Pricing System 1.0
Pricing System 1.0
BY STANDEL CORPORATION
BY JOSE SIAO LING & ASSOCIATES
EMPLOYED IN THE OFFERED QUOTATION REMARKS
Floor Level / Area in Proposed Contract Floor Level / Area in Total Capital
Cost per Sq.M. Cost per Sq.M.
Description Sq.M. Cost Description Sq.M. Investment
1. DESIGN &
ENGINEERING PHASE PHP 1,100,000.00
(Phase 1)
Proposed Total Cost for
Design & Engineering PHP 1,100,000.00
Phase 1
2. CONSTRUCTION
A. ARENA
PHASE (Phase 2)
Roof Deck Opened Area 569.42 @Php8,500/sq.m. PHP 4,840,070.00 Roof Deck Opened Area 921.51 @Php17,500/sq.m. PHP 16,126,425.00 Standel is Lower
Roof Deck Covered Standel has quoted cost but J. Ling did
Roof Deck Covered Area 3,848.45 @Php17,500/sq.m. PHP 67,347,875.00 - - -
Area not indicate any Investment Amount
B. OWNER SUPPLIED
PHP 60,893,671.43
MATERIALS
TOTAL CAPITAL
PROPOSED TOTAL INVESTMENT (ARENA) -
PHP 235,812,732.64 PHP 318,783,846.43
PROJEC COST Including Supplied
Materials