Professional Documents
Culture Documents
NASS CONTRACTING
DOCUMENT NO: 110310-C.8.1-003
PROJECT TITLE:
DOCUMENT TITLE:
METHOD STATEMENT
STRUCTURAL PILES
Main Contractor is advised to please reflect all signatories responsible in the preparation, review
and approval of the Method Statement submittal from Main Contractor's side and include the
name and the date to be specified. Please ensure that this information is supplied in the
subsequent Method Statements to be submitted.
SIGNATURE:
Page |2
Nass Contracting Co. W.L.L Doc. 110310-C.8.1-003
PROJECT: BAHRAIN MARINA DEVELOPMENT Rev. 00
METHOD STATEMENT: STRUCTURAL PILES Date: 13 August 2023
Table of Contents
1. SCOPE ................................................................................................................................................ 5
2. REFERENCE ....................................................................................................................................... 5
3. DEFINITION ........................................................................................................................................ 5
4. RESPONSIBILITIES ........................................................................................................................... 5
5. RESOURCES ...................................................................................................................................... 8
6. DEFINITION ........................................................................................................................................ 8
6.4 Auger................................................................................................................................................. 10
7. STEPS OF WORK............................................................................................................................. 12
Page |3
Nass Contracting Co. W.L.L Doc. 110310-C.8.1-003
PROJECT: BAHRAIN MARINA DEVELOPMENT Rev. 00
METHOD STATEMENT: STRUCTURAL PILES Date: 13 August 2023
Page |4
Nass Contracting Co. W.L.L Doc. 110310-C.8.1-003
PROJECT: BAHRAIN MARINA DEVELOPMENT Rev. 00
METHOD STATEMENT: STRUCTURAL PILES Date: 13 August 2023
1. SCOPE
This Method Statement is to describe the methodology for execution of Structural Piles for the
PROPOSED PILING AND SHORING WORKS AT BAHRAIN MARINA PHASE 1 & ZONE 3, to be constructed by
Bahrain Foundation Construction Company.
This is also developed to make concerned people familiarized with the sequence of activities, utilizations
of resources and relevant risk assessment to meet project specifications & contractual obligations.
This task will be carried out on the approved location in conjunction with the shop drawings/authorizes
approved drawings developed for the project.
2. REFERENCE
Institution of Civil Engineers, Specification for piling and Embedded Retaining walls 1996.
BS 8002: 1994 Code of Practice for Earth Retaining Structure
BS 8004 ‐ Code of Practice for Foundations
BS 8110 ‐ Structural Use of Concrete
MOW specifications Module 2019, Edition 2
Volume 2 ‐ Special Specifications Rev.D 2.2.2.
Project IFC Drawings
Approved shop drawings of piling work Please that piling Design Calculation has been approved
prior to commencement of the Piling Installation.
3. DEFINITION
4. RESPONSIBILITIES
Overall Responsible for implementation of the company management systems, policies, and
procedures in line with Project Specification, Drawings, Method Statements, Control Mechanism
and Quality & HSE Programme.
Preparing and monitoring a resources plan for the whole project duration in coordination with the
site team.
Page |5
Nass Contracting Co. W.L.L Doc. 110310-C.8.1-003
PROJECT: BAHRAIN MARINA DEVELOPMENT Rev. 00
METHOD STATEMENT: STRUCTURAL PILES Date: 13 August 2023
The name and contact number of the Project Engineer including the site staff who will be working for the
4.2 Project Engineer installation of the structural piles shall be submitted and coordinated with the Supervising Consultant Engineer.
The Project/Site Engineer shall ensure that the activities are being executed in accordance with legal
requirements.
The Project/Site Engineer shall ensure that legal approvals and permits, which are in BFCC’s
responsibility are received.
Project/ Site Engineer shall be sure of the provision of the required PPE as well its suitability for the
job and compatible with standards by the HSE Officer assistant.
Project/ Site Engineer with Safety shall maintain waste manifests and submit to HSE.
Ensuring that the quality of materials and the installation of work are in accordance with the criteria
identified for the project.
Identify and take the necessary corrective action to improve the progress and I or quality of work.
Ensure that all the works are carried out as per the specification and the related quality procedures
and QA/QC plan.
