Work Order Title Excavated Material Recycling and Storage CH 45+500 to CH 71+900
(Coastal Desert West)
Revision No. 01
1 0 - 6 0 3 1 1 0 - 0 0 0 0 1 0 0 2 0 1 - M A H - C I V - M S T - 0 0 0 0 0 0 – R e v. 0 1
Date
23 / 03 / 2 0 2 4
Excavated Material Recycling and Storage
CH 45+500 to CH 71+900 (Coastal Desert West)
Document History
Revision 01
PROJECT TITLE
Excavated Material
Recycling and Storage CH
45+500 to CH 71+900
(Coastal Desert West)
CONTRACT NO. 100201-WO-061
2 Purpose
The purpose of this method statement is to provide safe sequence of installation activities of the
fixed crusher (MESTO) into designated location, ensure all works are executed in accordance
with related drawings, and NEOM specification.
3 Reference Documents
➢ The Project Manager is responsible for all construction activities including ensuring
that all safety measures are implemented, and permits are obtained from the
relevant authorities connected with the scope of work.
➢ Construction Manager and Project Engineer in-charge are responsible for the
implementation of this method statement pertaining to all early site preparation civil
construction activities.
➢ Supervisor / Foreman will closely supervise the activities assigned to them and
ensure that all instructions are followed, and all necessary work permits are in place
prior to commencing the work and safety procedure of the project are strictly adhered
to.
➢ Safety Manager is responsible for the enforcement of all internally developed and
used, as well as external safety procedures and shall ensure that all the works
carried out are done in strict compliance to minimum standards as set out by NEOM
as well as where procedures does not exist, best practice.
➢ The QA/QC Manager is responsible to manage the quality requirements are properly
implemented and maintained on site as per project quality requirements.
➢ The surveyor is responsible for carrying out pre-construction survey to fix the
locations and corresponding elevations as per the approved Drawings.
➢ Other Manpower are Laborers, safety officers, applicable, fleet safety coordinator &
driver.
6 Tools and equipment
360
H H
100
390
12200
CONCRETE BLOCK (customer supply)
130
800
170
320
330 340
G G
CONCRETE WALL (customer supply) A-A ( 1 : 250 )
300
Position of electrical bungalow
(excluded : supply by customer)
230 D-D ( 1 : 150 )
19/25
320 V= Around 275m3
310 330
350
290
F F
370
D 380
240 360
65m
10/19
200 V= Around 570m3
205 DRAWING FOR PRELIMINARY STUDY
210 plan de pr - tude
270
D
E DRAWING NOT VALID FOR BUILDING PERMIT E
410 plan non valide pour permis de construire
390
260
250 DRAWING ISSUED FOR PROPOSAL PURPOSE
180 PLEASE NOTE THAT THIS DRAWING IS NOT
CERTIFIED FOR CONSTRUCTION
plan d livr pour proposition
merci de noter que ce plan n'est pas certifi pour la
construction
280
DRAWING NOT VALID FOR BUILDING PERMIT
plan non valide pour permis de construire
100 110 120
D 400 D
430 420
ITEM QTY DESCRIPTION
430 1 NC 650x20m
5800
0/5
V= Around 275m3 420 1 NC 500x20m
5/10 410 1 NC 650x25m
V= Around 275m3 400 1 CVB 2661-3
390 1 NC 800x30m
160 170
0/250 380 1 NC 500x20m
Volume live = around 1500m3 370 1 NC 650x20m
Volume total = around 6000m3 360 1 CVB 2060-2
130 190 350 1 NC 800x33m
A A 340 2 HP 300
C 330 2 METAL DETECTOR C
320 2 NC 650x20m
43m
310 2 VIBRATING FEEDER
140 300 1 HOPPER 60m3
290 1 NC 800x28m
280 1 NC 650x29m
270 1 NC 500x18m
Position of electrical bungalow 260 1 NC 650x20m
(excluded : supply by customer) 250 1 CVB 2661-4
240 1 NC 1000x38m
65m 87m 230 1 HP 400
210 1 METAL DETECTOR
150
205 1 FIXED PERMANENT SORTING MAGNET
200 1 NC 1000x55m
B 190 2 VIBRATING FEEDER B
180 1 CONCRETE TUNNEL (customer supply)
170 1 NC 1000x55m
WALKWAY FOR CONVEYORS ARE 160 1 NC 800x20m
150 1 NC 650x20m
OPTIONAL EQUIPMENT 140 1 DF2016-P
130 1 NC 800x19m
120 1 C120
REV DESCRIPTION OF REVISION BY APPD DATE 110 1 VF 561-2V
03 INITIAL RELEASE ABE/YBO 23/03/2023 100 1 PRIMARY HOPPER
TITLE DRN: macberthal
WASTE PRELIMINARY LAYOUT
