You are on page 1of 13

CLIENT BWE Energy India

PROJECT HAZIRA DELIVERABLE SCHEDULE AND PROGRESS REPORT - PRESSURE PARTS


PROJECT NUMBER
Detail Engineering
Progress Overall
Basic Inputs received on Total IBR 2nd unit
% as per drawing Rev 0
Sl.No Drawing Title Drawing Number Schedule Weightag Rev 1 Rev 2 Approval Completio Remarks
completio approva (90%)
e (5%) n (5%)
n l status
Rev 0 Rev 1 Rev 2 Rev 3 Planned Actual

Wt x
50.00 %progress

I STEAM DRUM 2.00

Steam drum with necessary stubs and


1
attachment
* 0.50 0.00

2 Steam drum cyclone separator * 0.50 0.00

3 Steam drum scrubbers * 0.50 0.00

4 Steam drum other internals and attachments * 0.50 0.00

II EVAPORATOR 15.00

5 Furnace front wall panel (tube to fin to tube weld) * 1.00 0.00

Furnace front wall bottom header with necessary


6
stubs & attachments
* 0.50 0.00

Furnace front wall top header with necessary


7
stubs & attachments
* 0.50 0.00

Wall blower, Burner Opening & Seal boxes for


8
front wall panel
* 0.80 0.00

Furnace rear wall panel (tube to fin to tube weld)


9
including bottom hopper and goose neck panels
* 1.00 0.00

Furnace rear wall bottom header with necessary


10
stubs & attachments
* 0.50 0.00

Furnace rear wall top headers (Gitter 1 & 2 Top


11
headers) with necessary stubs & attachments
* 0.50 0.00

Wall blower, Burner Opening & Seal boxes for


12
rear wall panel
* 0.50 0.00

Furnace right side wall panel (tube to fin to tube


13
weld)
* 1.00 0.00

Furnace right side wall bottom headers with


14
necessary stubs & attachments
* 0.50 0.00

Furnace right side wall top header with


15
necessary stubs & attachments
* 0.50 0.00

Access door & other opening Seal boxes for


16
right side wall panel
* 0.50 0.00

Furnace left side wall panel (tube to fin to tube


17
weld)
* 0.70 0.00

Furnace left side wall bottom header with


18
necessary stubs & attachments
* 0.50 0.00

Furnace left side wall top header with necessary


19
stubs & attachments
* 0.50 0.00

20 Access door, Seal boxes for left side wall * 0.50 0.00

21 Furnace steam cooled roof wall panel * 1.00 0.00

Page 1 of 13
CLIENT BWE Energy India
PROJECT HAZIRA DELIVERABLE SCHEDULE AND PROGRESS REPORT - PRESSURE PARTS
PROJECT NUMBER
Detail Engineering
Progress Overall
Basic Inputs received on Total IBR 2nd unit
% as per drawing Rev 0
Sl.No Drawing Title Drawing Number Schedule Weightag Rev 1 Rev 2 Approval Completio Remarks
completio approva (90%)
e (5%) n (5%)
n l status
Rev 0 Rev 1 Rev 2 Rev 3 Planned Actual