Overseeing quality related activities to control all non‐conformances to avoid occurrence in any
construction activities.
Inspect all activities while requesting and gaining the approval of the Client/Main Contractor team
(mainly inspectors).
Maintain inspection and test records complete for any future reference.
Verify and confirm casting of piles as per program of work and sequence.
Ensure all tests done comply with engineer's requirements and specification. Report all test failed
conducted by laboratories and to hold all activities that do not conform to contract specifications.
Engineer shall sign all requests for inspection prior to submittal of the same to the engineer's
Inspectors.
Prepare, control, and administer inspection and test plans, method statements and checklists and
other quality requirements in conjunction with the project quality.
Record for any NCR internal & external and copy furnish to the Engineer.
Maintain a log of all NCR's as well as follow up closure of all outstanding of NCR.
Page |6
Nass Contracting Co. W.L.L Doc. 110310-C.8.1-003
PROJECT: BAHRAIN MARINA DEVELOPMENT Rev. 00
METHOD STATEMENT: STRUCTURAL PILES Date: 13 August 2023
HSE Officer shall submit daily observation reports and incident reports to the Project Engineer.
Coordinate the safety activities between the Client/Main Contractor and Subcontractor.
Review and approve the subcontractor safety program and procedures, advice and recommend any
corrective actions necessary.
Patrol the work site periodically to verify that the work is carried out under safe conditions, with no
violations of safety requirements.
Advice promptly the supervisors and workers of corrective action when any unsafe conditions or
violations are observed.
Maintain the published safety literature, safety regulations, codes and other communications in
accordance with contract. Advise management of compliance and conditions requiring attention.
Conduct independent audits to ensure conformance with the established safety program and
determine the effectiveness of individual elements of the program.
Check each work procedure from the safety point of view and coordinate with the project Engineer
before commencement of work and, or while working.
Check on the use of all types of personal protective equipment, evaluate effectiveness and suggest
improvements.
Make thorough analysis of the statistical data through inspection, delineate problem areas, and
make recommendations for solutions.
Make sure that suitable personal protective equipment is available and in use.
Ensure that new employees attend safety induction and are properly instructed in precautions to be
taken before they are allowed to start work.
4.4 Surveyor
Reporting to Project Engineer and to receive all layout plans and approved drawings.
Coordinate with the project team and guide the team to execute the job as per the approved
layout.
Responsible for the settings out of coordinates of the working piles and ensure the required
accuracy. Any deviations of the plant‐as‐built coordinates shall be recorded and forwarded to the
Client/Main Contractor.
Responsible for the as built coordinates/ locations to be incorporated on the as‐built drawing prior
to proceeding with any activities.
Page |7
Nass Contracting Co. W.L.L Doc. 110310-C.8.1-003
PROJECT: BAHRAIN MARINA DEVELOPMENT Rev. 00
METHOD STATEMENT: STRUCTURAL PILES Date: 13 August 2023
The workforce shall attend daily Toolbox Talks and morning task briefs prior to starting any new
work.
The workforce shall receive a full Project briefing and site rules induction prior to commencing any
work on site.
5. RESOURCES
5.1 Manpower
Site Engineer – 1 no.
HSE Officer – 1 no.
Surveyor – 1 no.
Foreman – 1 no.
Technician (Mechanic) – Various
Electrician – Various
Labors – Various
6. DEFINITION
Page |8
Nass Contracting Co. W.L.L Doc. 110310-C.8.1-003
PROJECT: BAHRAIN MARINA DEVELOPMENT Rev. 00
METHOD STATEMENT: STRUCTURAL PILES Date: 13 August 2023
6.3 Casing
Steel tube used to maintain stability of a pile excavation in unstable ground.
Page |9
Nass Contracting Co. W.L.L Doc. 110310-C.8.1-003
PROJECT: BAHRAIN MARINA DEVELOPMENT Rev. 00
METHOD STATEMENT: STRUCTURAL PILES Date: 13 August 2023
A steel casing shall be used to support the wall of the drilled hole during drilling in the dry
construction method of a pile.
When the process encounters water bearing or caving soil formation a temporary casing is placed
into the impervious formation to seal the pile bore from water‐bearing and unstable strata.
6.4 Auger
Tool consisting of a stem, helical flights and cutting edge or edges for intermittent excavation.
