck scale (planned date 19 Nov 20).
Delay in issuance RFQ Piping Bulk material (RFQ No. 1) (planned date 26 dec 20) due to
delay in issuance P&ID IFR and General Arrangement IFR.
Delay in issuance RFQ valves (RFQ No. 1) due to delay in issuance P&ID IFR
Delay in delivery at site of part of Steel Structure (Batch-1) for MDF WH & Prod. Line
(only 86 % Arrived)
- Construction & Pre-commissioning
Delay Construction of TCF (Backfilling, Concrete Works & Finishing works).
Delay backfilling of Rice straw area & Production line.
Delay in piles Work, PTJ will increase piles machines to cover and mitigate the Delay
and working 24 hours (Night Shift).
WOTECH MEDIUM DENSITY FIBER BOARD (MDF) PLANT
EGYPT QUARTER SUMMARY REPORT Jan 2021
N
Discipline W%
o. P A P F P F P F P F P F P F P F
Siempelkam 5.04 12.63 25.68 46.20 58.53 69.93 70.32 70.32 76.99 76.99 86.60 86.60 97.56 97.56 100.00 100.00
1 47.12%
p Scope % % % % % % % % % % % % % % % %
Petrojet 1.61 6.20 36.41 33.91 67.23 63.32 86.93 83.67 94.96 95.77 98.76 99.27 100.00 100.00
2 52.88% 9.13% 6.57%
Scope % % % % % % % % % % % % % %
100.00 3.22 9.23 16.93 25.24 46.83 50.88 68.69 66.61 82.25 80.53 91.02 91.45 98.20 98.47 100.00 100.00
Total
% % % % % % % % % % % % % % % % %
Q1 Q2 Q3 Q4 Q5 Q6 Q7 Q8
Discipline W%
P A P A P F P F P F P F P F P F
15.74 22.73 74.42 88.75 95.96 98.50 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Engineering 5.00%
% % % % % % % % % % % % % % % %
Procurement &
65.00 6.54 17.68 33.79 64.25 82.66 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Equipment
% % % % % % % % % % % % % % % % %
supply
Installation 30.00 0.00 0.00 0.00 0.00 0.00 23.31 23.31 55.35 55.35 91.88 91.88 100.00 100.00
0.00% 1.06% 1.06%
Supervision % % % % % % % % % % % % % %
100.00 5.04 12.63 25.68 46.20 58.53 69.93 70.32 70.32 76.99 76.99 86.60 86.60 97.56 97.56 100.00 100.00
Total
% % % % % % % % % % % % % % % % %
WOTECH MEDIUM DENSITY FIBER BOARD (MDF) PLANT
EGYPT QUARTER SUMMARY REPORT Jan 2021
WOTECH MEDIUM DENSITY FIBER BOARD (MDF) PLANT
EGYPT QUARTER SUMMARY REPORT Jan 2021
N Discipline W% Q1 Q2 Q3 Q4 Q5 Q6 Q7 Q8
WOTECH MEDIUM DENSITY FIBER BOARD (MDF) PLANT
EGYPT QUARTER SUMMARY REPORT Jan 2021
o. P A P A P F P F P F P F P F P F
9.98 20.96 50.25 32.21 90.56 86.00 100.0 95.00 100.0 97.00 100.0 97.00 100.0 99.16 100.00 100.00
1 Engineering 5.00%
% % % % % % 0% % 0% % 0% % 0% % % %
Procurement
97.00 0.55 99.16 5.33 46.36 38.77 84.94 81.71 99.29 98.90 100.0 100.0 100.0 100.0 100.00 100.00
2 Professional 7.28
% % % % % % % % % % 0% 0% 0% 0% % %
Services
Logistics (for
0.00 0.00 0.00 2.94 23.01 98.00 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.00 100.00
3 SK scope of 1.00%
% % % % % % 0% 0% 0% 0% 0% 0% 0% 0% % %
delivery)
Material &
40.00 0.00 0.65 7.25 6.00 41.31 38.00 79.75 76.25 98.64 94.00 99.64 99.57 99.76 99.64 100.00 100.00
4 Equipment
% % % % % % % % % % % % % % % % %
supply
Construction
& Pre- 47.00 2.31 1.97 7.45 4.76 28.24 25.28 55.18 50.57 79.79 75.68 95.96 94.53 99.65 99.36 100.00 100.00
5
commissionin % % % % % % % % % % % % % % % % %
g
Commissionin 0.00 0.00 0.00 0.00 0.00 0.00 23.31 55.35 67.39 91.88 100.00 100.00
6 3.00% 0.00% 1.06% 0.00% 0.00%
g & Start-Up % % % % % % % % % % % %
