You are on page 1of 13

SIEMENS Hazard Identification and Risk AssessmentEM / IM/EHS-4.3.1/PR/01 dt. 11.06.

2018 EM

Division: - GP SD SPT BU / BS: - SPT Project /Factory Name: - Reliance Idc(132KV swith yard modification) Doc No: GP SD SPT/HIRA/Siemens001/19

Project Site Location/Factory Location: - Ril Mouda,Nagpur Rev: 0

Scope of Work: - 132 Kv Switch Yard modification work

Persons involved: - PM - Fenil Trivedi, Asst. PM - Site in-charge - Sachin patil, EHSMiP - Nagendra babu, Contractor -Hi-Tech electrials & Protech Electrials

Likelihood of Occurrence of Hazardous event or exposure (OH&S) & Likelihood of Env


Aspect. Hierarchy of Control Measures
OH &S Risk/environment Impact Rating Matrix
R = SxL

never will (<5

circumstances.
Could happen,

Could occur at

Almost certain
occur at most

occur in most
% possibility)

Will probably
but probably

Expected to

possibility)
Elimination 1

(> 90%
Likely
Rare

some time
Unlikely

times
Severity (S) Substitution /Reduction at source 2

Engineering Controls/
OHSAS 18001 : Occur. Health & Safety ISO 14001: Environmental Impact (Scale, Severity & Duration of Impact) 1 2 3 4
Conservation/Reuse/Recycle/Treatment
3

Minor environmental incident (leakage, spillage, waste of resource etc) within the
Low Low Low Admin Controls
First Aid Case/temp Illness/Near Miss Incident of less severe in workplace & not lasting for more than 1 shift. Or, conservation of natural Medium (Acceptable
1 (Acceptable & Non- (Acceptable & Non- (Acceptable & Non- (Training/Supervision/Guidelines/procedures/ 4
nature resources (water/fuel/electricity etc) or, business opportunity through & Significant)
significant) significant) significant) PTW/signages/posters/ etc)
waste/scrap/conservation.

Moderate environmental incident within the workplace/department & not lasting


for more than 1 day and /or waste of natural resources as follows (by judgement):
Reportable / Loss Time Injury/major fire with injury/Near Miss 1) Water: 1 % of average monthly consumption 2) Diesel/fuel: 0.25 % of avg
Low Medium High
incident of high severity/legal approvals about to expire in 2 weeks & monthly consumption 3) Electricity: 1 % of monthly energy consumption 4) 1 % Medium (Acceptable Personal Protective Equipments / Proper
2 (Acceptable & Non- (Acceptable & (Not acceptable & 5
no action taken / the measured parameters(or its exposure) are 10 excess of monthly raw material 5) HW waste or air /water emission or noise very significant)
& Significant)
Significant) Significant)
segregation/ Secondary containment
% within the permissible limits. close to permissible limits, or, legal approvals about to expire in 2 weeks & no
action taken in this regard. Interested parties communication without involvement
of legal authorities.

Reportable environmental incident (fire/major leakage/spillage) within the


factory/site. and /or waste of natural resources as follows (by judgement) :
Major / Serious Injuries/Occupational Diseases /legal approvals 1) Water: 5 % of average monthly consumption 2) Diesel/fuel: 1 % of avg monthly Low High High
Medium (Acceptable
expired / the measured parameters (or its exposure) are not consumption 3) Electricity: 5 % of monthly energy consumption 4) 5 % excess of 3 (Acceptable & Non-
& Significant)
(Not acceptable & (Not acceptable &
complying with the permissible limits. monthly raw material 5) HW waste or air /water emission or noise exceeding significant) Significant) Significant)
than the permissible limits, or, legal approvals expired & no action evident.
Interested parties communication with involvement of legal authorities.

Reportable environmental incident (fire/major leakage/spillage) affecting nearby


Fatality / Permanent Disability/ Legal approvals not obtained or external areas & HW waste/ or air or water emission or noise exceeding than the High High High
Medium (Acceptable
measured parameters not meeting the legal requirements for more permissible limits for continuously for 3 months/cycles or received communication 4
& Significant)
(Not acceptable & (Not acceptable & (Not acceptable &
than 3 months & actions taken in this regard not evident. from legal authority on legal non-compliance & actions taken in this regard are Significant) Significant) Significant)
not evident.

EHS Risk Assessment Assessment


Environment (ISO 14001) & Hazard/Risk (OHSAS 18001)
Activities & Sub-activities [Consider (No controls) (Residual Risk/Impact)
ISO 14001
Routine/Normal; Non- Controls Measures Acceptable & Non-significant;
(EMS) / OHSAS Applicable Legal requirement Contro
Sr. No. routine/Abnormal; Emergency ( Method statement; site specific controls in bullet points & Acceptable & Significant;
18001 (OH&S) (Y/N); Provide brief if 'Y' l Type

Likelihood
activities] Env. Impact / OH&S environment procedure (if applicable)) Risk/ Significant & Not-acceptable

Severity
relevance Env.Aspect / OH&S Hazard Risk/Impact
Risk Impact
Severity Likelihood

1- Submission of medical examination for all


workman prior to deployment at site.
Harm to other and self
Y'BOCW Act-1996 & Central
OH&S - Medically unfit manpower due to an incident cause 3 3 9
Rules 1998 (Schedule VII)
2- Without medical fitness certificate gate pass not 4 3 1 3 Acceptable & Non-Significant
by their act issued to concern person.3.Submission of Legal
documents for Gate Pass process. 4.Submission of
Work Competency Certificate

1- Safety induction for all new joinees by EHS Officer


1 Deployment of manpower support from BU EHS Manager
2- For all critical and risky activities only qualified and
trained manpower will deploy
Lack of awareness 3- Explanation of identification of Hazard and control
leading to unsafe act 'Y'BOCWA/R Act-1996 & measures to workmen through daily tool box talk
OH&S - Untrained Manpower 3 3 9 4 3 2 6 Acceptable & Significant
and resulting to an Central Rules 1998 Rules 39 Imparting of job /project specific training to all
Adobe Acrobat incident workman at site.
PDFXML Document 4- Imparting of job/ project specific training to all
workmen at site & same will be included and
identified in training plan 5-
Must Follow 12 Safety Essentials

