i) Nos. required : Two (2) [One (1) Two (2) [One (1)
operating and operating and
one(1) standby] one(1) standby]
Acid Alkali
x) Permissible Tolerance
in rated capacity and
in efficiency at rated
capacity : .... As per IS-5639 ....
c) Size : 50 mm 50 mm
xix) Motor Selection : While selecting the motor for pump 15%
(minimum) margin over BKW of pump at
rated duty point shall be taken and standard
motor with next higher KW rating available
shall be selected. This shall in no way be
less than maximum power required by pump.
i) Nos. required : Two (2) [ One(1) Two (2) [One (1) for
for cation units and anion units and one
one(1) for MB Units (1) for MB Units
Note :
Acid and alkali measuring tanks for cation
and anion units respectively shall be
adequate to carry out double regeneration as
and when required.
iii) Material of construction : Mild Steel with rubber lining, 4.5 mm thick in
3 layers
vii) Vent, overflow, drain : Required with fume absorber and over flow seal.
and sample connection
x) Level switches : Very high, high and low- level alarm for
annunciation and interlock, alongwith
analogue level indication in panel.
Very High level alarm shall be used for
double regeneration.
v) Material
viii) Manhole (Davit type) : Two (2) nos., on the top of roof
(500 mm dia.)
F. Flow Indicator
ii) Type and material : MSRL Vertical cylindrical type with dished
ends and fitted with immersion type electric
heaters. Shell-carbon steel as per IS 2062;
Dished ends-IS2002 Gr.1. All wetted parts of
Electric heater material shall be of SS : 316
construction.
vii) Level switch : Two (2) nos. level switches for high, low and
interlock Level switches shall be magnetic
type with external chamber and isolation
valves.
viii) Temperature indication : Two (2) nos. located on the discharge line
with temperature element of ejectors and panel mounted with high
alarm and interlock. Local as well as panel
temperature indication facility to be provided.
c) Dynamic Balancing
test : Required
d) Performance Test :
o Test to be
a) Casing, impeller,
stuffing box : SS conforming to AISI-304
xvi) Special Feature : While selecting the motor for pump, 15%
(minimum) margin over BkW of pump at rated
duty point shall be taken and standard motor
with next higher kW rating available shall be
selected. This shall in no way be less than
maximum power required by pump.
J. Density Indicators
ii) Size (dia. x length) : (To be finalized by Bidder to suit the capacity specified)
iv) Useful capacity : Fifteen (15) days capacity for each tank,
based on design flow rate through
two demineraliser chains.
vii) Protection
x) Manhole (Davit type) : Two (2) 500 NB size for each tank
xii) Level indicator per tank : Each tank shall be provided with three nos.
(minimum) gauge glass type level indicators
and one (1) no. dial type level indicator.
A. Morpholine Tank
vi) Protection
iii) Number : Two (2) [One (1) operating & one(1) standby]
iii) Recirculation-cum-
Disposal Pumps (or DM plant
Waste water pumps)
a) Material Test
required for : Casing, Impeller, Shaft and Shaft sleeve
b) Hydrotest pressure
duration and pro-
cedure : As per IS-5120
c) Dynamic Balancing
Test : Required
d) Performance Test :
o Testing
Standard : IS : 5120
o Test to be
Carried out : On all pumps at rated speed
Note * TDH of pump shall be checked with calculated head required for disposal of regeneration
effluent to waste management plant at about 600 metre from neutralisation pit at rated flow
of pump and shall in no case be less than that. The exact location of Guard Pond will be
informed to Bidders later.
iv) pH Monitor
v) Level Switch
a) Number required : Three (3) [one high, one low and one very
low in each pit.
b) Type of
Construction : ......... Vertical, Cylindrical .......
h) Agitator : - To be constructed
of SS-316 driven
through reduction
gear
vi) Material of
construction : Carbon Steel as per specified code min. 8
mm thick plate for the bottom plate. Shell and
roof plate may be 6 mm thick (minimum).
