Facilities For The Royal Saudi Land Forces Artillery Corps (RSLF‐ AC) Project
3 WEEKS LOOKAHEAD SCHEDULE
From : 19 May 2019
To : 08 Jun 2019
Projec ID: W912ER19C0001
Loacation: Eastern Province, Saudi Arabia
Report Date: 19‐May‐19
Facilities For The Royal Saudi Land Forces Artillery Corps (RSLF‐ AC) Project
3 WEEKS LOOKAHEAD SCHEDULE iiiiiiiiiii
From : 19 May 2019
To : 08 Jun 2019
S F
% May June
Week 1 Week 2 Week 3
Item Activity Completi REMARKS
S M T W TH F S S M T W TH F S S M T W TH F S
on 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8
Mobilization
A Site offices
1 Furnaturing YC site offices 100%
2 Construction of laboratory ‐ Brick Works 100%
3 Construction of Workshop ‐ Brick Works 100%
4 Laboratory Steel Roof procurement & installation 100%
5 Workshop Steel Roof procurement & installation 100%
Procure materials for foundation of Store Steel
6 100%
Structure
7 Construction of foundation for Store Steel Structure 100%
8 Fabrication of Store Steel Structure 100%
Planned to be finihsed
9 Erection of Store Steel Structure 60% on
17th Jun 2019
10 Erection of internal site fence for site offices 100%
11 Supply of boundry site fence 100%
Planned to be finihsed
12 Erection of boundry site fence 50% on
17th Jun 2019
13 Car Shed Steel structure instllation 100%
Zakimov 1 of 2
Facilities For The Royal Saudi Land Forces Artillery Corps (RSLF‐ AC) Project
3 WEEKS LOOKAHEAD SCHEDULE iiiiiiiiiii
From : 19 May 2019
To : 08 Jun 2019
S F
% May June
Week 1 Week 2 Week 3
Item Activity Completi REMARKS
S M T W TH F S S M T W TH F S S M T W TH F S
on 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8
1 Install Septic Tank & Sewage Network 100%
2 Water Supply Line & Water Network 100%
Engineering / Submittals
A Design Package
Incorporate Earth work 95% Package comments and
1 submit it to USACE includig Soil Improvement Method 100%
Statement
Earthwork Package & Soil Improvement Method
2 100%
Statement review by USACE
3 Mobilization of Soil Improvement Team 100%
Planned to be
4 C.P.T. Tests 25% completed on
13th Jun 2019
5 Facilities & Utilities Package Prepration / Submittal 100%
Construction
A Zone 2
A-1 Filling work
Planned to be
1 Mobilizing of the filling materials for zone 2 10% completed on
8th July 2019
Zakimov 2 of 2