Page 1 of 13
SIEMENS Hazard Identification and Risk AssessmentEM / IM/EHS-4.3.1/PR/01 dt. 11.06.2018 EM

EHS Risk Assessment Assessment


Environment (ISO 14001) & Hazard/Risk (OHSAS 18001)
Activities & Sub-activities [Consider (No controls) (Residual Risk/Impact)
ISO 14001
Routine/Normal; Non- Controls Measures Acceptable & Non-significant;
(EMS) / OHSAS Applicable Legal requirement 1- Cordon work area to restrict un authorized entry. Contro
Sr. No. routine/Abnormal; Emergency ( Method
2- statement;
Scheduled site specific
and before controls in bullet
use inspection points &
of Lifting Acceptable & Significant;
18001 (OH&S) (Y/N); Provide brief if 'Y' l Type

Likelihood
activities] Env. Impact / OH&S Tackles environment procedure (if applicable)) Risk/ Significant & Not-acceptable

Severity
relevance Env.Aspect / OH&S Hazard Risk/Impact
Risk 3- Crane movement inside the switchyard or live Impact
Severity Likelihood parts shall be done under supervision of Authorized
Person.
4 - Transportation route to be assessed for easy &
safe movement of vehicle.
5- solid ground & height barrier etc.Authorized rigger
to assist in lifting/movement of material
6 - Inspected and certified lifting tackles to be used.
7 - Crane /Farana should be operated by authorised
operator. Should be have valid driving licenes.
8 - Condition of crane to be checked prior to job start
9 -Weight & dimension to be assessed to decide
mode & lifting arrangement.
- Farana/ crane coming into contact - Fall or toppling of
10 - Load lifting and lowering will be done under the
with a power source during material supervision of competenat person/Rigger.
operation. - Caught in between 11 - Ensure no person underneath the load
Unloading of project material - exceeding the crane’s/Farana - Failure of lifting tools & 12-follow safety crane lifting essantials 13.Keep
operational capacity. tackles 'Y'BOCWA/R Act-1996 & yourself and others away from
2 - Manual Material Handling OH&S - Visual impairment, - Toppling of 4 3 12 Central Rules 1998 chapter suspended load. Use guide rope/tag line 3 3 2 6 Acceptable & Significant
- Material handling using - two-blocking, slipping, crane/hydra -Slop road XI & Rules 55, 69 instead of holding by hand for balancing of
hydra/crane/forklift - mechanical failure, for vehical movement material/load swing. Deploy dedicated signal
- operator incompetency - Fall of man as required.
-Obstacles in pathway person 14.Select the right type of equipment having
- Slippery Hands -Fall of material on foot
adequate lifting capacity. Examine load for its
weight and center of gravity, not to exceed
the dynamic and static design of lifting
equipment. PTW is mandatory for mobile
Adobe Acrobat crane operation. 15Pathway should be kept clear
PDFXML Document from any obstacle.
16.Proper illumination should be provided in the night

17.Follow Lifting & crane safety Essentials

15. Implement the manufacture instructions for lifting,


loading and unloading of material 16.During vehical
movement must use stopper blockes in emergency.
17.Follow cranes and lifting Safety
essentials 18.Fallow Driver and vechical safety
1- work done
essentials. under proper
19.mantain supervision
a safe distence from any
2- Inspect the
suspended loadwelding
safetymachine properly before
essantials
starting the job
3- only certified and experienced workmen deployed
- Welding fumes, for welding work
- bared welding lead/cables, - Fire 'Y'BOCWA/R Act-1996 & 4- Follow permit to work system with necessary
- poor earthing, - Exposure to UV/IR Central Rules 1998 Rules action
- unauthorised electrical rays 163, 5- Fire extinguisher is mandatory wherever welding
OH&S 3 3 9 4 3 2 6 Acceptable & Significant
connection. - Electric shock The Indian Electricity Act, work is going on
- Placed near chemical storage, - Burn Injury 2003 & Rules, 1956 & 2005 6- Remove all flammable material from surrounded
- hazardous material, - Fall into Duct (EA & ER) Rules 38, area.
- water lodging area. 7- Check welding machine cables regularly
8- wet clothing not allowed
9- Usage of Proper PPE
10- General instruction Tool box talk
11-Follow six electrial safety golden rules

Page 2 of 13
SIEMENS Hazard Identification and Risk AssessmentEM / IM/EHS-4.3.1/PR/01 dt. 11.06.2018 EM

EHS Risk Assessment Assessment


Environment (ISO 14001) & Hazard/Risk (OHSAS 18001)
Activities & Sub-activities [Consider (No controls) (Residual Risk/Impact)
ISO 14001
Routine/Normal; Non- Controls Measures Acceptable & Non-significant;
(EMS) / OHSAS Applicable Legal requirement Contro
Sr. No. routine/Abnormal; Emergency ( Method statement; site specific controls in bullet points & Acceptable & Significant;
18001 (OH&S) (Y/N); Provide brief if 'Y' l Type

Likelihood
activities] Env. Impact / OH&S environment procedure (if applicable)) Risk/ Significant & Not-acceptable

Severity
relevance Env.Aspect / OH&S Hazard Risk/Impact
Risk Impact
Severity Likelihood

1- Move the workplace to a safe location for carrying


out hot work;
2- Remove nearby combustible materials (such as
flammable liquids, wood, paper,
textiles, packaging or plastics);
3- Protect nearby combustible materials that cannot
- Loose cloths, gloves, jewellery, be moved.
long hair. 4- Use suitable guards or covers such as metal
- Non standard wheels, - Flying particles sheeting, mineral fibre boards or fire-retardant
'Y'BOCWA/R Act-1996 &
- Machine RPM not matching with - Fire blankets;
OH&S 2 2 4 Central Rules 1998 Rules 3 2 1 2 Acceptable & Non-Significant
wheel RPM. - Burn Injury
45. 5- Check that there are no combustible materials
- Non standard machine, - Fall into Duct hidden behind walls or in partitions, particularly if the
- working near flammable or welding or cutting will go on for some time.
hazardous material. 6- use flame-resistant sheets or covers to prevent hot
particles passing through
openings in floors and walls (doorways, windows,
cable runs, etc);
7- if the consequences of a fire are severe, eg work
inside flammable tank or same, you may need to
keep Sutable fire extinguishers nearby.