RESTRICTED
V= Around 250m3 DATE: 23/03/2023
RVWD: MATERIAL No: N/A
MATERIAL Spec.:
60 m3
17 167
583 2 x 30 m3
2 1 167 2 1
242 242
17 242 242
HP300 HP300
std fine std fine
0/5mm Stroke 84 mm Stroke 84 mm
Setting 20 mm Setting 20 mm
500 Speed 950 rpm Speed 950 rpm
242 242
540
HP400 COMPACT CVB2060-2
std extra coarse SEP 25 mm
484 SEP 19 mm
Metallic mesh
Stroke 95 mm Metallic mesh
49 64
Setting 45 mm 1
Speed 850 rpm 64
540
64
2
COMPACT CVB2661-4
SEP 56 mm 371 COMPACT CVB2661-3
SEP 19 mm SEP 15 mm
540 SEP 10 mm SEP 10 mm
Metallic mesh 450
SEP 5 mm SEP 5 mm
Metallic mesh Metallic mesh
Metallic mesh 40 Metallic mesh
Anticlogging mesh
40 Anticlogging mesh 118
303 1
99 129
47 95
99 2 60
28
1
50 108
47 2 19
158 95 247
3. Survey coordinates are fixed for the overall area, and of the foundations required for
the crusher process line equipment’s (Jaw Crusher, Conveyor lines, Cone crushers, &
screens) installations.
4. The installation personnel shall be familiar with the structure, performance and
technical specification of the machine, comprehend the necessary operation rules and
make the proper installation instructions in advance.
5. A suitable depth and size of trenches are excavated and well compacted to receive
these RCC foundations.
6. Reinforcement, formwork, and concrete activities are carried out as per requiredRCC
foundations dimensions(A separate approved document “Method Statement for
Formwork, Reinforcement and Concrete-10-603110-0000100201-MAH-CIV-MST-
000010” will be used for these activities)
7. All these structural installations throughout the installation process are strictly
monitored and examined for line, levels, and proper fixations.
1. Proper curing is done to the casted RCC Structures to gain strength to receive any
load over it.
2. A proper backfilling for these foundations is done till the existing ground level or as per approved shop
drawing.
3. A proper and stable base pad is prepared for mobilization of mobile cranes for the
lifting activities.
5. All the lifting activities are strictly adhered to the approved lift plan with all the proper
pre-lifting inspections, third party certifications and competent personals are
availability to proceed with lifting.
6. An approved adequate lifting plane shall be followed for any lifting activities for the
entire installation of crusher process.
7. Adequate Dust control measures will be used (Guards provided as required). (For
details, please refer Sec 9 Environmental Requirements.)
7.4. Installation Process & Sequence of Primary Part (MESTO Fixed Crusher)
1. Installation of stairs and handrails with the help of scaffolding and temporary handrails.
2. Feeder structure installation by Carne lifting
Two feeders (420Kg each) will be installed in the Tunnel. Pallet jack will be used to bring
them inside the tunnel then use a crane to lift them to an accurate position. The
conveyor’s frames will be carried inside the tunnel with pallet jacks or similar.
7.6. Installation Process & Sequence of JAW Crusher C120 (MESTO Fixed Crusher)
JAW Crusher
7.7. Installation Process & Sequence of Cone Crusher H300 & H400 (MESTO Fixed
Crusher)
• Make sure the foundation is perfectly levelled.
• Countershaft Installation: When installing the countershaft, ensure the axial position of the bearing relative to the
counter shaft, and pad gasket between the pedestal and the counter shaft frame flange.
• Eccentric Shaft Installation: Before the installation of the eccentric shaft, install the gasket on the bottom cover,
place the bottom cover on the lower end of the frame with the hook, and then install the lower round plate and the
round plate on the bottom cover in sequence with the hook.
• Bowl Bearing Installation: The bowl bearing frame shall be closely matched with the base, and the tightness of the
horizontal contact surface shall be checked with a feeler gauge. After the bowl bearing is installed, cover the bowl
bearing with the cover plate immediately.