P a g e | 10
Nass Contracting Co. W.L.L Doc. 110310-C.8.1-003
PROJECT: BAHRAIN MARINA DEVELOPMENT Rev. 00
METHOD STATEMENT: STRUCTURAL PILES Date: 13 August 2023
P a g e | 11
Nass Contracting Co. W.L.L Doc. 110310-C.8.1-003
PROJECT: BAHRAIN MARINA DEVELOPMENT Rev. 00
METHOD STATEMENT: STRUCTURAL PILES Date: 13 August 2023
Material Inspection Request (MIR) to be submitted for all materials delivered to the site.
7. STEPS OF WORK
7.1 Surveying
Setting out of works must be according to Project specification. At the start of the contract,
benchmarks are checked jointly with the Engineer and levels in the tender drawings are verified
accordingly in relationship to surveying department data.
For ease of reference in daily activities, temporary benchmarks are established and protected on
site. A layout drawing showing the location, coordinates, and values of these benchmarks shall be
produced, duly signed, and submitted to the Engineer for the future records.
At the beginning, setting of the lines is carried out to check all possible obstructions prior to
commencement of construction.
Surveying records must keep up to date as they will form the basis for as built records of the works
done on site in conjunction with inspection request.
The construction site should be prepared prior to the commencement of the work.
Ensure safe mobilization by following the safety control measures as determined in the approved
RA.
P a g e | 12
Nass Contracting Co. W.L.L Doc. 110310-C.8.1-003
PROJECT: BAHRAIN MARINA DEVELOPMENT Rev. 00
METHOD STATEMENT: STRUCTURAL PILES Date: 13 August 2023
Mobilize the drilling rig(s) and cranes after getting the required permit to carry out the construction
of the piles.
Locate the position of the pile and put an identification number referring to approved drawing.
The surveyor shall make sure that all the surveying equipment is calibrated, and valid calibration
certificates are available throughout the execution of the work.
Temporary benchmarks/control points shall be established on the site and shall be protected from
all the disturbances.
Pile center points will be marked as per the approved construction shop drawing.
Main Contractor should have specified in the Method Statement the preferred methodology for Pile
driving casing either by method Option 1 or method Option 2. The Method of pile driving shall be further
8.3 Construction of Structural Piles clarified by the Main Contractor at site prior to the commencement of pile casing installation.
The working platform is prepared at an appropriate level. The piling rig will be positioned at the
platform level.
Rig’s auxiliary hook shall lift the casing and place it into the adopter of the Kelly bar.
Position the casing exactly on the survey setting out/ pile center mark up.
The rotary head then twist the casing downward till top of the casing is approximately 500mm to
P a g e | 13
Nass Contracting Co. W.L.L Doc. 110310-C.8.1-003
PROJECT: BAHRAIN MARINA DEVELOPMENT Rev. 00
METHOD STATEMENT: STRUCTURAL PILES Date: 13 August 2023
During driving, the verticality of casing shall be monitored with the help of spirit level (1m length) at
every 2m interval, and the position of casing shall be continuously monitored with reference to the
reference pins.
The casing shall be driven up the position of hard strata and terminated. The placing and depth of
the casing shall be varying from place to place depending on the soil condition.
The casing vibrator then clamps the casing securely into the jaw area.
Position the casing on the previously identified pile location pin (with position being ascertained
with respect to the previously placed reference pins).
The casing vibrator is then switched on to vibrate the casing to pre‐determined depth level (into
hard strata).
During driving, the verticality of casing shall be monitored with the help of spirit level and the
position of casing shall be continuously monitored with reference to the reference pins.
During driving, the verticality of casing shall be monitored with the help of spirit level (1m length) at
every 2m interval, and the position of casing shall be continuously monitored with reference to the
reference pins.
Care must be taken that the casing is vibrated securely into hard strata.
Drilling will be carried out using drilling rigs at working platform elevation mentioned in IFC
drawings.
The auger is attached to the Kelly bar of the rig and lowered inside the casing to start the drilling.
The spoils accumulated in the auger during the boring process will be lifted to discharge it outside
the bore.
During the process of boring the soil condition changes on every layer, when the auger is no longer
suitable to pick up loose and wet soil, it is raised and replaced with the drilling bucket. The drilling
bucket is designed to bore with its teeth at the bottom and contained the loose soil on its
cylinder/bucket.