1- work done under proper supervision


2- Inspect the welding machine properly before
starting the job
3- only certified and experianced workmen diployed
for welding work
3- Follow permit to work system with neccesary
action
Building & Other Construction 4- Fire extinguisher is mandotory wherever welding
Workers (Regulation of
work is going on
EMS - generation of toxic fumes - Air Pollution 2 3 6 Employment & Conditions of 4 2 2 4 Acceptable & Significant
Service) Act, 1996 & Central 5- Remove all flamable material from surrounded
Rules 1998. (BOCWA/R) area.
6- Check welding machine cables regularly
7- wet clothing not allowed
8- Usage of Proper PPE
9- General instruction Tool box talk
Fabrication work 10- Follow Six electrial golden rules 11.
Follow Elactrical safety & machine Guarding safety
- Welding Essentails.
- Gas Cutting
- Grinding 1-Segregate the non-hazardous waste in line with
3 - Welding Fumes their requirements (e.g. dry/wet, biodegradable/non-
- Welding fluxs layers/ molten biodegradable)
material granules 2-Solid waste such as used welding
- Welding chipping, hammering rods,cutting bleads,grinding wheels etc are stored at
sound designated scrap yard.
- Welding grinding / sandering dust
The Municipal Solids Wastes 3-Proper signages are displyed .
- generation of solid waste (e.g.
EMS
stubs of weld rods, scrap etc.)
- Land Pollution 2 4 8 (Management & Handling) 4-Usage of Proper PPE 3 2 2 4 Acceptable & Significant
Rules, 2000 5- General instruction Tool box talk 6.Use
connectors instead of tape
joint, double earthing for
installation, rain protection,
rubber mat, cable routed aerially
at min.2m height, cable gland
and lugs are of suitable size.

Page 3 of 13
3 - Welding Fumes
- Welding fluxs layers/ molten
material granules

SIEMENS
- Welding chipping, hammering
sound Hazard Identification and Risk AssessmentEM / IM/EHS-4.3.1/PR/01 dt. 11.06.2018 EM
- Welding grinding / sandering dust
EHS Risk Assessment Assessment
Environment (ISO 14001) & Hazard/Risk (OHSAS 18001)
Activities & Sub-activities [Consider (No controls) (Residual Risk/Impact)
ISO 14001
Routine/Normal; Non- Controls Measures Acceptable & Non-significant;
(EMS) / OHSAS Applicable Legal requirement Contro
Sr. No. routine/Abnormal; Emergency ( Method statement; site specific controls in bullet points & Acceptable & Significant;
18001 (OH&S) (Y/N); Provide brief if 'Y' l Type

Likelihood
activities] Env. Impact / OH&S environment procedure (if applicable)) Risk/ Significant & Not-acceptable

Severity
relevance Env.Aspect / OH&S Hazard Risk/Impact
Risk Impact
Severity Likelihood

1-Cordon work area to restricted unauthorised


person.
2- Obey the laid down safety rules and
safety signage's displayed in various areas of plant
where generated high sound.
3-Noise exposure standers are based
on a worker's daily personal noise exposure .An
exposure of 85 dB(A) over a work shift is generally
The noise pollution(control & considered to be the upper exposure standard.
EMS - Generated high sound - Noise Pollution 2 3 6 regulation ACT)Amendment 4- 3 2 2 4 Acceptable & Significant
rules 2010 Noise exposure should be assessed by undertaking a
noise survey using a sound level metre.
5-
Control of exposure to noise can be achieved by:
Reducing the noise at source, Interrupting the
pathway from source to receiver, Protecting the
receiver using engineering controls/PPE.
6Usage of Proper PPE
7- General instruction Tool box talk

1. Recognize when industrial dust may be


generated and plan ahead to eliminate or control the
dust at the source. Awareness and planning are keys
to prevention of silicosis.
2-Use engineering controls and
containment methods such as blast-cleaning
machines and cabinets, wet drilling, or wet sawing of
silica-containing materials to control the hazard and
protect adjacent workers from exposure.
3-Routinely
maintain dust control systems to keep them in good
working order.
4- Practice good personal hygiene to avoid
unnecessary exposure to other worksite
contaminants such as lead.
EMS - Generating dust particle - Air pollution 2 3 6 5 2 2 4 Acceptable & Significant
5-Wear disposable or washable protective clothes at
the worksite.
6-Shower (if possible) and change into clean clothes
before leaving the worksite to prevent contamination
of cars, homes, and other work areas.
7-Conduct air monitoring to measure worker
exposures and ensure that controls are providing
adequate protection for workers. Post warning signs
to mark the boundaries of work areas contaminated
with respirable crystalline silica.
8- Provide workers with training that includes
information about health effects, work practices, and
protective equipment.