• Installation of mantle bearings and mantle parts
• Adjusting Ring Installation: The adjusting ring consists of hopper, thread ring, fixed cone liner and other
components. The cone-shaped liner plate and the thread ring contact through the cone surface. During installation,
place the cone-shaped liner plate, place the thread ring on it, place the flange on the thread ring, clamp the snap ring
on the outer neck ring of the cone-shaped liner plate, and then screw down the bolts one by one, repeatedly and
symmetrically. After the fixed cone liner plate is installed, the parts such as the pressing iron, the sealing ring and the
hopper will be installed.
• Locking Device Installation: Determine the position of the locking device and the support ring, screw in the
adjusting ring, and adjust to the appropriate position to obtain the appropriate discharge port. Ensure that the locking
device is parallel to the support ring.
• Lubricating Device Installation: The lubricating device must be configured to ensure smooth lubricating oil inlet
and return.
• Installation of Adjusting Device
• Installation of Feeding Device
Cone Crusher
7.8. Installation Process & Sequence (Screens of MESTO Fixed Crusher)
• Installation of base-mounted machines: Standard base-mounted machines are furnished with pedestal-type
support bases, which can be mounted on and secured to either structural steel or reinforced concrete. The concrete
or steel supporting structure must be leveled and plumbed. Use shims between the supporting structure and the
spring bases to level the machine if necessary.
• Installation of Coils springs
• Placing the screen on the coils springs
• Checking spring deflection
• Tightening bolts and checking the tightness
• As per Layout, we have 19 conveyors which will be installed for MESTO Fixed Crusher with total length 515m.
• Maximum length of truss for lifting will 22m
• As per Layout,11 conveyors have 22m length or lower which will be assembled on the floor then these 11 conveyors
will be installed lifted by Crane.
• As per Layout,7 conveyors (which are more than 22m in length) will be pre-assembled in two parts then both parts
will be lifted by crane in 2 two steps and connected with a boom lift. The supports will be lifted by an additional crane
or forklift.
• 1 conveyor (170 – Prestock) will be pre-assembled in 3 parts then lifted in 3 steps with 2 cranes and trusses
connected with a boomlift. The supports will be lifted by an additional crane or forklift.
8.0 Safety Requirements
1) All personnel involved in the above activities shall follow the pre-task briefing
requirements and MAH Project Safety Plan.
2) All safety measures and Internal Company Safety Procedures shall be implemented
in alignment with NEOM Standards Where applicable, barricades, warning signs or
safety signs shall be fixed around the construction area as per NEOM Standards.
3) If at all necessary, special work permits (as applicable) shall be obtained prior to
commencing any work
4) All earth moving equipment shall be operated and maintained by Qualified and
approved personnel.
5) All work areas shall be kept clean and tidy during work activities.
9) All relevant personal Protective Equipment (PPE) shall be provided and worn by all
personnel when entering the construction site.
9. Environmental Requirements
2) Any items which are non-compliance with this MST shall be recorded through a Non-
Conformance and Corrective Action Report.
3) As per NEOM Environmental & Social Sustainability Code of Practice (NEOM ECP-
PMEF), the following parameters should be monitored as specified below:
• MAH to produce monthly report for product output and resources usage such as
water and fuel.
• The HSE coordinator on site shall monitor emissions at least three times per shift and
record the findings in his daily report.
• Ambient boundary monitoring for a 30-min average of PM10, PM2.5, noise and wind.
The results for particulate matter and gaseous emissions will be compared against
the limits set by the General Authority of Environmental Protection rules and
regulations 2012.
• The location of the monitoring will be on the outer boundaries of the workplace,
down wind.
For a quick reference, the following table contains the limits set out by the local authorities
pertaining to particulate matter and gaseous emissions:
Table 1 Monitoring Parameters for air quality & noise
Environmental Personnel
Identify the source, investigate the causes and propose remedial measures.
1) Commissioning plant trials must be witnessed by NEOM and approved prior to the
operations.
2) All equipment and operators shall have a valid 3rd party certificate and shall submit to
OSH and Environmental department prior to mobilization.
3) All Equipment shall be thoroughly checked by the Equipment Inspector and approved
prior to mobilizing the equipment at the work site.
4) All the Equipment operators and Drivers shall undergo a training from Environmental
department or approved 3rd party training providers if required in below mentioned topic
but not limited to.
• Causes of Smoke emission in equipment.
• How to use equipment in Eco Friendly manner?