P a g e | 14
Nass Contracting Co. W.L.L Doc. 110310-C.8.1-003
PROJECT: BAHRAIN MARINA DEVELOPMENT Rev. 00
METHOD STATEMENT: STRUCTURAL PILES Date: 13 August 2023
The drilling bucket is lifted, and the spoils are discharged outside the casing.
The process of boring is repeated with the method above until pile toe level is reached as per
approved Drawing.
The top of casing and pile location will be checked again by the surveyor and counter check by the
engineer representative for reference.
Depth monitoring will be checked using meter tape with dead weight attached at the end of the
tape to ensure the pile length.
All reinforcement shall be clean and free from materials that may cause corrosion of the
reinforcement.
Binding wire shall be approved, and it shall be free from dust and other contaminants.
Reinforcement cages will be fabricated in the fabrication yard as per the requirement.
Fabrication will be carried out with minimum reinforcement cover as per the approved shop
drawing.
MIR (internal inspection by Nass QA/QC Department) shall be raised and secured approval
immediately after delivery of the cage to site, prior to use.
After the inspection the cage is lifted by the crane and lowered in the center of the casing down the
pile borehole.
Cages shall be provided with the spacers to maintain the clear cover as per the approved drawing at
min. 3 nos. every 3.0m c/c.
Tremie pipe shall be cleaned of all encrusted concrete or mortar prior to use it.
The tremie pipe shall be extended to the bottom of the pile toe and lift it 75cm at the
commencement of the concreting.
P a g e | 15
Nass Contracting Co. W.L.L Doc. 110310-C.8.1-003
PROJECT: BAHRAIN MARINA DEVELOPMENT Rev. 00
METHOD STATEMENT: STRUCTURAL PILES Date: 13 August 2023
Once the boreholes have been inspected and approved, the concrete shall be poured directly into
the boreholes by way of a tremie tube from the mixer truck fastened to a concrete pump.
The concrete must be poured without any interruption to avoid previously poured concrete from
hardening and a cold joint forming.
Test of fresh concrete shall be carried out by an independent testing laboratory for every concrete
delivered at site. All fresh concrete shall be at all approved check points.
The tremie tube should be withdrawn gradually throughout the concreting process.
The removal of the casing will be carried out using a power pack vibratory hammer which is carried
by the crane. The hammer jaw will be connected to the casing and then the extraction will start
using the crane.
Care must be taken not to exert too much pull prior to the loosening of the casing.
During the continued extraction a sufficient quantity and head of concrete shall be maintained to
balance the external pressure so that the annular space vacated by the removal of the casing is
filled with the concrete.
Careful visual inspection is carried out to ensure that the casing is extracted in the vertical position.
Flagman & banks man shall be assigned for vehicular movement within the site.
Two Tag lines will be provided with all loads while lifting/shifting with crane.
In addition to their safety induction received on their arrival on site, all workers will have a toolbox
meeting and be briefed about the risks of their specific work task, prior to start of works. A relevant
risk assessment is attached.
All personnel must require wearing basic personal protective equipment (PPE) and those exposed to
vehicular traffic shall always be provided with a warning vest marked with or made of reflectorized
or high visibility material as an additional safeguard.
P a g e | 16
Nass Contracting Co. W.L.L Doc. 110310-C.8.1-003
PROJECT: BAHRAIN MARINA DEVELOPMENT Rev. 00
METHOD STATEMENT: STRUCTURAL PILES Date: 13 August 2023
Starting instructions will be given by the HSE officer before the start of each activity to explain the
methodology of work and to communicate safe working procedures to the operatives. These talks
are structured in a way to highlight the major risks involved in the activity and the various control
measures required to minimize the risk. It is delivered in a manner such that the key points will be
remembered by the operative receiving it.
Weekly toolbox talks will be held for each crew, on group of employees, regarding more general
topics of the project HSE Policy, for example: lesson learned near miss report, implementation of
the requirements and message from the management, an Engineers, and HSE personnel.
The area in which workers are exposed to danger shall provide safeguards, including warning signs,
barricades, and temporary fences as required for the protection of the public and site personnel
during demolition and removal operations. The safeguards are to be maintained until the
demolition and removal operations are complete.