- continuous lifting / handling


activities. 1-Use of non slippery surfaces.
- load being too heavy, large, 2-Spill control and good drainage
difficult to grasp or unstable, 3-Designating pedestrian
- the task being too strenuous or walkways. 4-Fencing and
involving awkward postures or
- Fall or toppling of guarding.
movements, 'Y'BOCWA/R Act-1996 &
OH&S
- the working environment lacking
material 3 3 9
Central Rules 1998 Rules 38
5-Using signs and PPE. 3 3 2 6 Acceptable & Significant
- Caught in between 6-
sufficient space,
- having slippery, Information,Instruction,Training and supervision.
- uneven or unstable floors,
- having extreme temperatures 7-Routine inspection and maintenance of control
- poor lighting. measure 08-

Page 4 of 13
SIEMENS Hazard Identification and Risk AssessmentEM / IM/EHS-4.3.1/PR/01 dt. 11.06.2018 EM

EHS Risk Assessment Assessment


Environment (ISO 14001) & Hazard/Risk (OHSAS 18001)
Activities & Sub-activities [Consider (No controls) (Residual Risk/Impact)
ISO 14001
Routine/Normal; Non- Controls Measures Acceptable & Non-significant;
(EMS) / OHSAS Applicable Legal requirement Contro
Sr. No. routine/Abnormal; Emergency ( Method statement; site specific controls in bullet points & Acceptable & Significant;
18001 (OH&S) (Y/N); Provide brief if 'Y' l Type

Likelihood
activities] Env. Impact / OH&S environment procedure (if applicable)) Risk/ Significant & Not-acceptable

Severity
relevance Env.Aspect / OH&S Hazard Risk/Impact
Risk Impact
Severity Likelihood

1- Only experienced rigger and fitter familiar with


work need to deploy
- Farana/ crane coming into contact 2- cordon work area to restrict unauthorised entry.
with a power source during 3- Obtain written permission from client
operation. - Fall or toppling of 4- Full time supervision required
Adobe Acrobat - exceeding the crane’s/hydra material 'Y'BOCWA/R Act-1996 & 5- check all equipment before putting into use
PDFXML Document OH&S operational capacity - Caught in between 3 3 9 Central Rules 1998 chapter 6- check test report of all lifting tools & tackles. 4 3 2 6 Acceptable & Significant
- Visual impairment, - Failure of lifting tools & XI & Rules 55, 69 7- usage of proper PPE
- two-blocking, slipping, tackles 8- General instruction tool box talk
- mechanical failure, 9- Working at height
- operator incompetency 10- First aid box.
11- Follow Cranes and lifting safety essentials

Adobe Acrobat
PDFXML Document

1- Deploy trained manpower only.


2-Certified third party certificate of all lifting tools &
tackles.
3-Cordon work area & hard barrication at
opening cut outs.
- Fall or toppling of 4-Check all equipment before putting
- unapropriate tools and tackles, material into use.
'Y'BOCWA/R Act-1996 &
- untrained manpower, - Caught in between
OH&S
- Unstable platform/base plate, - Failure of lifting tools &
2 3 6 Central Rules 1998 chapter 5-Method statement prepare & work is done 4 2 2 4 Acceptable & Significant
XI & Rules 55, 56, 81 as per method statement.
- open cut outs tackles
- Fall into Duct 6- usage of proper PPE
7- General instruction tool box talk
8- Working at height
9- First aid box.
10- Follow six electrial safety golden rules 11-
1- Deploy
Follow trained
cranes andmanpower only
lifting safety Essentials
2- Material should be easily operatable,

it should not be overloaded


3- Handling aids such as Trolleys, Barrel lifts, Gin
- Fall or toppling of wheels,Trucks,Hoists and lifts.
material 4-Modify the task, load or
- unapropriate tools and tackles, environment. 5-Ensure
- Caught in between
- untrained manpower, individual capabilities are matched to the activity.
- Failure of lifting tools &
Equipment Installation - Unstable platform/base plate, 'Y'BOCWA/R Act-1996 &
tackles 6- General instruction Tool box talk
OH&S - open cut outs, 2 3 6 Central Rules 1998 chapter 4 2 2 4
- Fall into Duct 7- Usage of PPE
- Manual material handling -Wrong manual lifting positions XI & Rules 55, 56, 82
-Some musle Cracks & 8.Safe work method statement
- Material handling using -Obstacles in pathway
sprains - Slips & trip - (Safety procedure) is required to
crane/hydra/HOT/pallet truck. - Slippery Hands
Fall of person be prepared for all the critical
4 - Equipment assembly Fall of material on foot
- Equipment erection activities, well ahead of time
- Testing & Commissioning 9.Must follow manual Lifting positions 10.
- Charging Pathwayinsulated
1-Only should be keptused,
tools clearCertify
from any
DB obstacle.
with ELCB &
- Working at Height MCB.
- Electrical consumption 11.Proper illumination
2-Electrical work done should be provided
by electrician only in the night
3-Only skilled person deployed.
4-Work done under proper
supervision. 5-Obtain written
permission from client. 6-
Proper earthing & 30mA tripping system ELCB to be
used.
7-All overhead cable mounted
- Untrained manpower, above 2mtr. 8-Temporary joint
- Improper grounding, or insulated tape for cable joints is strictly banned or
- exposed electrical connection, prohibited.
- inadequate wiring, 9 - Safe cables, three pin plugs, sockets etc. Provide
- Electrocution
OH&S - damaged insulation,
- Fire & Explosion
4 3 12 standard quality cables, three pin plugs, sockets 3 3 2 6 Acceptable & Significant
- overloaded circuit, etcCarry out periodic testing of plug points, sockets
- damaged and non calibrated tools for checking healthiness
and tackles, 10--Genaral instruction LOTO.
- working in wet condition 11-Electric & electronic waste handling.
A dobe Acrobat
Docum ent 12-First
aid box.
13-General instruction of TBT.
14-Apply independent LOTO if
multiple agencies/people are
working on same equipment/
source. Person/s deployed to
carry LOTO key/s.
15.Follow six electrial safety golden rules
16.Follow electrial safety Essentials Page 5 of 13
SIEMENS Hazard Identification and Risk AssessmentEM / IM/EHS-4.3.1/PR/01 dt. 11.06.2018 EM

EHS Risk Assessment Assessment


Environment (ISO 14001) & Hazard/Risk (OHSAS 18001)
Activities & Sub-activities [Consider (No controls) (Residual Risk/Impact)
ISO 14001
Routine/Normal; Non- Controls Measures Acceptable & Non-significant;
(EMS) / OHSAS Applicable Legal requirement Contro
Sr. No. routine/Abnormal; Emergency ( Method statement; site specific controls in bullet points & Acceptable & Significant;
18001 (OH&S) (Y/N); Provide brief if 'Y' l Type