• Oil Spill Response.
• Noise.
• SASO Standards
5) All the workforces shall undergo Environmental Induction and Emergency Response
plan training.
9.3 Management and Maintenance
1) Equipment shall be used and operated in an optimal condition; Equipment shall be fit
for purpose and free of defects, leaks, excessive dark atmospheric emissions.
3) Implement an effective preventative maintenance program for all plant and equipment;
Spares and consumables - in particular, those subject to continual wear –are held on
site, or available at short notice from guaranteed local suppliers, so that plant
breakdowns can be rectified rapidly.
5) Records of all maintenance activities shall be held on file for audit by NEOM
Environment.
6) To perform any kind of Maintenance activity a prior approval shall be taken from
Environmental department and if needed from EPM.
8) Appropriate measure shall be taken as per the NEOM standards to prevent any kind
of spill during maintenance.
➢ Preventive maintenance programs are the best method for keeping a crusher in good operating
condition for a long period. preventive maintenance activities for crushers are as list below:
➢ Predictive maintenance refers to monitoring the condition of the rock crusher while it is in
operation. Predictive maintenance tools such as these aid in providing visibility on:
9) Any kind of routine Maintenance work shall not be carried out at the work site. Oil
Change Activity shall only be carried out on concrete/Protected surface.
10) Only emergency maintenance shall be allowed provided that all precautionary
measures are undertaken, including, and not limited to:
➢ drip trays
➢ spill kits
➢ ground protection
➢ proper training.
11) All waste oil generated shall be safely disposed as per NEOM standards.
12) Environmental Department will use a WTN, and log record all waste oil generated.
13) To prevent any spill of Hydrocarbons all the equipment shall always carry a drip tray.
14) All Equipment shall be inspected by Equipment Inspector prior to mobilization to the
work site.
15) For any Maintenance activity the equipment shall be carried out of the Work site to a
Saudi Government Approved workshop.
16) After the Equipment is serviced, it shall be re inspected by the Equipment Inspector
and get approval from Environmental Department prior to starting work.
9.4 Training
1) Ensure all crusher plant staff whose functions could have an impact on the
environment, are competent to operate plant, equipment and processes; and they
are aware of their responsibilities under the Accord.
2) An environmental training program shall be implemented, which shall include
environmental induction, spill prevention, emergency spill response, actions to be
taken in the event of process malfunction.
3) Training records of all environmental training shall be held on file for audit by NEOM
Environment.
4) CAN Shall be notified to responsible person through email & cc to PM, CM & Senior
Management. Such email conversations shall be retained and made available as
records for audit by NEOM.
5) The non-compliance will be checked during the next daily site inspection, or earlier.
Progress will be noted until the action has been satisfactorily completed.
7) MAH will prepare and maintain an internal audit schedule. Records of the
environmental audit activities are subject to audit by NEOM Environment and will be
available / produced upon request
2) Copies of specific incident response procedures and emergency contact details willbe
posted in higher-risk areas (HAZMAT Storage Facilities; Bulk Fuel Storage
Facilities, etc.).
3) Emergency response equipment will be kept in stock at the location where higher risk
activities are being carried out. The emergency response equipment will be labelled and
have simple directions for usage.
5) Materials Safety Data Sheets (MSDS) will be available for each chemical or fuel thatis
used, in an accessible location at the storage and usage areas.
6) Emergency response training and awareness will be carried out for staff involved in
activities that have higher environmental risk, including the use of emergency
response equipment. Training details will be recorded in the Training Register.
8) Emergency response equipment will be regularly checked to ensure its readiness inthe event of an
emergency situation.
9) A schedule for Emergency drill shall be submitted to the Client.Emergency drills shall be
conducted every 6 months.
10) Emergency Drill shall cover environmental emergency scenarios including but not
limited to: (Minor Oil Spill Response, Adverse weather condition, Equipment Break
down.NEOM representative shall be invited for Emergency drill.
11) Within 48 hours of the drill conducted a detailed report shall be submitted to NEOM.
Lessons learned and suggestions for improvement shall be incorporated in the next
Drill.
2) Fuel-powered generators shall be placed within concrete bunds. If the Operator is unable to
provide a concrete bund; metal spill trays are permissiblein exceptional circumstances,
based on the Contractors justification as to why concrete bunds are not possible to
construct.
