itp tank rapp
itp tank rapp
1. 3 Welder Qualification
ASME Section IX,
ASME IX WPQR I A A
WPS,Drawing,Welding Map
sheet 1 of 4
ATTACHMENT - 1
sheet 2 of 4
ATTACHMENT - 1
2.2 Foundation
a.Levelness Visual
b.Center Point & Radius Levelness, Centerpoint
Drawing, Tolerance, Client Spec API 650 I/D A A
c.Flatness & Slope Flatness & Orientation Report
d.Orientation
e.Anchor Bolt & Etc
2.3 Visual Check after welding for each parts Approved Drawing, Weld Map .API 650 API 650 Welding Control Record I R RW
sheet 3 of 4
ATTACHMENT - 1
3.1 Finishing
Client Spec, Drawing S.O.P Client Spec, Drawing S.O.P Pickling & Pasivation
a.Cleaning
I RW RW
3.2 Punch List Client Spec, Drawing S.O.P Client Spec, Drawing S.O.P Punch List Report
3.3 Manufacturing Data Report ( MDR ) Client Spec, Drawing Client Spec, Drawing MDR D R R/A
Note : Abbrevation
1. Complete operation must be sign off and dated ITTU = Indoteknik Tjandra Utama Legend : D - Document I - Inspection R - Review
H - Hold Point W - Witness M - Monitoring
RAPP = PT.RIAU ANDALAN PULP & PAPER A - Approval RW - Random Witness
sheet 4 of 4