Likelihood
activities] Env. Impact / OH&S environment procedure (if applicable)) Risk/ Significant & Not-acceptable

Severity
relevance Env.Aspect / OH&S Hazard Risk/Impact
Risk Impact
Severity Likelihood

- Improper grounding, 1- Proper earthing,Checking of all connection.before


- exposed electrical connection, work at energising
- inadequate wiring, The Indian Electricity Act, 2- Clearance, Display caution signs
- damaged insulation, - Electrocution 2003 & Rules, 1956 & 2005 3- Obtain written permission from Client
OH&S 4 3 12 3 3 2 6 Acceptable & Significant
- overloaded circuit, - Fire & Explosion (EA & ER) Rules 32, 40, 50, 4- Use calibrated instrument only
- damaged and non calibrated tools 38 5- General instruction Tool box talk
and tackles, 6- working on high voltage system
- working in wet condition 7-Follow six Electrial safety golden rules

1-Nature and duration of the task be carried out.


2-Level of
competence of the persons to be involved
3-Training
- Unprotected sides, that need to be provided. 4-
- edges, 'Y'BOCWA/R Act-1996 & Planing and level of supervision required.
- Fall from height
OH&S - Leading edges,
- Slip, Trip, Fall
3 3 9 Central Rules 1998 Rules 42, 5-Means of access and egress. 3 2 2 4 Acceptable & Significant
- Damaged or missing guardrails 65 6-Suitability of requirement to be
- improper Access ladders used, and it's maintenance.
7-Use of working platform,
guard rail and toe boards.
8-PPE such as
harness and helmet.

###
1 - Avoid unnecessary charging of panels
2- Make proper schedule for charging and adhere it
- Unnecessary charge the panels till handingover
EMS for long time, - Resource depletion 2 3 6 3- Make team accountable for repeated testing 4 2 2 4 Acceptable & Significant
- repeated testing of panels. activity
3 - Signages to save power
4 - OCP for Tool box talk

1- work done under proper


supervision
2- Inspect the welding machine
properly before starting the job
Cable Tray Installation
3- only certified and experianced
workmen diployed for welding work
- Welding 4- Follow permit to work system
- Working at Height with neccesary action
- Grinding 5- Fire extinguisher is mandotory
- Welding Fumes EMS - generation of toxic fumes - Air Pollution 3 2 6 wherever welding work is going on 4 2 2 4
- Welding fluxs layers/ molten 6- Remove all flamable material
material granules from surrounded area.
- Welding chipping, hammering 7- Check welding machine cables
sound regularly
- Welding grinding / sandering dust
8- wet clothing not allowed
9-Usage of Proper PPE
10- General instruction Tool box
talk 11.Follow Machine Guarding
and height work safety essentails

Page 6 of 13
SIEMENS Hazard Identification and Risk AssessmentEM / IM/EHS-4.3.1/PR/01 dt. 11.06.2018 EM

EHS Risk Assessment Assessment


Environment (ISO 14001) & Hazard/Risk (OHSAS 18001)
Activities & Sub-activities [Consider (No controls) (Residual Risk/Impact)
ISO 14001
Routine/Normal; Non- Controls Measures Acceptable & Non-significant;
(EMS) / OHSAS Applicable Legal requirement Contro
Sr. No. routine/Abnormal; Emergency ( Method statement; site specific controls in bullet points & Acceptable & Significant;
18001 (OH&S) (Y/N); Provide brief if 'Y' l Type

Likelihood
activities] Env. Impact / OH&S environment procedure (if applicable)) Risk/ Significant & Not-acceptable

Severity
relevance Env.Aspect / OH&S Hazard Risk/Impact
Risk Impact
Severity Likelihood

1-Segregate the non-hazardous


waste in line with their
requirements (e.g. dry/wet,
biodegradable/non-biodegradable)

2-Solid waste such


as used welding rods,cutting
- generation of solid waste (e.g.
EMS
stubs of weld rods, scrap etc.)
- Land Pollution 2 4 8 bleads,grinding wheels etc are 3 2 2 4
stored at designated scrap yard.

3-Proper signages are displyed


4-Usage of
Proper PPE
5- General instruction Tool box
talk
1- Have knowledge of hazards and risk associated
with the process & equipments located in various
areas of plant.
2- Understand various hazards & risk associated with
the area, equipments etc and be vigilent when you
move in the plant.
3- Obey the laid down safety rules and safety
signages displayed in various areas of plant.
4- In case of you notice any abnormal condition,
sound, smell, vibration etc immediately move away
of the area or equipment.
- unapropriate tools and tackles,
5- Inform fire station or the the concern department
- untrained manpower,
- exposed electrical connection,
as appropriate.
- inadequate wiring, - Slip, trip, fall 6- Visitor induction training to be given to visitor.
- damaged insulation, - Caught in between 7- Usage of PPE
- overloaded circuit, - Insect or reptile bite 8- Visitor safety
- damaged and non calibrated tools - Hit by vehicles/ 'Y'BOCWA/R Act-1996 & 9- Noise pollution control 10-
OH&S and tackles, machinery 3 3 9 Central Rules 1998 chapter Fallow six Electrial safety golden rules 11.Must 4 3 2 6 Acceptable & Significant
- Machine RPM not - Collapse of structure. XI & Rules 55, 56, 82 fallow Electrial safety & Height work/Fall protection
matching with wheel RPM. -Electrial Essentials rules 12.Must read msds
- Testing shock of all equpiments 13.Understanding of
Equpiment failuer -Multiple SLD/drawing/process, product
agencies working - Un
sufficent parking area
and deployment of qualified,
-Vechile movement authorized and competent
personnel are pre-requisites 14.Verify a
Zero Energy State for all
work e.g. Electrical energy- by
using live line detector. 15.Apply independent LOTO
if
132 KV switch yard modification multiple agencies/people are
work working on same equipment/
- Dismandling of old Equpiment source. Person/s deployed to
With farana carry LOTO key/s.16..If requir barecate & Isolate
-Eraction of new materil & your working area with Fiber sheets.17.Safe walk
5 1- Only experienced rigger and fitter familiar with
Equpiment using with farana ways for reaching site.
-Fixing of conductor work need to deploy.2- Suitable iron plates must be
-Testing & Commissioning work used for out riggers positining
.-Shifting of Transfarmer with using - unapropriate tools and tackles, 3- cordon work area to restrict unauthorised entry.
of Crane & Heavy Trailer - untrained manpower, '- 4- Obtain written permission from client
Hydra/ crane coming into contact 5- Full time supervision required
with a power source during 6- check all equipment before putting into use
operation. Fall or toppling of 7- check test report of all lifting tools & tackles.
- exceeding the crane’s/hydra material Y'BOCWA/R Act-1996 &
8- usage of proper PPE
OH&S operational capacity - Caught in between 3 3 9 Central Rules 1998 chapter 4 3 2 6 Acceptable & Significant
- Visual impairment, - Failure of lifting tools & XI & Rules 55, 69 9- General instruction tool box talk
- two-blocking, slipping, tackles 10- Working at height
- mechanical failure, 11- First aid box. 12-
- operator incompetency Fallow six Electrial safety golden rules
Adobe Acrobat
PDFXML Document
- Crane positining near cable 13.Fallow electrilal safety & Lifting Safety
trenchs & Drainages essentials.14.Proper insulation Should be Provided
for crow bars.15.Hard barication should be done near
excavation area & Provide safety sign boards.
16.Provide sutable plates for out rigger positining.

