Average Hours Total Days a Production Workers No.

Average hours Total Manpower per day


Office Staff No.
worked per day week Worked Per day
GENERAL Manager 1 9 5 Carpenter 40 440
PROJECT Manager 2 18 5+6 Steel Fixer 22 242
Planning Engineer 1 9 6 Mason 7 77
Civil Site Engineer 2 18 6 Labor/Helper 7 77
MEP Coordinator 1 9 6 Electrician 3 33
QA/QC Engineer 1 9 6 Painter 3 33
Safety Officer. 1 9 6 Mechanic -
Civil Forman 2 18 6 Plumber 1 11
Document Controller 1 9 6 Crane Operator 1 11
Office Boy/Cleaner 1 9 6 Rigger 1 11 Office staff=22
Driver 4 36 6
Security/Watchman 2 24 6 Labor=935/9
Surveyor 1 9 6 =104
Surveyor Asst. 1 9 6
Store/Time Keeper 1 9 6
Safety Officer. Assistant - 104+26
Electrical Forman -
Plumb. Forman -
Total 22 Total=213 hours Total 85 Total=935 hours 126