PROZEAL GREEN ENERGY PRIVATE LIMITED

Document
Name:
Installation Checklist for AC Cable
Location. : Project Name.: GSECL 14MW SPV Project
Issue No.: 1 Revision No.: 0
Issue Date: 18-01-2024 Revision Date: NA

Type of
Characteristics/ Check Status
Brief about Parameter check details Acceptance Norms OK/Not Remarks
(Visual,
operation Mech, Ok
Tech.)
1) Unloading from vehicle

2) Verification of quantity & identification


1 Unloading
3) Package Inspection Visual NO Physical Damage.

4) Reporting of damage/ missing items

The storage area shall be non-


flooded. All Cable drums
preferably stored on wooden
pallet for transportation so as to
Store handling Visual avoid direct Mechanical hit with
sharp objects, store in such a
way so that easy material
movement / trolley movement/
material access.

Ensure the availability of


required tools as per
2 Visual
Tool availability Tools like jacking arrangements, rollers etc. manufacturer's instruction
manual

Ensure route for laying of cable


Visual as per drawings & proper
3 Cable routing Survey
clearances and avoid sharp
edges

Visual Ensure route for laying of cable


Excavated land / Trench / Conduits, Cable as per drawings
crossing

Visual Ensure excavated land is


dressed properly to avoid loose
particle back fill, Conduits free
from obstacles.
PROZEAL GREEN ENERGY PRIVATE LIMITED
Document
Name:
Installation Checklist for AC Cable
Location. : Project Name.: GSECL 14MW SPV Project
Issue No.: 1 Revision No.: 0
Issue Date: 18-01-2024 Revision Date: NA

Cable installation area should be


Installation area to meet
Installation Area suitable for Cable drum
Cable drum size & other activity placement.
Cable drum shall be lifted as per
Jack the drums by using proper material
3 Installation- handling equipment and position the
Visual the guidelines given in
Drum handling Manufacturing manual, to avoid
drum in place.
any damages.
Pull cable through proper
pulling arrangement. Cable
Pull cable from end Visual
Cable pulling shall not be pulled from end
without having intermediate
arrangement.

HT cable shall be laid on


bottom most. The power
cable should not be laid
Cable laying & above the
4 Cable laying on direct ground Visual
Dressing telecommunication cable.
Power, control &
communication cable shall
be laid in separate layers
with
proper space
HT cable shall be laid on Top
most tier and subsequent
Cable laying on trays Visual lower voltage grades on
lower tiers on
cable trays.
At joints and terminations
bending radius for the individual
Visual
5 Cable bending radius to be maintained cores should be above 12 times
Cable bending
properly to avoid cable excessive heating the diameter over the
insulation.
The desired minimum
6 Space between Power and communication Visual
Cable spacing clearances between cables shall
cable
be as per IS 1255 Clause 6.3.3
PROZEAL GREEN ENERGY PRIVATE LIMITED
Document
Name:
Installation Checklist for AC Cable
Location. : Project Name.: GSECL 14MW SPV Project
Issue No.: 1 Revision No.: 0
Issue Date: 18-01-2024 Revision Date: NA
Cable shall be held at both
7 Visual sides firmly and cutting shall be
Cable cutting Cable cutting using proper tools
done using proper tool to avoid
insulation & conductor damages
Power & control cable shall be
secured fixed to trays with self
8 Visual
Securing of cables Cable to be firmly secured to trays locking type straps. Single core
cable in Trefoil formation shall
be clamped at every 2 mtr.
Cables shall be laid as per IS
9 Visual 1255 Clause 6.3.4 with proper
Road crossing Protection of cables in road crossing
identifications & warning
markers.
Jointing kit to be from approved
10 Joints & Visual
Straight through joints and Termination source. Qualified jointer to do
Termination
the activity.
- Cable tags shall be provided at
both ends of corners.
11 Cable tags shall be provided for
Tagging - Cable Sleeve to be
identification
provided along with Color
code of the
Incoming & Outgoing Phases.
Route marker shall be marked
12 Route Indicators should be provided at legible (letters preferably in red
Route marking
regular interval color) for power and
communication cable.
Metallic sheath / screen &
armour of multi-core cables
13 Earthing Earthing of sheath/screen & armour shall be earthed at both ends,
Single core cables shall be
earthed at one ends

Checked By Witnessed By Witnessed By Witnessed By


Signature
Name
Date
Company