Page 7 of 13
SIEMENS Hazard Identification and Risk AssessmentEM / IM/EHS-4.3.1/PR/01 dt. 11.06.2018 EM

EHS Risk Assessment Assessment


Environment (ISO 14001) & Hazard/Risk (OHSAS 18001)
Activities & Sub-activities [Consider (No controls) (Residual Risk/Impact)
ISO 14001
Routine/Normal; Non- Controls Measures Acceptable & Non-significant;
(EMS) / OHSAS Applicable Legal requirement Contro
Sr. No. routine/Abnormal; Emergency ( Method statement; site specific controls in bullet points & Acceptable & Significant;
18001 (OH&S) (Y/N); Provide brief if 'Y' l Type

Likelihood
activities] Env. Impact / OH&S environment procedure (if applicable)) Risk/ Significant & Not-acceptable

Severity
relevance Env.Aspect / OH&S Hazard Risk/Impact
Risk Impact
Severity Likelihood
1- Oli must be stored in supprate oil drums .
2.Follow the Msds of that oil.
3.Use sutable Bins during oil leakge.
4.Proper training required.
5.Only competent person should handle this oil.
EMS Westage & Leakage of oil Land pollution 2 4 8 3 2 2 4
6.Sign boards must be important near stroge area.
7.General
instructrion on tool box.
1-Plan of the ask
8. If possible areaclient
of theforexcavation should be
proper treatment.
obtained.
9- AwarnessPlan do notwithin
requird necessarily
team. show the exact
position of buried services, but can give an indication
of the existence of services and an approximate
Adobe
Adobe Acrobat
Acrobat - exposure to underground services position.
PDFXML
PDFXML Document
Document or overhead electrical cables 2-The buried services should be located using
- excavated material or other surface clues and detection equipement.Various
objects falling on workers devices can be used to detect different types of
- toxic, irritating or flammable and service :-metal detector, hum detector, cable
'Y'BOCWA/R Act-1996 &
explosive gases detector, ground radar.
- Fall from height Central Rules 1998 Rules
- mishandled or poorly placed
OH&S
materials
- Slip, Trip, Fall 3 3 9 188, 3-Isolating the power supply when 3 3 2 6 Acceptable & Significant
- Collapse of scaffolding 190,191,192,193,196,197,19 working in the vicinity of power lines.
- Soil that does not hold tightly
8 4-Using safe work Method
together, such as sandy soil
Water, which weakens the strength statement(SWMS)and permit systems to control
of trench sides access into danger area.
- The weight of equipment too 5-Using barriers,sinage and goal-posts to keep plant
close to the edge of a trench and vehicles a safe distance from overhead power
line/ excavation.
6- usage of proper PPE
7- General instruction tool box talk. 8.Follow Safety
procedure Safet essentails
Excavation

7 - Manual Digging 1- Deploy trained manpower only.


- Mechanically Digging - Untrained operator, 2-Soil heaps should be positioned a safe
- wastage of Top soil - Loose soil due to vibrations from distance from the excavation side.
excavator/ construction equipment 3-Vehicles should be prevented
or traffic in the construction area from approaching the excavation by use of barriers
- exposure to underground services and sinages.
- overhead electrical cables 4-Vehicle movement close to unsupported excavation
- excavated material or other - Fire must be minimised to prevent the side of the
objects falling on workers - Exposure to UV/IR excavation from becoming loose as a result of
'Y'BOCWA/R Act-1996 &
- toxic, irritating or flammable and rays
OH&S
explosive gases - Electric shock
3 3 9 Central Rules 1998 Rules vibration. 4 3 2 6 Acceptable & Significant
202 5-Using safe Work method
- mishandled or poorly placed - Burn Injury
materials - Fall from height statement(SWMS)and permit systems to control
- Soilt does not hold tightly access into danger area. 6-
together, such as sandy soil Sides of the excavation can be prevented by
- waterwhich weakens the strength Battering,Shoring,Trench box
of trench sides 7- usage of proper PPE
- weight of equipment too close to 8- General instruction tool box talk. 8
the edge of a trench Must using insulated crow bars during manual
digging.

1- Excavated top soil need to used


for gardening purpose only
2- Top soil didn’t mis with normal
EMS wastage of Top soil Natural resource depletio 3 3 9 soil 4 3 2 6
3- If possible ask client for proper
treatment.
4- Awarness requird within team.