Operations in a manner that minimizes the spread of flying particles and dust. Rubbish and debris
shall be sprinkled with water to keep dust to a minimum. Also, to carry out regular housekeeping to
maintain a clean and safe working place for the workers.
10. Environmental
All personnel should follow the health requirements and maintain a good housekeeping on site.
All equipment and materials used on site will be correctly stored. Oil, fuel, sewage spillage from
motorized equipment will be avoided by placing adequate catch/retention basin/dip tray & spill kit.
Dust control using ground water from the nearest extraction point.
Main Contractor should have specified in the Method Statement the area where the Piling inert waste
materials are disposed. Main Contractor to further clarify the disposal area prior to the commencement of
piling installation.
P a g e | 17
Nass Contracting Co. W.L.L Doc. 110310-C.8.1-003
PROJECT: BAHRAIN MARINA DEVELOPMENT Rev. 00
METHOD STATEMENT: STRUCTURAL PILES Date: 13 August 2023
APPENDIX A
Inspection and Test Plan (ITP No.: 110298‐L.8‐002)
P a g e | 18
PROJECT: BAHRAIN MARINA DEVELOPMENT ITP No. : 110310‐D.9‐003
Inspection Requirements
No. Activity/Test Reference Document Acceptance Criteria Frequency Controlling Documents
Third party S/C Nass Engineer
5 Steel casing installation. True Verticality +/‐2mm All Piles ‐ P W S Daily Report
Approved Method statement
Verify the dept of the drilled Approved Shop Drawing Depth of each pile in compliance with the
9 All Piles ‐ P W H Internal Inspection Request
contiguous pile. Approved Method Statement approved toe level of the pile
page 1 of 3
PROJECT: BAHRAIN MARINA DEVELOPMENT ITP No. : 110310‐D.9‐003
Inspection Requirements
No. Activity/Test Reference Document Acceptance Criteria Frequency Controlling Documents
Third party S/C Nass Engineer
Rebar installation as per the approved
Drawing
Inspection of cab beam rebar Approved Shop Drawing
13 All Piles ‐ P W H Internal Inspection Request
prior to casting Approved Method Statement Level of the cab beam as per the approved SD
page 2 of 3
PROJECT: BAHRAIN MARINA DEVELOPMENT ITP No. : 110310‐D.9‐003
Inspection Requirements
No. Activity/Test Reference Document Acceptance Criteria Frequency Controlling Documents
Third party S/C Nass Engineer
R Review of Documents, means Review document, which includes the review of quality control records, test reports, etc.
H Hold Point , is a mandatory verification point beyond which a work cannot proceed without approval by the Engineer or Consultant or Municipality
S Surveillance, is monitoring and verification of the status of conditions, procedures, to ensure that the established requirements are being complied with
W Witness point, is point in the process where the Eng. or Consultant may review, inspect method or process of work. The activities however may proceed
P Perform the activity
page 3 of 3
Nass Contracting Co. W.L.L Doc. 110310-C.8.1-003
PROJECT: BAHRAIN MARINA DEVELOPMENT Rev. 00
METHOD STATEMENT: STRUCTURAL PILES Date: 13 August 2023
APPENDIX B
Risk Assessment
P a g e | 19
Risk Assessment Report (B)
STRUCTURAL PILES
Task
5 5 10 15 20 25 Likelihood Severity
OHS-C1-001-001-R00
Rev.:00 Page 1 of 9
Correct manual handling techniques
Manual handling assessment completed for high-risk tasks
MOBILIZATION/TRANSPORTA Obtain the necessary relevant documents, drawings and permits
TION OF EQUIPMENT AND prior to commence the activity.
MATERIALS HSE Induction, daily toolbox talks and other trainings in line with the
task to be conducted before commencing of activity.
(Contact with existing services / Approved Risk assessment shall be conveying with all site
utilities during site grading, operatives
clearance and preparation – Full supervision to be deemed ensuring work shall be carried out in a
Engineer & Site
Main contractor scope) 2 4 8 safe manner. 1 4 4 Yes
supervisor
Carry out survey to confirm depth and line of existing utilities (utilize
suitable survey equipment relevant to the scope and scale of the
work (By main contractor).
