ACTION PLAN/ ACCOMPLISHMENT PLAN

BRIGADA ESKWELA
S. Y 2018-2019

DATE ACTIVITIES REMARKS

May 28, 2018  Construct temporary learning  Done


(Monday) center (TLC) for Grade 5 class The construction of TLC was accomplished
through the help of the construction workers
of the two-storey building of the school.

May 29, 2018  Repainting of wood chairs  Done


(Tuesday)  Washing plastic chairs  Done
 Installation of temporary  Done
blackboard Repainting of wood chairs was
accomplished through the help of volunteers
from Greenwich Bacarra Rd, ARMY Reservist
and other parents; washing of the plastic
chairs was done by the alumnae of the
school; and installation of temporary
blackboard was done by the construction
workers of the two-storey building of the
school.

May 30, 2018  Cleaning of the temporary  Done


(Wednesday) learning center
 Cleaning and washing of  Done
electric fans Day 3 activities were accomplished
through the help of some parents of incoming
grade 5 pupils.

May 31, 2018  Fixing of wiring for ceiling fans  Done


(Thursday) and wall fan. The wirings were done by the Engineer
in-charge in the construction of the two-storey
building of the school.

June 1, 2018  Reconstruct bulletin boards  Done


(Friday)  Arranging the classroom set  Done
up

June 2, 2018
( Saturday)  Final reconstruction of  Done
classroom
 Make instructional materials  Done

Prepared by:

JENNIE MAE D. IPAC


Teacher I

NOTED:

SONIA REINAVIC M. ESPIRITU


Principal I