Page 8 of 13
SIEMENS Hazard Identification and Risk AssessmentEM / IM/EHS-4.3.1/PR/01 dt. 11.06.2018 EM

EHS Risk Assessment Assessment


Environment (ISO 14001) & Hazard/Risk (OHSAS 18001)
Activities & Sub-activities [Consider (No controls) (Residual Risk/Impact)
ISO 14001
Routine/Normal; Non- Controls Measures Acceptable & Non-significant;
(EMS) / OHSAS Applicable Legal requirement Contro
Sr. No. routine/Abnormal; Emergency ( Method statement; site specific controls in bullet points & Acceptable & Significant;
18001 (OH&S) (Y/N); Provide brief if 'Y' l Type

Likelihood
activities] Env. Impact / OH&S environment procedure (if applicable)) Risk/ Significant & Not-acceptable

Severity
relevance Env.Aspect / OH&S Hazard Risk/Impact
Risk Impact
Severity Likelihood

1- Have knowledge of hazards and risk associated


with the process & equipments located in various
areas of switch yard
2- Understand various hazards & risk associated with
the area, equipments etc and be vigilent when you
move in the plant.
3- Obey the laid down safety rules and safety
- Slip, trip, fall signages displayed in various areas of switch yard.
- Caught in between 4- In case of you notice any abnormal condition,
- Visitor induction training not taken
- Insect or reptile bite
Visit / properly, sound, vibration etc immediately move away of the
8 OH&S - Hit by vehicles/ 3 3 9 4 2 2 4 Acceptable & Significant
Site Round - visiting site without having
machinery area or equipment.
appropriate PPE's. 5- Inform fire station or the the concern department
- Collapse of structure
- Snake bite as appropriate.
6- Visitor induction training to be given to visitor.
7- Usage of PPE
8- Visitor safety. 9.Must
fallow all safety essantials during site visit. 10.Don't
enter Snake Movement areas. 11 Must Follow Six
Adobe Acrobat
electrial safety golden rules
PDFXML Document

1'- proper first aid measures are to be taken , for e.g


pressure immobilisation of affected limb etc.Training
2- Refresher training with latest updates to all first
aiders.
9 Insect Bites OH&S - Snake / scorpion/ Honey been/ rept- Insect or reptile bite 3 3 9 3- Seek help of security department, fire department 4 3 2 6 Acceptable & Significant
& Medicare team (Ambulance)
4- First aid box
5- Usage of PPE
Adobe Acrobat 6- Use snake repling kits in snake Closed areas
PDFXML Document

- Slip, trip, fall 1- Safe handling and disposal of waste, Proper bins
- Caught in between shall be used for tools, equipment parts,
- Insect or reptile bite consumables etc.Ensure thorough housekeeping
10 Cleaning EMS - Housekeeping - Hit by vehicles/ 2 3 6 2- After completion of each job housekeeping of 3 2 1 2 Acceptable & Non-Significant
machinery surrounded area need to ensure.
- Collapse of structure 3- TBT need to taken on good housekeeping and its
importance

1- Handle with care


- Suffocation 2- don't allow the cylinder to fall.
- Flying particles 3- Protect the valve Cylinder valve should always
- Usage of expiry date & rusted
11 Fire Fighting equipment OH&S
Fire Extinguisher.
- Cold Burn 2 3 6 have protection cap. 4- 3 2 1 2 Acceptable & Non-Significant
- Caught in between Consider Wind direction & chemical properities.
- Fall from height 5- Perodic Trainings for staff & workers
Adobe Acrobat
PDFXML Document

1 - EHS cost should consider during bidding phase to


- EHS Cost not consider during
project bidding, avoid NCC.
- missing dedicated safety walks, 2- Make Site team accountable for UAUC reporting &
- audit observation not complied on - Lack of management its tracking
time, focus may leading to 3- Site manager need to conduct dedicated walks
- Missing analysis of unsafe act serious offences. with site team.
12 Site Management OH&S 2 2 4 4 2 1 2 Acceptable & Non-Significant
unsafe condition analysis - Quality of work & 4- Need to ensure the involement of site safety officer
- participation missing during Project may delayed during day to day schedule/planning
contractor evaluation, - NCC will occurred 5- Site manager should help BU EHS for contractor
- EHS not consider for day to day evaluation
Adobe Acrobat activity/schedule,
6- Monthly meeting with site contractor to
PDFXML Document - Contractor not engaged for EHS.
demonstrate actionable/areas for improvement.

Page 9 of 13
SIEMENS Hazard Identification and Risk AssessmentEM / IM/EHS-4.3.1/PR/01 dt. 11.06.2018 EM

EHS Risk Assessment Assessment


Environment (ISO 14001) & Hazard/Risk (OHSAS 18001)
Activities & Sub-activities [Consider (No controls) (Residual Risk/Impact)
ISO 14001
Routine/Normal; Non- Controls Measures Acceptable & Non-significant;
(EMS) / OHSAS Applicable Legal requirement Contro
Sr. No. routine/Abnormal; Emergency ( Method statement; site specific controls in bullet points & Acceptable & Significant;
18001 (OH&S) (Y/N); Provide brief if 'Y' l Type

Likelihood
activities] Env. Impact / OH&S environment procedure (if applicable)) Risk/ Significant & Not-acceptable

Severity
relevance Env.Aspect / OH&S Hazard Risk/Impact
Risk Impact
Severity Likelihood

- Only trained and competent employees to be


deployed
- Product specific training to be imparted to
employees
- Positive Isolation to be esnured prior to usage of
Live line detector.
- Live line detector should not be connected with live
terminal or equipments
- Presence of live circuit/ induction - Electrocution - Periodic inspection of live line detector to be done
- Untrained manpower/employee - Flash over by authorised person.
- Damaged Probe/Rod - Burn injury - Site manager to ensured that correct application of
- Foulty Detector/siren - Lack of awareness live line detector
13 Usage of Live line detector OH&S 3 3 9 3 2 1 2 Acceptable & Non-Significant
- Inadequate application leading to unsafe act - Do not used the live line detector in wet condition.
- Discharge Battery cell during and resulting to an - After each and every breaks/instervals voltage to be
application lead to false reading incident verifying using live line detector.
- Inadequate storage - Physical injury - Store in dry and safe place as per manufacturer
instruction.
- Always follow six golden rules of electrical safety
instructions.
- Always wear appropriate PPE's
- Live line detector to be used as per SWMS for
different application
- Obtain written valid work permit from customer and
comply all the requirement

- Disposal of dead batteries Reachable batteries to be used.