Dig trial pits to locate underground services (by Main Contractor).
Mark the line of underground services to ensure visibility to all
persons working in the vicinity (By main contractor).
All required permits shall be taken prior Permits to works
Sufficient cool drinking water will be provided to site operatives and
MOBILIZATION/TRANSPORTA available at the workplace all time
TION OF EQUIPMENT AND Adequate Rest Shelters with mist/industrial fan shall be provided.
MATERIALS Lone working is highly restricted " buddy system" should be applied.
Heat stress training shall be conducted to the operatives with
(Exposure to hot weather, regards to the awareness and associated risk of hot weather Engineer & Site
Lightning, and Rainy season) 2 3 6 1 3 3 Yes
Emergency standby vehicle shall be always provided at site supervisor
Work will be stopped in adverse weather conditions.
All DB, equipment’s & Machine shall be protected against rainwater
All DB's must be protected and covered with polyethylene sheet to
prevent electrical shocks.
All generators to be correctly earthed & grounded.
A site logistics plan shall be prepared and submitted
This plan shall provide with detail of site boundary, pedestrian and
vehicle access, site roads, parking, laydown areas and temporary
MOBILIZATION/TRANSPORTA structures.
TION OF EQUIPMENT AND Traffic management signage and lighting shall be installed, as
MATERIALS necessary.
3 4 12 Trained Flag man / Banks Man shall be deployed to control heavy Engineer & Site
1 4 4 Yes
Pedestrian accident, vehicle earthmoving equipment’s or while reversing the equipment supervisor
accident and properties damage Safe pedestrian access/ walkways shall be provided and marked
separately for site pedestrians.
Barriers shall be installed to separate pedestrians from vehicle
traffic.
Pedestrian routes shall be clearly marked and illuminated where
necessary.
OHS-C1-001-001-R00
Rev.:00 Page 2 of 9
MOBILIZATION/TRANSPORTA Barricading shall be in place once the mobilization is completed.
TION OF EQUIPMENT AND HSE Induction and other training requirements conducted by NASS.
MATERIALS Trade test/third party certifications is required.. Equipment inspection
2 2 4 Engineer & Site
and approval by a third party. 1 2 2 Yes
supervisor
Unauthorized entry to site. Signages shall be posted to avoid unauthorized personnel entry (No
Entry Trespassers keep out, Mandatory PPE and Emergency
Contact Numbers etc.)
MOBILIZATION/TRANSPORTA
Competent Operator shall be deployed to operate the Equipment’s
TION OF EQUIPMENT AND
while offloading, Moving/reversing the equipment.
MATERIALS Trained Flag man / Banks Man shall be deployed to control heavy
equipment’s or while reversing the equipment.
Equipment Accident while
3 4 12 Safe pedestrian access/ walkways shall be provided and marked Engineer & Site
offloading, Movement of 1 4 4 Yes
separately for site pedestrians. supervisor
Equipment/Material Manually &
Barriers shall be installed to separate Equipment’s from vehicle
Mechanically traffic.
Pedestrian/Equipment routes shall be clearly marked and illuminated
where necessary.
MOBILIZATION/TRANSPORTA
TION OF EQUIPMENT AND
MATERIALS Suitable means to dispose of waste (rubbish bins)
Housekeeping shall be carried out and supervisor/HSE officer shall
Lack of waste management / Engineer & Site
2 3 6 ensure the waste material is removed from site at the earliest 1 3 3 Yes
waste facilities supervisor
opportunity.
Log sheet shall be maintaining for all disposal of waste from the site.
OHS-C1-001-001-R00
Rev.:00 Page 3 of 9
Unstable / Uneven Ground. machines.
Unauthorized entry of Ensure the exclusion zone shall be maintained all the time.
personnel. Adequate illumination in the workplace and Banks’s man must be
Slip, trip, and fall. available all the time to control the movement of the equipment.
Struck by equipment and Reverse rotates the auger cleaner when necessary to control the
object. direction of spoil.
Incompetent operatives. Toolbox talk must be conducted regularly for the refreshment of the
Poor maintenance and involved operatives with regards to safe working procedures and the
defective equipment. Oil associated risk of the piling operation.
spillage Unauthorized personnel are restricted to enter the piling rig operation.
