Project Name EPCC of CPF-OIL Treatment System and Auxiliary System Project Package No. 1310-U135--FG-HT-002

Job Code. System No. U135--FG


Area / Unit CPF/ 135 Date of Inspec. 24-Apr-24
Cat.* Issued Verified by
No. DWG No. Description
(A/B/C) by CAMCE QC PMC/PMT

1 General Flange Management Report to be attached B

2 General Reinstatements to be done after hydro test as per UID B

3 General Touch-up Painting to be done B


All non-destructive testing (NDT) should be checked according to the requirements of
4 General A
line class

Remarks

[*Legend] Category "A" : Must be Cleared before Pressure Test Category "B" : Must be Cleared before Pre-commissioning Category "C" : Must be Cleared before Final Accetance

CONSTRUCTION CAMCE QC PMC/PMT


Name Panneerselvam
Position QA/QC
Signature
Date 24/04/2024