3) Spill kits shall be provided at all spills sensitive locations (bulk fuel storage areas,HAZMAT storage
facilities, HAZWASTE storage facilities, generators, workshops,warehouses, sewage storage
tanks) on site and shall be always available to handle spills and leaks.
4) Spill kits shall be clearly labelled and placed at prominent locations in all spills sensitive locations.
5) Spill kits shall be regularly inspected to ensure that they have adequate stock of spillresponse
materials.
6) Used items from a spill kit shall be disposed of as hazardous waste and promptlyreplaced.
7) Dispose of or recycle oil and oily wastes in accordance with the waste managementstandards.
8) Place secondary containment drip trays under any static plant or equipmentcontaining fuel or other
hazardous liquids.
9) Any spillages into the secondary containment drip tray shall be treated as hazardouswaste.
10) Persons involved in fuel transfer activities and operations shall have received specifictraining to do
so. Records of such training shall be held on file by MAH for audit by NEOM Environment.
12) Where fuel bowsers cannot be used for refueling, Jerry cans and manufacturedfunnels shall be
used for fuel transfers.
13) A suitably sized drip tray and ground protective sheet shall be placed under thereceiving vehicle’s
refueling point prior to starting pumping of fuel.
14) All fuel spills that meet or exceed reporting thresholds shall be reported to NEOMEnvironment.
15) All fuel transfers shall be conducted using a fuel nozzle which are equipped with sensors (inside
the nozzle) that senses the back pressure and shuts off, preventingany overflow.”
16) Fuel storage at the work site will not be allowed (Only in area Approved by NEOM)
17) All the fuel storage refueling shall be carried out in accordance with MAH Equipmentrefueling
procedure
2)Where dusty materials are conveyed, the conveyor and any transfer points shall be
provided with adequate protection against winds.
3)Where chevron belts are used, catch plates shall be fitted to contain dust falling from
the underside of the belt at the turning point.
4)Where the design of the conveyor allows free fall of material to occur, techniques
shall be used at the point of discharge to minimize this, for example the use of a
chute or similar equipment.
6)The boundaries of stockpiles shall be clearly marked with physical markers, such as
posts, to limit the potential lateral spread of stockpile storage areas.
7)Where access to stockpiles is NOT required for a period longer than 7 days, the
stockpile must be covered with netting or similar material to minimize wind erosion.
8)Vehicle speeds on temporary access and haul roads shall be regulated to 30km/h (or
less when material is prone to being disturbed or windblown).
10) All temporary access and haul roads shall be regularly dampened down with
waterusing a water suppression truck.
11) All trucks transporting bulk friable materials shall be covered with a suitable
tarpaulinsheet or similar when in motion.
12) Trucks transporting bulk friable materials shall NOT be overfilled. Truck loads
shallNOT be filled within 300mm of the top of the trucks dump box.
13) Water cannons and/or misting systems shall be provided to control dust
emissionsassociated with material handling and crushing and screening works.
14) 1 Water tankers shall be provided to all the work areas as backup for controlling
dust.Number of water tanker used in the dust suppression work shall be logged.
15) Water shall be collected only from NEOM approved water sources. The number
andsize of stockpiles shall be kept to a minimum.
16) All temporary access and haul roads shall be regularly dampened down with
waterusing a water suppression truck.
18) To ensure that there is a constant source of water for crusher 1 water tanker with the
capacity of 30 cubic meters will be dedicated as backup in addition to water bladders
available for Dust Suppression.
19) Water and Dust may cause slurry to avoid over sparing of water a person will be
assigned to log and monitor the dust control activity.
20) An Environment officer will be assigned in the site location for visible inspection to
ensure there is no dust emissions in the work site. In Addition to that PM 2.5 and PM
10 will be monitored and logged as per NEOM standards.
1) Conduct emissions monitoring for vehicles, plant or stationary equipment used onsite
and ensure that they comply with NEOM Environment emissions standards.
2) All vehicles and plants used during the works shall be maintained to ensure optimal
performance and that no excess exhaust emissions are emitted. MAH will keep
records of all maintenance activities on file, for audit by NEOM Environment.
3) All vehicles, plant or stationary equipment shall be operated by qualified and skilled
personnel.
4) Spill kit material shall be suitable for the specific purposes they are assigned to □
chemical spill kits shall be used in chemical storage locations and fuel / oil spill kits
used in fuel / oil storage/ distribution areas.
7) Empty drums and containers are NOT permitted to be present on site and shall be
removed.
8) Empty containers shall be either recycled or disposed of as hazardous waste.