100.00 1.61 6.20 9.13 6.57 36.41 33.91 67.23 63.32 86.93 83.67 94.96 95.77 98.76 99.27 100.00 100.00
Total
% % % % % % % % % % % % % % % % %
WOTECH MEDIUM DENSITY FIBER BOARD (MDF) PLANT
EGYPT QUARTER SUMMARY REPORT Jan 2021
N Planned Expected
Task Name Actual Statues
o Finish Finish
GENERAL MILESTONE (WOTECH)
1 Land agreement 01-Oct-20 01-Mar-21 90.00 %
2 Permits and Approvals 07-Dec-20 01-Mar-21 93.00 %
3 MOU of Chemical & Feedstock 16-Jun-20 ____ 100.00%
4 Chemical & Feedstock Agreements 23-Apr-20 01-Mar-21 93.00 %
5 Financial Close 15-Oct-20 01-Mar-21 0.00%
6 Assignment of PMT 01-Apr-20 ____ 100.00%
7 Staff Regulations 31-Dec-20 01-Mar-21 95.00 %
PROJECT MILESTONE (EPC)
Siempelkamp MILESTONE
8 Contract Signature & Kickoff Meeting 11-Feb-20 ____ 100.00%
9 Effective date 07-Jun-20 ____ 100.00%
10 Engineering 21-Jun-21 21-Jun-21
Start on 11 Dec
11 Equipment Delivery Start 07-Mar-21 07-Mar-21
2020
12 Equipment manufacturing and Delivery Finish 07-Jun-21 07-Jun-21
Equipment Erection and MC & Start of Pre‐
13 07-Dec-21 07-Dec-21
Commissioning
PTJ MILESTONE
14 Mobilization 01-Jan-20 ____ 100.00%
15 Effective date 07-Jul-20 ____ 100.00%
16 Engineering 27-Jul-21 27-Jul-21
17 Procurement (ISBL & OSBL) 22-Apr-22 22-Apr-22
PRODUCTION LINE & UTILITIES (OSBL)
18 07-May-22 07-May-22
installation
Mechanical Completion for Production line &
19 07-Dec-21 07-Dec-21
Start of pre-commission without Feedstock
20 Pre‐Commissioning (without feedstock) 20-Jan-22 20-Jan-22
ISBL-Commissioning With feedstock (with
21 21-Mar-22 21-Mar-22
feedstock)
22 OSBL-Commissioning 21-Jun-22 21-Jun-22
23 Start Start-up, performance tuning & Test 21-Feb-22 21-Feb-22
24 complete Start-up, performance tuning & Test 07-Jun-22 07-Jun-22
25 Provisional Acceptance 07-Jun-22 07-Jun-22
WOTECH MEDIUM DENSITY FIBER BOARD (MDF) PLANT
EGYPT QUARTER SUMMARY REPORT Jan 2020
6. Progress Statistics
(A)
Checking Owner’s architectural building drawings on
7 Submit By 1 type final only ( B ) 1 0 0
collision with main machinery eq.
10 Principle drawings for silo casing Submit By 1 type final only ( B ) 5 4 0
12 Lighting plan Submit By 1 type final only ( B ) 8 0 0
Layout for process, cooling & extinguishing water, for the
16 Submit By 1 type final only ( B ) 28 26 26
consumers
14 Layout for compressed air for the consumers Submit By 1 type final only ( B ) 10 10 10
Workshop drawings for ducting of drier, cyclone
18 Submit By 1 type final only ( B ) 198 195 195
separators, pneumatical conveyors
Electrical layout, scale, showing location of switch
19 Submit By 1 type final only ( B ) 49 11 3
rooms ,local panel, transformers
20 (No.2) Electrical Cable tray Submit By 1 type final only ( B ) 15 0 0
Spare parts list for all machines to be supplied by the
21 Submit By 1 type final only ( B ) 1 0 0
Contractor
Operating manuals for machinery included in Contractor’s
23 Submit By 1 type final only ( B ) 1 0 0
scope of supply per each
Technology manual with proposals for the first settings of
24 Submit By 1 type final only ( B ) 1 0 0
machine
List of operating supplies and auxiliaries in
28 Submit By 1 type final only ( B ) 1 0 0
Contractor’s scope of supply
List of lubricants specifying various grades of oil &
29 Submit By 1 type final only ( B ) 1 0 0
