BOQ SUMMARY

Project Name: 11 Atienza

Element :  Beam

No. Material Unit Quantity Rate $ Cost $


1 Concrete C28 (cum) 4.00 4350.00 17393
Sub Total 4.00 17,393

2 Rebar #10 (Fy276) (kg) 393.35 22.00 8654


3 Rebar #12 (Fy276) (kg) 4.95 22.00 109
4 Rebar #16 (Fy276) (kg) 532.12 22.00 11707
Sub Total 930.42 20,469

5 Shuttering (sq.M) 39.99 100.00 3999


Sub Total 3,998

Grand Total 41,861

Design Metrics
1 Consumption : Reinforcement/Concrete ratio = 232.69 kg/cum
2 Consumption : Reinforcement/Planarea = 11.63 kg/sqm
3 Consumption : Concrete/Planarea = 0.05 cum/sqm
4 Concrete % C28 = 100.00 % 
5 Shuttering  = 10.00 sqm/cum