Number : Three (3) for each tank, (high, low and very
low) for alarm and interlock.
b) Additional nozzle
connections : Four (4) (two 200 NB and two 150 NB) per
tank and suitably blanked with blank flanges.
c) Conservation vent
valves : One on each tank
c) Dynamic Balancing
test : Required
d) Performance Test :
o Test to be
carried out : On proto-type at rated speed
a) Casing, impeller,
stuffing box : SS conforming to AISI-304
xvii) Special Feature : While selecting the motor for pump, 15%
(minimum) margin over BKW of pump at
rated duty point shall be taken and standard
motor with next higher KW rating available
shall be selected. This shall in no way be less
than maximum power required by pump.
v) Regeneration/Degreasing/
Defouling : Suitable regeneration of resins from any
softener exchanger vessel/ from one of the
cation, anion or mixed bed unit by acid/ alkali
arrangement shall also provided for
degreasing/ defouling of cationic and anionic
resins.
vi) Accessories : Suction filter, Inter cooler, after cooler, Lube Oil
System and Local gauge board.
vii) Control : Load / Unload with the help of pressure switch for
running compressor.
vii) Pressure Switch : One (1) at each receiver with low pressure
alarm at panel.
SOFTENING PLANT
ix) Range of Operation : From safe minimum flow to 100% of rated capacity
b) Hydrotest pressure
duration and pro-
cedure : As per IS-5120
c) Dynamic Balancing
Test : Required
d) Performance Test :
i) Stuffing box
packing : Graphitized Asbestos
xv) Instrument
b) Pressure switch : Yes, at common pump discharge header for "low &
high" header pressure alarm and interlock for
individual chain.
xvi) Special feature : Two (2) nos. very low level contact from the filtered
water pump sump will be provided by the Owner.
Bidder shall provide the necessary interlock of the
pumps from the same as per flow diagram.
19.0 Salt Storage Area : Shed (Tubular Steel Shed with High Quality
roof covering Sheets)
20.0 Salt lagoon / Salt Saturator
f) Duty : Intermittent
22.0 TANKS Filtered Brine Filtered Brine Fresh Brine Spent Brine
Storage Tank Week Storage Meas. cum Storage cum
Tank Storage tank Meas. tank
iv) No. of compartments Two (2) Two (2) Three (3) Three (3)
v) Capacity of each 700 m3 Sat. ---1 Week Req. --- Req. of two ---Req. of two
Compartment Salt Solution--- of Softening. ---Exchangers --Exchangers
Plant--------(+)20% margin-- (+)20% margin
for 2 streams
23.0 PUMPS Filtered Brine Filtered Brine Fresh Brine Spent Brine
Transfer Pump Transfer Pump Dosing Pump Dosing Pump
(to week tank) (to brine meas.
tank)
iv) Capacity 300 m3/hr ---- 300 m3/hr --------- 200 m3/hr ------- 300 m3/hr
a) Casing : CIRL
b) Impeller : CIRL
c) Shaft : EN-8
f) Packing : Teflon
b) Dished ends : Boiler quality steel as per IS- 2002, Gr. 2A.
xi) Internal andExternal painting : Epoxy painting as per Specification No. M0.
xiv) Handhole (150 mm dia.) : One (1) in each vessel for taking out the resin.
xv) Resin
b) Number : One/Unit
c) Type : Rotameter
a) Location and Type : Outlet of unit, integrator electronic type with digital
LED display and manual reset type, indicator
analogue type. (Refer instrumentation specification)
b) Number : One/Unit
e) Transmitter : DP Type
b) Number : One/Unit
xx) Interconnection of
Exchanger Units : The outlet of Softener Exchanger Units shall be
interconnected with isolation valves so that any of
the exchangers can be used for any stream.
xxi) Design code for exchanger vessel : IS-2825/ ASME Section-VIII Div.1
v) Overflow, drain, vent, manhole : Required with C.I. goose neck with bird
connections, dewatering sumps, screen for the overflow line
rung ladder
ix) Isolation gates : One (1) no. at the inlet to each chamber of
softened water storage tank.
vi) Capacity and Head : 1600 Cu.m/hr (rated), TDH 20 mWC. (Considering
C=120 in Hazen William Equation for calculating
pipe friction loss).
xi) Noise Level : 85 dB(A) (at a distance of 1.5 m from the outer
(Pump Motor Set) surface of motor)
a) Material Test
required for : Casing, Impeller, Shaft and Shaft sleeve
b) Hydrotest pressure
duration and pro-
c) Dynamic Balancing
Test : Required
d) Performance Test :
i) Stuffing box
packing : Graphitized Asbestos
xvi) Instrument
b) Pressure switch : Yes, at common pump discharge header for "low &
high" header pressure alarm and interlock for
individual chain.
xvii) Special feature : Two (2) nos. very low level contact from the filtered
water pump sump will be provided by the Owner.
Bidder shall provide the necessary interlock of the
pumps from the same as per flow diagram.