Checklist shall be maintained and filled daily, and the operator shall
report if found/observed damage/defective equipment accessories.
Housekeeping should be maintained, and all unwanted materials
shall be removed immediately to prevent slips, trips and fall hazards.
All workers involved in the piling zone area should wear the
mandatory PPE if exposed from noise earplug must be worn all the
time.
All mock soil materials should be kept in a designated dumping area
before removal at the site.
All operatives shall wear earplugs all the time if expose from noise.
Ensure flagman are available all the time to control the movement
of equipment.
Housekeeping and a removal of unnecessary materials shall be
conducted regularly.
PILING REBAR CAGE
During lifting for rebar cage installation no one can stand in the
INSTALLATION
suspended load and 2 tag lines must be maintained.
The third-party certificate of the equipment, lifting accessories,
Sharp Edges of the rebars.
rigger, and operator shall be obtained before commencing any
Caught in between steel
lifting activity.
cages. Engineer & Site
2 3 6 The area must be cordoned off all the time to prevent the 1 3 3 Yes
Incompetent operators. supervisor
unauthorized entry of personnel.
Unsafe lifting procedure.
Any protruding rebar shall be protected by a rebar cap.
Poor supervision.
START talk shall be conducted towards the rebar cage installer.
Suspended load. Borehole
opening Falling of loads NO one can stand beneath the rebar cage while lowering, a safe
distance should be applied and maintained.
A mandatory PPE is to be worn all the time.
Before do lifting a rigger and supervisor should check the lifting
point of rebar cage are made available as per approved MS.
No bore left open, it must be guarded and covered with steel guard
mesh.
OHS-C1-001-001-R00
Rev.:00 Page 4 of 9
Avoid standing nearby the concrete pump or concrete delivery truck.
Assign require the number of workers to avoid the crowd or
congested work area.
Make sure an adequate number of lights are installed to avoid poor
illumination.
CONCRETE POURING Maintain good housekeeping and provide safe access.
Ensure the equipment has safety guards for all rotatory parts.
Inspect the concrete pump delivery hose is properly secured with
Concrete Splash. Awkward
clamps.
Posture.
Avoid usage of damaged rubber delivery hose to prevent concrete
Inadequate safety guards. Engineer & Site
3 2 6 splash. 1 3 3 Yes
Chemical burns from wet supervisor
Provide plastic sheets under the backend kit to avoid concrete spills.
concrete
Assign flagman for assisting the vehicles during reversing / night work
Slip, Trip, and Falls.
concrete pouring.
Equipment rolls over.
Provide appropriate PPEs like gumboot, clear safety goggles, rubber
Poor illumination. Concrete hand gloves, and protective clothing, etc...,
Spillage.
Ensure the first aider is always available on site
Provide polyethelene sheet & bunding around the concrete barricade
around the concrete barricade around the site to avoid Nass-Huta JV
barriers became dirty during piles and concreting work
OHS-C1-001-001-R00
Rev.:00 Page 5 of 9
Appropriate PPE should always be used.
Use mobile scaffolding on level and stable ground only.
Wheels of mobile scaffolding should be locked while use.
Access ladder should be through inside the scaffolding.
OHS-C1-001-001-R00
Rev.:00 Page 6 of 9
Use correct posture and ensure mandatory PPE must be worn all
the time.
Avoid repetitive motion and operative must know about the hazard
of the activities
If lifting manually is unavoidable use the mechanical equipment or
PILE SURFACE CLEANING ask someone to enable to break and distribute the
load.
Exposed from dust Only 20 kg can lift by one worker as per legal requirements.
Noise Adequate supervision for the intended task must be provisioned.
Sharp and flying object. Provision of Instructions, Information, Prestart meetings shall be
Engineer & Site
Incompetent personnel. 3 2 6 conducted before commencing the activity. 1 2 2 Yes
supervisor
Not wearing required PPE. Use proper manual handling techniques.
Heat exhaustion The area must be clear from any obstruction of materials and all the
Poor supervision and unnecessary materials to be removed at the workplace.
control of equipment Ensure all protruding pile rebars must be protected with a rebar cap.
Slip, trip, and fall The provision of safe access and egress must be maintained all the
time.
If equipment must be used for the removal of pile concrete debris,
ensure all valid documents must available upon request and
approved, inspected by clients.