Furnace steam cooled roof wall panel inlet


22
header
* 0.40 0.00

23 Seal boxes for roof wall * 0.40 0.00

24 Vestibule and second pass common inlet header * 0.40 0.00

25 Vestibule Bottom panel * 0.40 0.00

26 Vestibule Right Side panel * 0.40 0.00

27 Vestibule Right side top & bottom header * 0.40 0.00

28 Vestibule Left side panel * 0.40 0.00

29 Vestibule Left side top & bottom header * 0.40 0.00

30 Gitter tube 1 * 0.40 0.00

31 Gitter tube 2 * 0.40 0.00

III Second pass steam cooled wall 7.00

Steam cooled second pass front wall including


32
dead panel, access door and seal boxes
* 1.00 0.00

Steam cooled second pass right and left side


33 wall including dead panel, access door and seal * 1.00 0.00
boxes

Steam cooled second pass right and left side


34
wall inlet headers
* 1.00 0.00

Steam cooled second pass rear wall including


35
dead panel
* 0.50 0.00

36 Steam cooled second pass roof wall panel * 0.50 0.00

37 Steam cooled second pass outlet ring header * 0.50 0.00

38 Second pass suspension tubes * 0.50 0.00

39 Second pass suspension tubes inlet headers * 0.50 0.00

40 Second pass suspension tubes outlet headers * 0.50 0.00

41 Gitter tube 3 * 0.50 0.00

42 Screen loose tubes * 0.50 0.00

IV Super Heaters 8.00

43 Super heater 1 coil with necessary bends * 1.00 0.00

Page 2 of 13
CLIENT BWE Energy India
PROJECT HAZIRA DELIVERABLE SCHEDULE AND PROGRESS REPORT - PRESSURE PARTS
PROJECT NUMBER
Detail Engineering
Progress Overall
Basic Inputs received on Total IBR 2nd unit
% as per drawing Rev 0
Sl.No Drawing Title Drawing Number Schedule Weightag Rev 1 Rev 2 Approval Completio Remarks
completio approva (90%)
e (5%) n (5%)
n l status
Rev 0 Rev 1 Rev 2 Rev 3 Planned Actual

44 Super heater 1 inlet header * 0.25 0.00

45 Super heater 1 outlet header * 0.25 0.00

46 Super heater 2 coil with necessary bends * 0.50 0.00

47 Super heater 2 inlet header * 0.50 0.00

48 Super heater 2 outlet header * 0.50 0.00

49 Super heater 2 inlet intermittent header * 0.50 0.00

50 Super heater 2 outlet intermittent header * 0.50 0.00

51 Super heater 3 coil with necessary bends * 0.50 0.00

52 Super heater 3 inlet header * 0.50 0.00

53 Super heater 3 outlet header * 0.50 0.00

54 Super heater 3 inlet intermittent header * 0.50 0.00

55 Super heater 3 outlet intermittent header * 0.50 0.00

56 Super heater 4 coil with necessary bends * 0.50 0.00

57 Super heater 4 inlet header * 0.50 0.00

58 Super heater 4 outlet header * 0.50 0.00

V Re Heaters 2.00

59 Re heater coil 1 with necessary bends * 0.50 0.00

60 Re heater 1 inlet header * 0.25 0.00

61 Re heater 1 outlet header * 0.25 0.00

62 Re heater coil 2 with necessary bends * 0.50 0.00

63 Re heater 2 inlet header * 0.25 0.00

64 Re heater 2 outlet header * 0.25 0.00

VI Economiser 1.50

66 Economizer coil including bends * 0.50 0.00

Page 3 of 13
CLIENT BWE Energy India
PROJECT HAZIRA DELIVERABLE SCHEDULE AND PROGRESS REPORT - PRESSURE PARTS
PROJECT NUMBER
Detail Engineering
Progress Overall
Basic Inputs received on Total IBR 2nd unit
% as per drawing Rev 0
Sl.No Drawing Title Drawing Number Schedule Weightag Rev 1 Rev 2 Approval Completio Remarks
completio approva (90%)
e (5%) n (5%)
n l status
Rev 0 Rev 1 Rev 2 Rev 3 Planned Actual

67 Economizer inlet header * 0.50 0.00

68 Economizer outlet header * 0.50 0.00

VII Integral piping 5.50

Economizer recirculation piping from down


69
comer to economizer inlet
* 0.25 0.00

70 Economiser inlet piping * 0.25 0.00

71 Feed piping from Economiser to Steam drum * 0.25 0.00

72 Riser piping from Evaporator top Headers * 0.30 0.00

73 Down comer, down comer bottle & supply piping * 0.30 0.00

Link between steam drum to furnace roof wall


74
inlet header.
* 0.25 0.00

Link between common header to second pass


75
top headers
* 0.25 0.00

Link between common header to suspension


76
tubes top headers
* 0.25 0.00

Link between common header to vestibule top


77
headers
* 0.25 0.00

Link between vestibule bottom headers to


78
intermittent headers
* 0.25 0.00

Links between SH2 intermittent headers to main


79
outlet header
* 0.25 0.00

Attemperator piping from SH2 main outlet


80
header to SH3 main inlet header
* 0.25 0.00

81 Attemperator 1.1, 1.2, 2.1 & 2.2 * 0.50 0.00

Links between SH3 main inlet header to


82
intermittent headers
* 0.20 0.00

Links between SH3 intermittent headers to main


83
outlet header
* 0.20 0.00

Attemperator piping from SH3 main outlet


84
header to SH4 inlet header
* 0.20 0.00

Main steam outlet piping from SH4 outlet header


85
to outlet of main steam stop valve
* 0.20 0.00

86 HP byepass piping to Re heater * 0.20 0.00

87 Re heater 1 inlet piping from TP * 0.20 0.00

Attemperator piping from Re heater 1 to Re


88
heater 2
* 0.20 0.00

89 Attemperator 3.1 & 3.2 * 0.30 0.00

Page 4 of 13
CLIENT BWE Energy India
PROJECT HAZIRA DELIVERABLE SCHEDULE AND PROGRESS REPORT - PRESSURE PARTS
PROJECT NUMBER
Detail Engineering
Progress Overall
Basic Inputs received on Total IBR 2nd unit
% as per drawing Rev 0
Sl.No Drawing Title Drawing Number Schedule Weightag Rev 1 Rev 2 Approval Completio Remarks
completio approva (90%)
e (5%) n (5%)
n l status
Rev 0 Rev 1 Rev 2 Rev 3 Planned Actual

