Professional Documents
Culture Documents
(Option 2 is the choice of the architect I’ve interviewed tho he did not elaborate on how to
do it)
• Option-2 For instance: Compute all the volume of the following
• Column-footing, wall footing, columns, tie beams, roof beams, lintel beams, slab
• Estimate the quantity of the following: Cement, Sand, Gravel, water
• Compute for labor cost
Division-4 Masonry
• Materials: Masonry
• Cement+sand+water=Mortar/Grout/plastering
• CHB, Reinforcement
• Option-1 square meter method (cement+sand+water+chb+rebar)
• 120 sq.m. x (210+30+5+120+300) = Php. 161,425.00 materials
• 120sq.m. x 300/sq.m. = Php. 36,000.00
• 161,425.00+36,000.00=Php. 197,425.00
(the Architect I interviewed used the sqm method too, he says its much more reliable)
Division-5 Metal
• Materials: Metals
• Reinforcing bars, G.I. wires
Compute all rebars for Column-footings, wall footings, columns, tie beams, roof beams,
lintel beams, slab
• 230 pcs 16mm bars x 325/pc =74,750.00
• 391 pcs 10mm bars x 130/pc=50,830.00
• 45 pcs 12mm bars x 220/pc=9,900.00
• 150 kgs #16 G.I wires x 60/roll= 9000.00
• Total material 184,580
• Labor cost 24,893.00
• Sub-total 209,473.00
Division-6 Wood, Plastic and Composites
• Materials: Wood
• Ceiling Joists, Eave Ceiling, and Ceiling Boards
• Compute all Materials
• 85 length SPANDREL x 200/pc= 17,000.00
• 60 sheets 1/4" THK HARDIFLEX CEMENT BOARD x 380/pc= 22,800.00
• 200 length DOUBLE FURRING x 85.00/pc= 17,000.00
• 50 LENGTH WALL ANGLE x 40.00/pc= 2,000.00
• 35 LENGTH CARRYING CHANNEL x 120.00/pc= 4,200.00
• 1 PCS. DIAMOND BLADE x 500.00/pc= 500.00
• 5 PCS. DRILL BIT x 60.00/pc= 300.00
• 9 KGS. PANHEAD SCREW x 560.00/pc= 5,040.00
• 15 KGS. 1" HARDISCREW x 560.00/pc= 8,400.00
• 4 KGS. 2" METALGYPSUM SCREW x 400.00/pc= 1,600.00
• 2 KGS. CONCRETE NAILS NO. 1x 60.00/pc= 120.00