Patimban Port Development Project (I) Package 3 Connecting Bridge

Package “Patimban Port Development Project (I) Package 3 is


1 Connecting Bridge that connects Package 4 (access
Package 3 :
road) with Packages 1 & 2 (reclamation side)”
1.005 m
Connecting
Bridge
Construction Progress
Progress until 5 August 2020
Lokasi Paket 3 Plan : 5.5506 %
Actual : 8.0189 %
Deviation : + 2.4683
Activity Photograph
General Information Progress of Causeway :
- The length of the east
East side causeway work
MINISTRY OF TRANSPORTATION - DIRECTORATE GENERAL OF SEA West Side
Owner Side done is 300 m
TRANSPORTATION
- The length of the west
Contractor WIKA – PP JOINT OPERATION side causeway work
done is 200 m
Consultant PatimOne Consul

Name of Bank Japan International Cooperation Agency (JICA)

Name of Lender The Government of The Republic of Indonesia


Long Section
Contract Amount
IDR 524.140.228.418,00
(WIKA – PP)

Project Duration April, 2nd 2020 to December, 23th 2021 (630 days after Commencement Date)

Maintenance Period 730 days

LWS
Advance Payment 15% of the Contract Amount (IDR 78.621.034.262,70) Seabed Causeway Site
Scope Of Works
Structure Excavation, Pavement, Concrete Structure, Miscellaneous, Utilities, Works Office Stockyard Spun Piles
Installation of Water Supply Pipe Typical Section