Professional Documents
Culture Documents
Minutes of Meeting
Attendees:
No. Name Organisation Position Mobile No. Email
1 Eng. Shahatah MOD Sr. Electrical Engineer
2 Eng.Mohamed AL qurashi JCD
3 Eng.Hasan Shalaan WSP Consultant
4 Eng. Essam MBL Utility Engineer
5 Eng. Ahmed Hakeem MBL Electrical Engineer
6 Eng.Abdulrahman AlNajrani JCD Construction Engineer
Page 1 of 3
Jeddah Central Development Company شركة وسط جدة للتطوير
Meeting Notes
NO. Description Action Date
1. Some substations were upgraded from 500KVA and 750KVA to 1000KVA JCD/MBL
3. The diversion plan was explained by Eng. Ahmad Hakim, and all the points -
of concern of MOD (will be mentioned in this report) were discussed.
4. In MS-4, it was agreed that one loop will be cancelled (serving Phase 1), and JCD/MBL
other two loops will be combined in a single loop.
5. MOD representive Eng. Shahatah requested to remove one joint (joint 5), JCD/MBL
and to connect the cable directly to SS-403.
6. MOD representive Eng. Shahatah requested to keep one of the main feeders MBL
of SS-441, and not to shift it to a new feeder.
7. MOD representive Eng. Shahatah requested to include the diversion of SS- MBL
508 and SS-625 in the report.
8. MOD requested another study, which is connecting the substations that are MOD/JCD/MBL
inside phase 2 and were previously served from phase one, to the existing
MV switchgear that is currently inside phase 2. This means that the cables
that are feeding the loads inside phase 2 are to be shifted to substation
already existing inside phase 2.
However it was agreed that this option is not required because it needs a lot
of excavation inside phase 2.
9. It was agreed that there is no need for MOD to witness the low voltage MBL
disconnection.
10.MOD representive Eng. Shahata requested to keep the MV loop that is MOD/JCD/MBL
feeding the camp in operation.
11.It was stated that the load calculations of the MV Switchgear are based on
the full capacity of the substations (rated capacity) and not on the demaind
Page 2 of 3
Jeddah Central Development Company شركة وسط جدة للتطوير
load.
12.MOD representive Eng. Shahata requested that the MV Switchgear to be
supplied with earthing for each section
Page 3 of 3