Project name: wind farm Revision:

Country: ROMANIA Reference:

Nº PROJECT INFORMATION

GENERAL INFORMATION 2012 2021

1 Project Name WIND FARM WIND FARM


132MW/-22 TURBINES SIEMENS-GAMESA
2 Nominal total power and number of turbines(WTG type if it is decided) 44MW-/-22 TURBINES Vestas V-90 2.Mw
SG 6.0-170.
3 Area / region Muntenia sud /Teleorman Muntenia sud /Teleorman
4 Company Name and the Registered office
5 Contact person
LANDS
6 Type of land ownership (public/private) public/private public/private
7 Type of contract, validity period (years) and price for unit of the contract Joint venture contract 49 years Joint venture contract 39 years
8 Total surface 1.400.000 m 1.400.000 m

Optimization completed. The file will be The optimization has not been completed.
9 Situation of land registration
made available in the attached document. Payment is required.

WIND RESOURCE
10 Owned wind met mast in the area available (height of the wind mast) 40 m 40 m
11 Date of instalation 04/17/2009/-04/18/2011
Coordenates of the wind mast wind study completed wind study completed
12
13 Wind Resource Study yes, 13.04.2010 yes 21.10 2021
14 Wind data: average speed and predominant direction W-E W-E
44 MW Coordinates UTM in STEREO-70 132 MW Coordinates UTM in STEREO-70
Layout (coordenates UTM) of the wind farm and installed power system. They will be provided in a separate system. They will be provided in a
15 file. separate file.
16 Number of net operating hours 2980 3100
ENVIRONMENT
17 Natura2000 affected? (YES/NO). If yes, please specify NO NO Afected
18 Protected areas affected? (YES/NO). If yes, please specify NO NO Afected
Environmental Impact Asessment No environmental impact. No environmental impact.
19
Aditional studies (birds, landscape… etc). YES/NO. If yes, please specify NO
20 NO
21 Environmental permit NO (unpaied yet) NO (unpaied yet)
GRID CONECTION
YES Application for the issuance of the
22 Location Approval available, emission date; Technical Connection Approval No. 44884 /
yes, 13.04.2010 18.10.2021 TRNSELELECTRICA SA

Yes Application for the issuance of the Site


23 Solution Study available, emission date, economical implication, proposed solutions; Available 24.02.2011 Permit No. 9536 / 15.10.2021
TRANSELECTRICA SA

Technical Connection Approval (ATR) available, emission date, characteristics, prolongation date; NR.86/11779/13.09.2011
NR.33/7248/27.03.2012
Available NR.86/11779/13.09.2011
25 ATR is available description
NR.33/7248/27.03.2012 It is scheduled for February 15, 2022

26 Grid Connection Contract/ If is not available description of status Network connection contract / Not signed
missing Paid
27 Grid Operator TRANSELECTRICA SA
28 Line and subestation (voltage level, etc) high voltage 110 Kw
29 Wind farm tension 110 Kw.
30 Distance considerered to the grid connection 14000 m
31 Price of the conection solution (opted solution) to be seen in ATR
URBANISM
32 Investment Positive Opinion from Local Council YES 04.02.201O YES 02.09.2021
33 Development of cadastre studies YES YES
YES Nr.76/ 13.04.201O
34 Certificate of Urbanism YES Nr.16/ 02.09.2021
Nr.49/21.04.2011
35 Opinion of the Romanian Civil Aeronautical Authorities YES Nr.26893/1085. 06.10.2010
36 Opinion of the Teleorman Environmental Protection Agency YES Nr.8956/21.09.2010
37 Agreement of the Ministry of Administration and Interior YES Nr.52991/17.11.2010
38 Ministerial Agreement Roads and Bridges YES Nr.2712/22.11.2010
39 Approval of the Ministry of Culture and National Heritage YES Nr.23/A/27.10.2010
40 Opinion of the Ministry of National Defense YES Nr.D/1756/15.10.2010
41 Change of the designation of the land NO NO
42 Puz Approval (please specify all the authorities) not yet NO
Issued Permits for the Building Authorization (please specify the permit , the authorities, and the
43 to be presented during the meeting After ATR
emision date)
44 PAC/POE not yet
45 Technical Study not yet
46 Geotechnical Study not yet
47 Building Permit not yet
depends on the financing. Average: MAX 1.
48
Estimated date for Building Authorization year from now