9) Damaged, leaking or empty drums and containers shall be removed from site, clearly
marked (using spray paint) as leaking / defective and appropriately disposed of.
10) All spilled chemicals and hazardous materials shall be collected and treated as
hazardous waste and removed from site.
11) All chemical containers and hazardous materials shall be appropriately labelled
identifying its contents, quantity, and hazard / risk warning information.
12) Incompatible chemicals and hazardous materials shall not be stored together.
13) All waste fuel, oils and hydrocarbons shall be stored in closed topped container and
removed from site.
14) All waste fuel, oils, and hydrocarbons, but while in use at work locations, shall not be
placed within 50 meters of bodies of water (the coastline).
2) All works and ancillary activities (such as heavy vehicle movement and material
deliveries) that are audible at the site boundary shall be carried out during designated
daytime hours unless otherwise approved by NEOM Environment.
5) Materials shall be handled with care and gently placed in loading / storage areas.
Conduct noise monitoring at the site boundaries.
6) Plans shall be in place to deal with any noise complaints during the Processing plant
operation. Investigate noise complaints immediately and records kept for audit by
NEOM Environment.”
7) All vehicles, compressors and mobile equipment shall be equipped with effective
silencers and noise reducing insulation.
8) All plant, machinery and vehicles shall be fitted with appropriate mufflers are
maintained in good working order.
9) Maintenance and servicing of noise mitigation on plant, equipment and vehicles shall
be done in accordance with manufacturers recommendations.
11) All the manufactures recommendation for controlling noise in the equipment shall
beadhered.
12) All the covers of the equipment shall be in place during operations.
9.14 Waste Management
4) All bins shall be available at required locations on site and clearly labelled, identifying
their intended contents.
7) All skips containing light-weight waste shall be covered at all times with a net to
prevent light waste becoming airborne and escaping the skip.
12) Littering and the generation / accumulation of litter on site shall be prevented.
13) Bins containing food waste, shall be fitted with close-fitted lids.
14) Waste bins and skips shall be regularly inspected to ensure that they are in a good
state of repair.
15) Waste bins and skips that are damaged beyond unreasonable wear and tear shall be
removed from the project and replaced with equivalent containers.
16) A waste tracking system is used, Waste Transfer Note (WTN) or similar.
17) WTN’s shall include a full description of the waste, the total quantity being
transferred, the date of transfer, the waste recipients name, and any other relevant
information.
18) All waste records shall be always available for audit by NEOM Environment.
Each employee will be issued with personal protective equipment as set out in the Safety
plan and internal PPE issuing procedure and enforcement of the wearing of the PPE will be
done according to procedure. Specifications for personal protective equipment shall comply
with the relevant minimum construction site standards.
Hard Hat: Employees are responsible for wearing hard hats with chin straps during any work
activity that is conducted on heights, and where possibility of head injury is present. The
hard hat must be worn when working within a construction site.
Safety Vest: High visibility apparel (vest, shirt, or jacket) of orange, strong yellow- green or
fluorescent versions of these colors must be worn whenever working within any highway
right of way or on a construction site.
The following is the minimum personal protective equipment that will be provided to
employees:
RISK ASSESSMENT
RISK ASSESSMENT FORM
Site
• Ensure all workers have undergone SUPERVISOR
safety induction and obtain HSE
necessary permit on the job.
• Ensure that the group is wearing
required PPE and High Visibility
Vest.
• Provide flagman to guide the
• Hit, Struck by a moving equipment’s or motorist and barriers and safety
1 Site Preparation • vehicle. signs to protect the survey group
4 3 12 High 2 2 4 Low
Survey Works • Slips trips and fall from being hit of the moving
• Severe weather condition, Sand storms equipment or vehicle.
rain etc. • Monitor local weather forecast of
• Back injury during manual handling of possible high wind or storms that
materials. might arise during the work.
• Proceed directly to the emergency
vehicle if signs of rain, storm or
sandstorm is arising.
• Conduct training or toolbox
regarding manual handing hazards
• prior to start the work.
• Ensure a proper permit is obtained SITE
prior to start of activities. SUPERVISOR
• Ensure that the equipment working HSE
have proper valid certification
inspection, no defect and safe to
• Personnel Hit and struck by moving use.
equipment. • Verify underground utilities, and
• Damage mechanical parts of the existing nearby structures that are
Excavation
equipment will result in oil leak in the area of scope of work
works for the 4 3 12 High 2 2 4 Low
and contaminate the environment. and adhere proper requirements
2 foundations.
