You are on page 1of 5

HVAC System Completion Schedule - Priority-1

(Chiller Plant, WTP ECR, DC ECR, HSM ECR, TSC ECR & Pulpit)

PRECONDITIONS / DATE
COMPLETIO
# TASK REQUIREMENTS (manpower, REQUIRED AT
N DATE
material, etc.) SITE

1 Condenser line piping installation 16 Jan'21 Supporting material ISMC 100

2 Installation of pressurization unit 20 Jan'21


2 Installation of equilizer line 25 Jan'21
3 Hydrotest of condenser line 30 Jan'21
4 Flushing of condenser line 19 Feb'21
5 Flushing of chilled water line Loop-1 20 Feb'21
6 Allignment of pump motor 27 Jan'21 Coupling 20.01.2021
7 Cable Termination of pump motor 2 Feb'21
8 Replacement of Chiller cable entry box 28 Jan'21 Cable entry JB (termination 22.01.2021
box)
9 Termination of HT cable 10 Feb'21 Termination Kit 1 10.01.2021
10 Hipot test of HT cable 8 Feb'21 Testing manpower
11 HT panel erection 25 Jan'21 Termination Kit 2 21.01.2021
12 LT MCC testing 29 Jan'21 Testing agency

13 HT Panel testing 3 Feb'21 Testing agency


14 HT Panel commissioning 15 Feb'21 Specialist from DAI or Vendor 10.02.2021
15 Transformer Charging 18 Feb'21
16 LT MCC charging 20 Feb'21
17 Actuator installation & termination 30 Jan'21
18 AHU Starter Panel charging 27 Jan'21
19 AHU motor no-load testing 6 Feb'21
20 Chiller plant motor no-load test 25 Feb'21

Chilled water pipe insulation( Only Puff 1st lot by


21
installation) 28 Feb'21 Puff insulation 22.01.21. 2nd
lot by 15.02.21

22
Chiller commissioning & rectification and 15 Mar'21 Kirloskar Engineer 01.03.2021
CT commissioning
23 LT cabling for controller 12 Mar'21 LT Cable supply 31.01.2021
24 Pan Humidifier installation 20 Mar'21
25 Thermostat installation 24 Mar'21
26 Humidostat installation 27 Mar'21

Priority # 2 (second phase)


CTL ECR & Pulpit
Roll Shop ECR and Laboratory
HSM Pulpit
DC Pulpit
TF ECR (main & maintenance)
Service building Roll Shop & Mill areas
Area Repar ECR
TSC ECR & Pulpit)

Site
Site
Site
Site
Site
Site
Site
Site
Site
Site
Site
Site
Site
Site
Site
Site
Site
Site
BLE

SPCPL

Sourav
Sourav
Sourav
Sourav
Sourav
Sourav
Sourav
Sourav
RESPONSI

basis
REMARKS

Kit received at site


Material taken from
SPCPL on returnable

Wed 1-Jan-21
Thu 7-Jan-21
Fri 8-Jan-21
Sat 9-Jan-21
Sun 10-Jan-21
Mon 11-Jan-21
Tue 12-Jan-21
Wed 13-Jan-21
Thu 14-Jan-21
Fri 15-Jan-21
Sat 16-Jan-21
Sun 17-Jan-21
Mon 18-Jan-21
Tue 19-Jan-21
Jan-21

Wed 20-Jan-21
Thu 21-Jan-21
Fri 22-Jan-21
Sat 23-Jan-21
Sun 24-Jan-21
Mon 25-Jan-21
Tue 26-Jan-21
Wed 27-Jan-21
Thu 28-Jan-21
Fri 29-Jan-21
Sat 30-Jan-21
Sun 31-Jan-21
Mon 1-Feb-21
Tue 2-Feb-21
Wed 3-Feb-21
Thu 4-Feb-21
Fri 5-Feb-21
Sat 6-Feb-21
Sun 7-Feb-21
Mon 8-Feb-21
Tue 9-Feb-21
Wed 10-Feb-21
Thu 11-Feb-21
Fri 12-Feb-21
Sat 13-Feb-21
Sun 14-Feb-21
Mon 15-Feb-21
Feb-21

Tue 16-Feb-21
Wed 17-Feb-21
Thu 18-Feb-21
Fri 19-Feb-21
Sat 20-Feb-21
Sun 21-Feb-21
Mon 22-Feb-21
Tue 23-Feb-21
Wed 24-Feb-21
Thu 25-Feb-21
Fri 26-Feb-21
Sat 27-Feb-21
Sun 28-Feb-21
Mon 1-Mar-21
Tue 2-Mar-21
Wed 3-Mar-21
Thu 4-Mar-21
Fri 5-Mar-21
Sat 6-Mar-21
Sun 7-Mar-21
Mon 8-Mar-21
Tue 9-Mar-21
Wed 10-Mar-21
Thu 11-Mar-21
Mar-
Fri 12-Mar-21
Sat 13-Mar-21
Sun 14-Mar-21
Mon 15-Mar-21
Tue 16-Mar-21
Wed
Mar-21

17-Mar-21
Thu 18-Mar-21
Fri 19-Mar-21
Sat 20-Mar-21
Sun 21-Mar-21
Mon 22-Mar-21
Tue 23-Mar-21
Wed 24-Mar-21
Thu 25-Mar-21
Fri 26-Mar-21
Sat 27-Mar-21
Sun 28-Mar-21
Mon 29-Mar-21
Tue 30-Mar-21
Wed 31-Mar-21

You might also like