90 Re heater 2 outlet piping up to TP * 0.20 0.00

VIII Blow tanks 1.00

91 Continuous blow down tank with internals * 0.50 0.00

92 Intermittent blow down tank with internals * 0.50 0.00

IX Non-Pressure Part 8.00

93 Buck stay * 0.00

94 Seismic restraints * 0.00

Penthouse casing, frames, access opening, door


95
& sealings, etc.
* 0.00

96 Pressure part sealing at various locations * 0.00

97 Furnace bottom sealing arrangement * 0.00

98 Seal boxes & cover plates for all openings * 0.00

99 Supporting stay at furnace nose location * 0.00

Economiser bottom casing with necessary


100
attachments
* 0.00

101 Anti vibration baffles * 0.00

Doors (Normally it is a standard drawings


102
supplied by client)
* 0.00

Top suspension rods with necessary


103
accessories (both spring/without spring type)
* 0.00

104 Steam drum suspension * 0.00

105 High crown * 0.00

106 Header supports * 0.00

107 Instrument pockets & its accessories * 0.00

108 Supports for integral piping - Spring type * 0.00

109 Supports for integral piping - Rigid type * 0.00

110 Economiser supports * 0.00

111 Skin casing * 0.00

Page 5 of 13
CLIENT BWE Energy India
PROJECT HAZIRA DELIVERABLE SCHEDULE AND PROGRESS REPORT - PRESSURE PARTS
PROJECT NUMBER
Detail Engineering
Progress Overall
Basic Inputs received on Total IBR 2nd unit
% as per drawing Rev 0
Sl.No Drawing Title Drawing Number Schedule Weightag Rev 1 Rev 2 Approval Completio Remarks
completio approva (90%)
e (5%) n (5%)
n l status
Rev 0 Rev 1 Rev 2 Rev 3 Planned Actual

50.00

Total Progress 0.0

Page 6 of 13
CLIENT BWE Energy India
PROJECT HAZIRA DELIVERABLE SCHEDULE AND PROGRESS REPORT - PIPING
PROJECT NUMBER
Detail Engineering
Progress Overall
Basic Inputs received on IBR 2nd unit
Total % as per drawing Rev 0
Sl.No Drawing Title Drawing Number Schedule Rev 1 Rev 2 Approval Completio Remarks
Weightage completio approva (90%)
(5%) n (5%)
n l status
Rev 0 Rev 1 Rev 2 Rev 3 Planned Actual