• Damage Underground utilities during and coordination.
excavation. • Ensure that the operator has a
• Incompetent / unauthorized operator valid competency certificate and
doing the job which resulted into a tragic have enough experience to
accident. undertake the activities.
• Provide safety sign and barricade
to isolate the area and illumination
during nigh time.
SITE
• Ensure to provide proper flat form SUPERVISOR
and access when working elevated HSE
area with guardrails and toe
boards.
• Fall from height. • Wear safety harness and provide
• Improper posture and overreaching proper guardrail system when
3 Steel Fixing and resulting into a back injury. working at height at about 1.8
4 3 12 High 2 2 4 Low
Formworks. • Hand Injury. Meters.
• Eye injury. • If excavation 4 feet height a
• Pinch Points. confine space entry procedure will
• Working in a deep excavation where be followed.
there is insufficient of air and possible • Proper protective system inside the
accumulation of toxic gas. excavation must be provided when
• Excavation cave in. the classification of soil poses high
• Slips, trips, and fall. risk hazard,
• A design ramp for access and
egress must be provided in the
excavation.
• Keep distance on the moving SITE
equipment and in the pumping SUPERVISOR
pipe. HSE
Concrete
4 • Hit by a moving concrete pump pipe • Provide varication and signs t avoid
Pouring of the 4 3 12 High 2 2 Low
during the uncontrolled movement when unauthorized entry of personnel 4
Formworks
pouring of concrete. from the work area.
• Hit by moving equipment. • Proper PPE as per required must be
• Contact with cement chemicals. provided and used to avoid being
• contact with the cement.
• Watch out for the moving SITE
equipment obtain proper safe SUPERVISOR
distance. HSE
Rigger
• Provide competent rigger during
• Hit by a moving equipment. lifting activities to ensure that the
• Fall of load. orientation of lifting gears to the
load is safe and secured.
Assembling of • Crane Outrigger positioned on uneven
5 surface during lifting process. • Conduct Pre inspection of crane
Parts 4
4 4 16 Very prior to use, any sign of defects 2 2 Low
mechanism via • Lifting equipment’s failed and crane tip
must be reported to supervisor for
lifting of crane • over due to High wind High
repair.
• Contact with Overhead powerline.
• Ensure proper distance will be
• Unauthorized entry walking underneath
obtained from the overhead power
the suspended load.
line before lifting.
• Fall from height.
• Provide varication on the work
area to avoid unauthorized entry in
work area.
SITE
• Provide proper guard rail on the SUPERVISOR
edge of the flat form where there HSE
is a risk of falling, wear additional
PPE safety harness attached with a
lifeline anchored 100% at all times.
• Fall from height • Provide fire watcher in the area
Welding works
6 • Fire during welding activities.
at elevated area
• Electrocution • Ensure that the Welding 4
and bolt 4 4 16 Very 2 2 Low
• Ergonomics injury resulting from equipment used is inspected and
tightening High
improper manual lifting of materials. safe to use.
• Using defective tools and improper • Wiring connections must be
positioning leads to back pain properly secured.
• Over exertion • Maintain proper posture during
welding and avoid overreaching.
• Maintain proper posture during
manual handling of materials. Keep
the load near to the body.
• Do not defective tools
CM, SITE
• Ensure to provide proper flat form and SUPERVISOR
access when working elevated area with HSE
guardrails and toe boards.
• Maintain proper back posture during
manual handling of materials.
Installation of
• Fall from height. • Wear safety harness and provide proper
utilities, air
7 • Back injury, during manual handling of guardrail system when working at height
system, electrical,
materials. 4 3 12 High at about 1.8 Meters. 2 2 4 Low
lighting fixtures
• Electrocution. • Provide proper access removed unwanted
and water line.
• Hand injury. materials in the area.
• Slips, trips, and falls. • Wear proper hand protection gloves that
suitable for the Job.
SITE
SUPERVISOR
• Ensure the safe platform for the erection
HSE
of crusher and hot work.
• Ensure proper cable management.
• Ensure welding machines, cords and
cables are in good conditions.
• Flash Burns during welding operations. • Ensure that the permit is issue as per
• Unsecured wires that have splices and client/ main contractor procedures.
8 Welding lead to electrocution • Ensure the fire extinguisher media are in Low
4 3 12 High 2 2 4
activities • Slips trips and fall place.