greases in SK scope of supply
List of connecting chutes and ducts in Contractor’s
27 Submit By 1 type final only ( B ) 9 0 0
scope of supply
Principal information on insulation requirements for
30 Submit By 1 type final only ( B ) 1 0 0
machines and equipment
Document for the installation schedule , crane
22 Submit By 1 type final only ( B ) 6 6 6
sizebuilding openings for installation
TOTAL ENGINEERING WORK 488 394 376
WOTECH MEDIUM DENSITY FIBER BOARD (MDF) PLANT
EGYPT QUARTER SUMMARY REPORT Jan 2020
- Sidpic location
https://earth.google.com/web/search/sidpec/@31.00251812,29.83660379,8.79477433a,907.5899191d,35y,-73.42611787h,45.00011133t,-0r/
data=CigiJgokCZWpGAeuGj9AEfbO3FVSGj9AGfSA0laq3T1AIWUDr6_L3D1A
WOTECH MEDIUM DENSITY FIBER BOARD (MDF) PLANT
EGYPT QUARTER SUMMARY REPORT
Jan 2020
Cathodic Protection 21 - - -
Electrical 92 69 48 46
Fire - Fighting 23 11 - -
HVAC 33 23 13 7
Loss Prevention 14 3 3 3
Mechanical 21 6 4 1
Piping 24 2 2 -
Process 30 24 15 6
Steel Structure 236 30 12 12
Tanks 127 7 4 4
Fire & Gas 10 2 2 2
Telecommunication 94 56 42 40
Scope
No. Budget (EURO) Actual Paid Remaining
S. K PTJ
Quarter
Note
yearly
Planned Forecasted / Actual Planned Forecasted / Actual
4.00 Engineering p Euro ـــــــ 170,000.00 358,691.72 370,909.00 370,909.00 370,909.00 123,636.00 ـــــــ ـــــــ 170,000.00 1,935,054.72
5.00 Material Supply p Euro ـــــــ 2,448,289.00 2,448,290.00 1,958,632.00 5,875,895.00 5,875,895.00 5,875,895.00 ـــــــ 2,448,289.00 26,931,185.00
6.00 Material Supply p Euro ـــــــ 113,710.00 113,710.00 90,968.00 272,905.00 989,261.74 989,261.74 ـــــــ 113,710.00 2,683,526.49
7.00 Land preparation Euro ـــــــ 900,000.00 1,440,000.00 900,000.00 4,320,000.00 1,440,000.00 ــ ـــــــ ـــــــ 900,000.00 9,900,000.00
8.00 Construction p Euro ـــــــ 4,768,001.00 - 2,542,933.00 5,154,357.70 7,538,357.70 7,538,357.70 5,154,357.70 5,085,868.00 4,768,001.00 42,550,233.79
)Installation & Construction (Petrojet 8,400,000.00 1,798,691.72 6,375,842.00 11,894,866.70 15,498,066.70 14,527,150.44 12,019,514.44 5,085,868.00 8,400,000.00 84,000,000.00
9.00 Spare parts Euro ـــــــ ـــــــ ـــــــ ـــــــ 330,000.00 670,000.00 ـــــــ ـــــــ ـــــــ ـــــــ 1,000,000.00
10.00 ERP & Furniture Euro ـــــــ ـــــــ ـــــــ 250,000.00 250,000.00 ـــــــ ـــــــ ـــــــ ـــــــ ـــــــ 500,000.00
Customs & custom
11.00 Euro ـــــــ ـــــــ 97,932.00 146,897.00 624,164.00 1,066,927.00 ـــــــ ـــــــ ـــــــ ـــــــ 1,935,920.00
duties
12.00 VAT Euro ـــــــ ـــــــ 1,384,652.00 2,184,978.00 2,040,978.00 1,479,313.00 499,982.00 293,807.00 ـــــــ ـــــــ 7,883,710.00
)13.00 Others(Advisors Euro 48,189.00 14,476.00 14,476.00 14,476.00 15,924.00 15,924.00 15,924.00 15,924.00 ـــــــ ـــــــ 155,313.00
14.00 Others Euro 11,000.00 1,941.00 ـــــــ ـــــــ ـــــــ ـــــــ ـــــــ ـــــــ ـــــــ ـــــــ 12,941.00
15.00 Vehicles & Trucks Euro ـــــــ ـــــــ ـــــــ ـــــــ ـــــــ ـــــــ ـــــــ 600,000.00 ـــــــ ـــــــ 600,000.00
16.00 Utilities & Permits Euro ـــــــ ـــــــ 1,000,000.00 ـــــــ ـــــــ ـــــــ ـــــــ ـــــــ ـــــــ ـــــــ 1,000,000.00
17.00 Contingency Euro ـــــــ ـــــــ ـــــــ ـــــــ ـــــــ ـــــــ 1,720,800.00 5,162,401.00 3,441,600.00 ـــــــ 10,324,801.00