Only competent person is allowed
Ensure adequate lighting arrangements are provided before darkness
NIGHT WORK & LIGHTING as per the planned activities which will take place during nighttime.
ARRANGEMENT Ensure sure all tower lights located at the planned work area have
sufficient diesel to function at night.
Check all the tower lights bulbs by the experience, competent
Insufficient light. Slip, trip, electrician to ensure that the bulbs are in good condition.
and fall. Ensure suitable fire extinguishers are provided. Engineer & Site
3 3 9 1 3 3 Yes
Unprotected borehole Avoid unwanted/unrequired movement of vehicles during night work. supervisor
opening. Provide a trained bank man to direct the equipment.
Uneven surface. Avoid unauthorized personnel entering a site without any coordination
Fire and explosion. Lack of and permission by project site management.
firefighting equipment. Poor Ensure all the new operatives must attend site induction training.
electrical management. Avoid storing/stacking the materials on the access.
Maintain a good illumination level on the access and worksite.
ENVIRONMENTAL IMPACTS Performing authorizes are required to adhere to Safe working
Procedures.
Extreme Temperature Chemicals to be used shall be stored as per the Manufacturer Data Engineer & Site
4 2 8 2 2 4 Yes
Storage of Chemicals sheet. supervisor
Oil Spillage from Any Oil Spillage should be controlled using Drip tray and removed
Equipments using Spill kit.
OHS-C1-001-001-R00
Rev.:00 Page 7 of 9
Appropriate PPE should always be worn.
Minimum manual load on workers
Provide plenty of cold drinking water at work location.
Close supervision around the working area.
Ensure surrounding sea is kept tidy and waste spillage should be
avoided.
Check the availability of third-party certificate for the Crane,
Operator, Rigger & all lifting tackles.
Make sure the lifting operations done by competent crane operator
& riggers and certified by third party.
Check for tag lines, 2 no. must be used to control the load and
avoid hitting any plant facility like pipelines and equipment. • Avoid
lifting the load when wind speed exceeds the allowable wind speed
as per the crane manufacturers’ recommendations.
Follow the crane load chart for lifting any load.
Ensure the ASLI (automatic Safe Load Indicator) is operative and
crane operator must not lift any load out of the load chart limit.
LIFTING ACTIVITY
Check the Crane is positioned in a stable ground.
Provide barricades and proper signage to keep unauthorized
Equipment may overturn
personnel away from the lifting area.
due to bad Ground
Avoid personnel standing under the suspended load.
conditions, Overload
/Stability. Stop the activity where there is a possibility to hit the adjacent
structure during lifting operations. Engineer &
Incompetent Operator, 3 4 12
Rigger Equipment inspection checklist to be filled in by operator prior to 1 4 4 Site Yes
commence a lifting activity. supervisor
Weather conditions
Ensure pre-task/pre-lift meeting must be conducted by the in-charge
Substandard Equipment
supervisor.
Failure of lifting
Ensure lifting gears inspected before using and color-coded in a line
gears/accessories
to monthly color coding.
Ensure the capacity of the lifting gears is more than 70% of lifting
capacity.
Any damaged/defective lifting gears and accessories must not be
permitted to use at site.
Visual thoroughly inspection must be conducted before rigger will
use it and if found irregularities must be reported to the site
supervisor.
Site supervisor must be visible and pro-active all the time as the
lifting commence
Crane setup procedure to be complied with outrigger and outriggers
fully extended & on adequate outriggers pads.
No unloading operations to be performed in adverse weather
OHS-C1-001-001-R00
Rev.:00 Page 8 of 9
conditions.
Lifting activity Shall be stopped if the Wind speed is more than the
Crane Manufacture allowable limit.
Use softeners at the sharp edges of the load to be lifted.
All the damaged, wear/tear lifting accessories will not be used for
lifting.
A proper record of every tool & tackles shall be recorded and
provided on-site.
Assessment
Designation Signature Date
Conducted by
Main Contractor is advised to please reflect all signatories responsible in the preparation, review
and approval of the Risk Assessment report enclosed from the Method Statement submittal.
Please ensure that this information is supplied in the subsequent Risk Assessment Reports.
OHS-C1-001-001-R00
Rev.:00 Page 9 of 9