• Ergonomics problem
• Ensure certified and competent welders.
• Fire and explosion
• Ensure fire watcher for each welder.
• Ensure safe platform and safe access /
egress of scaffold while work at height.
• Ensure regular supervision of hot work
activities.
SITE
• Cranes must be certified and fit for SUPERVISOR
intended operations. HSE
Rigger
• Cranes must be positioned on level ground
which has been assessed as suitable for
the subjected load bearing capabilities.
• All outriggers must be fully extended, and
the cranes blocked and levelled as per
manufacturer’s instructions.
• The cranes must be configured to the
manufacturer specification.
• Only personnel assessed as competent are
permitted to operate the cranes.
• Barrier off the work site area and restrict
access to unauthorized personnel.
Suspended loads must not be transferred
Use of • Por maintenance of equipment and over personnel at any time throughout the
mobile rigging hardware that leads to lifting operation.
9 Very
crane for failure and resulted to an accident. 4 4 16 • The cranes safe load indicator must be 2 2 4 Low
High
lifting • Fall of unsecured load calibrated and be accurate to within the
• Severe weather condition manufactures recommended tolerance.
• The cranes safe operating radius must not
be exceeded.
• The cranes must be operated smoothly,
and all necessary precautions taken to
ensure the crane is not subjected to
“shock loading”
• The crane operator must adjust the safe
load indicator accordingly to ensure the
cranes are not unintentionally overloaded.
• Cranes must be operated within the
manufactures always designed parameters
during the operation.
• The designated Supervisor shall be
responsible for overseeing the operations.
SITE
• Task Briefing shall be given to all workers SUPERVISOR
to start of activity and hazards HSE
• Could suffer from back pain and work-
communicated.
related upper body disorder (WRULD)
• All workers shall go to site safety
due to
induction prior to mobilization at site.
• Using incorrect handling techniques
• Labor involves in cleaning activities shall
when cleaning at site)
Manual Handling be briefed regarding safe lifting
10 • Poor body position when working at 4 3 12 High 2 2 4 Low
techniques.
site resulting in poor posture.
• Individuals with back pain and other
• Individuals with health conditions,
injuries shall not be allowed to work.
previous back injuries etc. affecting
• Workers shall be provided with mandatory
ability to safely handle items.
and task-related PPE.
Probability (P)
3 Possible 3 Lost time injury or permanent disability 2 2 - Low 4 - Low 6 - Medium 8 - Medium 10 - High
Single fatality or permanent disability of 15 – very
4 Likely 4 3 3 Low 6 - Medium 9 - Medium 12 - High
3 or more people High
20- very
5 Very Likely 5 multiple fatalities 4 4 - Low 8 - Medium 12 - High 16 -very High
High
25 – very
5 5 - Medium 10 - High 15 – very High 20- very High High
Reference Table in completing Section III – Job Safety Analysis (Column F – Risk)
Very high - 4 4 8 12 16 20
Additional control measures must be implemented to further
reduce the High and very high risk to acceptable level.
high - 3 3 6 9 12 15 Note: The Construction Director/Manager or Facility Manager
must personally review the activities with a High or Very High
2 4 6 8 10
Medium - 2
residual risk score and approve suitable additional control
low - 1 1 2 3 4 5
measures by signing the risk assessment.
Appendix 2. Fixed Crusher Location & Crusher Components
The crushers’ location refers to below scope location overview for Work Order No.61.
NEOM Environment
Project N
SECTION 1 -
Contractor
ame: Report by:
Note to Contractors - Guidance regarding this Checklist 11.2.4 Are marine environments unaffected by Contractor activities?
11.2.5 Are coastal systems unaffected by Contractor activities?
1. Contractors shall conduct Daily Environmental Inspections of their work locations using this form.
11.2.6 Are pollution risks to the marine adequately controlled?
2. Contractor shall seek out activities and conditions on site which allow them to respond to each question detailed on this
11.2.7 Are vessel / equipment movement risks in the marine environment adequately controlled?
checklist
3. For each question listed on the checklist, enter Yes or No in the relevant cell.
4. Any questions that generate a 'No' response, the Contractor shall rectify the site condition that was observed to be non- Rev.0
compliant with the checklist question.
5. All completed Daily Environmental Inspection Checklists must be retained by Contractors for au dit by NEOM
Environment.
Page 48 of 71 10-603110-0000100201-MAH-CIV-MST-000004_02