18.00 Land Euro ـــــــ ـــــــ 1,302,206.00 1,953,309.00 1,953,309.00 2,604,412.00 ـــــــ ـــــــ ـــــــ ـــــــ 7,813,236.00
19.00 PRMS Euro ـــــــ ـــــــ ـــــــ ـــــــ ـــــــ ـــــــ 1,500,000.00 ـــــــ ـــــــ ـــــــ 1,500,000.00
20.00 Cover Euro ـــــــ ـــــــ ـــــــ ـــــــ ـــــــ ـــــــ 2,000,000.00 ـــــــ ـــــــ ـــــــ 2,000,000.00
operating expensesــ21.00 Pre Euro 79,187.00 402,717.00 237,562.00 237,562.00 237,562.00 237,562.00 237,562.00 237,562.00 237,562.00 79,187.00 2,224,025.00
22.00 Initial working capital Euro ـــــــ ـــــــ ـــــــ ـــــــ ـــــــ ـــــــ 1,571,336.00 4,714,008.00 ـــــــ ـــــــ 6,285,344.00
23.00 Head Office Rent Euro 4,018.00 4,018.00 4,018.00 4,018.00 4,018.00 4,018.00 4,018.00 4,018.00 4,018.00 1,339.00 37,501.00
Grand Total 40,620,668.72 22,148,737.00 45,791,371.70 21,780,222.70 22,743,772.44 23,687,234.44 9,269,048.00 16,074,836.00
202,115,891.00
Accumulative Total 40,620,668.72 62,769,405.72 108,560,777.42 130,341,000.12 153,084,772.56 176,772,007.00 186,041,055.00 202,115,891.00
WOTECH MEDIUM DENSITY FIBER BOARD (MDF) PLANT
EGYPT MONTHLY REPORT Jan 2021
28%
Siemelkamp 72% Actual paid
47% Petrojet Remaining
53%
Petrojet Siempelkamp
Paid amount
10%
8.4.1. For Document that will be submitted 2 times as preliminary and final (A & B).
Basis of weightiness: Man-Hours (MHR)
Updated based on Finish millstone (Not Progressive Percentage).
8.4.2. For Document that will be submitted 1 time as preliminary only (A).
1st DOCUMENT
CERTIFIED
CATOGRIES & MILESTONES ISSUANCE (NOT
DOCUMENTS
CERTIFIED)
Document will be submitted 1
45.00% 55.00%
time as preliminary (A)
8.4.3. For Document that will be submitted 1 time as final only (B).
1st DOCUMENT
CERTIFIED
CATOGRIES & MILESTONES ISSUANCE (NOT
DOCUMENTS
CERTIFIED)
Document will be submitted 1
45.00% 55.00%
time as final (B)
8.6.1. Change on the dates of Position No. 14. (Layout for compressed air for the consumers)
8.6.2. Change on the dates of Position No. 16. (Layout for process, cooling & extinguishing
water, for the consumers)
The list of Engineering Document has been updated on 6 - Sep - 2020 according to
new data from suppliers so Engineering work Progress has decreased.
Position No. 10 (Principal drawings for silo casing) need to update and determine
final scope.
WOTECH MEDIUM DENSITY FIBER BOARD (MDF) PLANT
EGYPT QUARTER SUMMARY REPORT Jan 2021
etd port of loading FOB 28.11.2020 FOB 22.12.2020 FOB 09.12.2020 FOB 10.01.2021
port of loading Hamburg, Germany Bremen, Germany Hamburg, Germany Hamburg, Germany
Name of the vessel Monte Alegre Annamaria Monte Verde CMA CGM White Shark
eta Alexandria, Egypt appr. 10.12.2020 12-01-21 appr. 21.12.2020 appr. 26.01.2021
PERCENTAGE %
CATOGRIES &
CRITERIA OF UPDATING (FROM MHR of Each
MILESTONE
Doc.)
10. PETROJET Procurement professional services Work Notes and Progress Assumption
11. PETROJET Material &Equipment Supply Work Notes and Progress Assumption
Attached
WOTECH MEDIUM DENSITY FIBER BOARD (MDF) PLANT
EGYPT QUARTER SUMMARY REPORT Jan 2021
Attached
Attached
WOTECH MEDIUM DENSITY FIBER BOARD (MDF) PLANT
EGYPT QUARTER SUMMARY REPORT Jan 2021
Attached
WOTECH MEDIUM DENSITY FIBER BOARD (MDF) PLANT
EGYPT QUARTER SUMMARY REPORT Jan 2021
Attached