- Disposal of damaged/dead live - Land contamination All dead batteries to be handed over to the supplier
EMS line detector - Air Pollution if its burn 3 3 9 or manufacturer. 0
- Disposal of damaged insulation - Water contamination All electronics items to be handed over to approved
probe or athorised recyler.
- Only trained and competent employees to be
deployed
- Earthing clamp to be connected first to the gorund
earthing before connecting to the
equipment/conductor.
- Product specific training to be imparted to
employees
- Positive Isolation to be esnured prior to application
of earth discharge rod
- Presence of live circuit/ induction
- Untrained manpower/employee - Electrocution
- Periodic inspection of earth discharge rod to be
- Damaged Probe/Rod - Flash over done by authorised person.
- Damaged Cable insulation - Burn injury - Periodic inspection/continuity of earthing cable to be
- Damaged clamp/connector - Lack of awareness done by authorised person
- Working at height leading to unsafe act - Site manager to ensured that correct application of
14 Earth Discharge OH&S - Adequate earthing and resulting to an 3 3 9 earth discharge rod 3 2 1 2 Acceptable & Non-Significant
- Loose earthing incident - Store in dry and safe place as per manufacturer
- Inadequate - Physical injury instruction.
application/components - Fall of - Earthing resistance of grid and pits to be check prior
- Inadequate storage material/equipment to job start or application of earth discharge rod.
- Usage of non-certified and unsafe - Slip, trip, fall
earth discharge rod
- Always wear appropriate PPE's
- Always follow six golden rules of electrical safety
instructions.
- Earth discharge rod to be used as per SWMS for
different application
- Don’t use underrated discharge rod. Don’t use over
rated voltage detector.
- 16/32Sqmm cable to be used.
- Obtain written valid work permit from customer and
0 comply all the requirement mentioned in the PTW. 0

0 0

0 0

0 0

Prepared by: Nagendra babu Checked by: Approved by:


Date: 23/08/2019 Date: Date:

Page 10 of 13
EM Safety Poster v02.pdf
Likelihood of Occurrence of Hazardous event or exposure (OH&S) & Likelihood of
Env Aspect.
OH &S Risk/Ienvironment mpact Rating Matrix
R = SxL

circumstanc
happen, but

Expected to

es. (> 90%


possibility)

possibility)
Could

most times
probably
probably

some time
occur at

occur at

occur in
Almost
never will

certain
Likely
(<5 %
Could
Rare

Unlikely

most
Will
Severity (S)
OHSAS 18001 : Occu. Health & Safety ISO 14001: Environmental Impact (Scale, Severity & Duration of Impact) 1 2 3 4

Minor environmental incident (lekage, spillage, waste of resource etc) within the Low
First Aid Case/temp Illness/Near Low Low
workplace & not lasting for more than 1 shift. Or, conservation of natural resources (Acceptable Medium (Acceptable &
Miss Incident of less severe in 1
& Non-
(Acceptable & Non- (Acceptable &
Significant)
(water/fuel/electricity etc) or, business opportunity through significant) Non-significant)
nature significant)
waste/scrap/conservation.

Moderate environmental incident within the workplace/department & not lasting for
Reportable / Loss Time Injury/major
more than 1 day and /or waste of natural resources as follows (by judgement): 1)
fire with injury/Near Miss incident of
Water: 1 % of average monthly consumption 2) Diesel/fuel: 0.25 % of avg monthly Low
high severity/legal approvals about Medium High
consumption 3) Electricity: 1 % of monthly energy consumption 4) 1 % excess of (Acceptable Medium (Acceptable &
to expire in 2 weeks & no action 2
& Non- Significant)
(Acceptable & (Not acceptable &
monthly raw material 5) HW waste or air /water emission or noise very close to Significant) Significant)
taken / the measured significant)
permissible limits, or, legal approvals about to expire in 2 weeks & no action taken
parameters(or its exposure) are 10
in this regard. Interested parties communication without involvement of legal
% within the permissible limits.
authorities.

Reportable environmental incident (fire/major leakage/spillage) within the


Major / Serious
factory/site. and /or waste of natural resources as follows (by judgement) :
Injuries/Occupational Dieases Low
1) Water: 5 % of average monthly consumption 2) Diesel/fuel: 1 % of avg monthly High High
/legal approvals expired / the (Acceptable Medium (Acceptable &
consumption 3) Electricity: 5 % of monthly energy consumption 4) 5 % excess of 3
& Non- Significant)
(Not acceptable & (Not acceptable &
measured parameters (or its Significant) Significant)
monthly raw material 5) HW waste or air /water emission or noise exceeding than significant)
exposure) are not complying with
the permissible limits, or, legal approvals expired & no action evident.Interested
the permissible limits.
parties communication with involvement of legal authorities.

Fatality / Permanent Disability/


Reportable environmental incident (fire/major leakage/spillage) affecting nearby
Legal approvals not obtained or Medium
external areas & HW waste/ or air or water emission or noise exceeding than the High High High
measured parameters not meeting (Acceptable
permissible limits for continuously for 3 months/cycles or received communication 4
&
(Not acceptable & (Not acceptable & (Not acceptable &
the legal requirements for more Significant) Significant) Significant)
from legal authority on legal non-compliance & actions taken in this regard are not Significant)
than 3 months & actions taken in
evident.
this regard not evident.

Hierarchy of Control Measures


Elimination 1
Substitution /Reduction at source 2

Engineering Controls/ Conservation/Reuse/Recycle/Treatment 3

Admin Controls
(Training/Supervision/Guidelines/procedures/PTW/signages/p 4
osters/ etc)
Personal Protective Equipments / Proper segregation/
5
Secondary containment

You might also like