You are on page 1of 3

# 10

Facilities For The Royal Saudi Land Forces Artillery Corps (RSLF‐ AC) Project
3 WEEKS LOOKAHEAD SCHEDULE
From : 19 May 2019
To    : 08 Jun 2019

Projec ID: W912ER19C0001

Loacation: Eastern Province, Saudi Arabia

Report Date: 19‐May‐19
Facilities For The Royal Saudi Land Forces Artillery Corps (RSLF‐ AC) Project
 3 WEEKS LOOKAHEAD SCHEDULE  iiiiiiiiiii
                    From : 19 May 2019
To    : 08 Jun 2019

S F

% May June
Week 1 Week 2 Week 3
Item Activity Completi REMARKS
S M T W TH F S S M T W TH F S S M T W TH F S
on 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8

Mobilization
A Site offices

1 Furnaturing YC site offices 100%

2 Construction of laboratory ‐ Brick Works  100%

3 Construction of Workshop  ‐ Brick Works  100%

4 Laboratory Steel Roof procurement & installation  100%

5 Workshop  Steel Roof procurement & installation  100%

Procure materials for foundation of Store Steel 
6 100%
Structure 

7 Construction of foundation for Store Steel Structure  100%

8 Fabrication  of Store Steel Structure  100%

Planned to be finihsed 
9 Erection  of Store Steel Structure  60% on 
17th  Jun 2019

10 Erection of internal site fence for site offices 100%

11 Supply of  boundry site fence  100%

Planned to be finihsed 
12 Erection of boundry site fence  50% on 
17th  Jun 2019

13 Car Shed Steel structure instllation  100%

Zakimov 1 of 2
Facilities For The Royal Saudi Land Forces Artillery Corps (RSLF‐ AC) Project
 3 WEEKS LOOKAHEAD SCHEDULE  iiiiiiiiiii
                    From : 19 May 2019
To    : 08 Jun 2019

S F

% May June
Week 1 Week 2 Week 3
Item Activity Completi REMARKS
S M T W TH F S S M T W TH F S S M T W TH F S
on 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8

B Power , Water Supply, Sewage Line

1 Install Septic Tank & Sewage Network 100%

2 Water Supply Line & Water Network  100%

Engineering / Submittals
A Design Package
Incorporate Earth work 95% Package comments and 
1 submit it to USACE includig  Soil Improvement Method  100%
Statement

Earthwork Package &  Soil Improvement Method 
2 100%
Statement review by USACE

3 Mobilization of Soil Improvement Team  100%

Planned to be 
4 C.P.T. Tests  25% completed on           
13th Jun 2019

5 Facilities & Utilities Package Prepration / Submittal  100%

Construction
A Zone 2
A-1 Filling work
Planned to be 
1 Mobilizing of the filling materials for zone 2 10% completed on           
8th July 2019

Zakimov 2 of 2

You might also like