Wt x
23 %progress

Feed water piping with control station from TP to


1 economiser inlet piping with necessary valves & * 0.50 0.00
fittings

Intermittent blow down pipe from drum to IBD


2
tank with all necessary fitting and valves
* 0.50 0.00

Blow off piping from down comer to blow down


3 line
* 0.50 0.00

Continuous blow down pipe from drum to CBD


4
tank with all necessary fitting and valves
* 0.50 0.00

Spray water piping from feed water line to super


5 heater attemperators
* 0.50 0.00

Spray water piping from feed water line to


6
reheater attemperators
* 0.50 0.00

7 All steam & water drains to blow down tank * 0.50 0.00

All steam & water vents to vent receiver and to


8
blow down tank
* 0.50 0.00

HFO oil forward piping to front burners including


9 steam tracing with provision for valves and * 0.50 0.00
fittings

HFO Oil return piping with steam tracing


10
including provision for valves and fittings
* 0.50 0.00

Auxiliary steam piping for steam tracing for HFO


11 Forwarding / return piping
* 0.50 0.00

12 Auxiliary steam piping drain to IBD tank * 0.50 0.00

LDO Oil forwarding piping to all five elevation


13 burners
* 0.50 0.00

14 Atomizing steam piping for HFO * 0.50 0.00

15 Atomizing air piping for LDO * 0.50 0.00

Auxiliary steam piping from TP to SCAPH and


16
Condensate water to IBD
* 0.50 0.00

17 Auxiliary steam piping to steam soot blower * 0.50 0.00

Soot blower steam piping from SH outlet header


18
to soot blower inlet
* 0.50 0.00

High pressure water piping from boiler front


19 column to soot blower.
* 0.50 0.00

20 Mill seal air pipes * 0.50 0.00

21 Feeder seal air pipes * 0.50 0.00

22 Air heater seal air pipes * 0.50 0.00

Service air pipe from boiler front column to


23 individual equipment
* 0.50 0.00

Page 7 of 13
CLIENT BWE Energy India
PROJECT HAZIRA DELIVERABLE SCHEDULE AND PROGRESS REPORT - PIPING
PROJECT NUMBER
Detail Engineering
Progress Overall
Basic Inputs received on IBR 2nd unit
Total % as per drawing Rev 0
Sl.No Drawing Title Drawing Number Schedule Rev 1 Rev 2 Approval Completio Remarks
Weightage completio approva (90%)
(5%) n (5%)
n l status
Rev 0 Rev 1 Rev 2 Rev 3 Planned Actual

Instrument air piping from boiler front column to


24
individual instruments
* 0.50 0.00

Cooling water supply & return piping between


25 TP & individual equipments / auxiliaries
* 0.50 0.00

Service water supply & return piping between TP


26
& individual equipments / auxiliaries
* 0.50 0.00

High pressure chemical dosing system with


27 piping and valves & fittings
* 0.50 0.00

Temporary steam blowing piping with valves and


28
fittings
* 0.50 0.00

29 N2 Preservation piping with valves and fittings * 0.50 0.00

30 Boiler initial filling piping with valves and fittings * 0.50 0.00

Air heater water washing piping with valves and


31 fittings
* 0.50 0.00

32 Service water piping to electro static precipitator * 0.50 0.00

33 Fire fighting piping with valves and fittings * 0.50 0.00

34 Start-up vent piping * 0.50 0.00

35 Exhaust piping for Safety valves * 0.50 0.00

Temporary acid cleaning and alkali boil out


36
piping with necessary valves and fittings
* 0.50 0.00

37 Instrument connection stubs for all line * 0.50 0.00

38 Supports for all piping – spring type * 0.50 0.00

39 Supports for all piping – rigid type * 0.50 0.00

40 Necessary supporting structure for all piping * 0.50 0.00

41 Equipment/vessel trim piping * 0.50 0.00

42 Preservation piping * 0.50 0.00

43 Fuel gas piping * 0.50 0.00

44 Piping Terminal Point drawing (All piping) * 0.50 0.00

22.00

Total Progress 0.0

Page 8 of 13
CLIENT BWE Energy India
PROJECT HAZIRA DELIVERABLE SCHEDULE AND PROGRESS REPORT - DUCTING
PROJECT NUMBER
Detail Engineering
Progress Overall
Basic Inputs received on Total IBR 2nd unit
% as per drawing Rev 0
Sl.No Drawing Title Drawing Number Schedule Weightag Rev 1 Rev 2 Approval Completio Remarks
completio approva (95%)
e (0%) n (5%)
n l status
Rev 0 Rev 1 Rev 2 Rev 3 Planned Actual

Wt x
17 %progress

1 Cold air duct from FD Fan to SCAPH * 1.00 0.00

2 Interconnecting duct between FD outlet duct * 1.00 0.00

3 Hot air duct from SCAPH to RAPH * 1.00 0.00

4 Hot air duct from SCAPH to common bus duct * 1.00 0.00

Hot air from common bus duct to individual


5
burner
* 1.00 0.00

Combustion air (Air split) duct for hot tertiary


6
and secondary air to each burner
* 1.00 0.00

Hot air duct from common bus duct to PA Fan


7
inlet
* 1.00 0.00

Tempering air duct from common bus duct to PA


8
Fan inlet
* 1.00 0.00

9 PA Fan inlet mixed air duct * 1.00 0.00

10 PA Fan outlet mixed pressurized air duct to Mill * 1.00 0.00

11 Economizer hopper & necessary supports * 1.00 0.00

Hot flue gas ducting from economizer to air pre


12
heater inlet
* 1.00 0.00

13 RAPH Hopper * 1.00 0.00

14 Hot flue gas duct from RAPH outlet to ESP inlet * 1.00 0.00

Hot air duct from RAPH outlet to flue gas


15
recirculation line
* 1.00 0.00

16 Hot flue gas duct from ESP outlet to ID Fan inlet * 1.00 0.00

17 Interconnecting duct between ID Fan inlet duct * 1.00 0.00

Hot flue gas duct from ID fan outlet to chimney


18
inlet with matching flanges.
* 1.00 0.00

Provision duct for flue gas desulphurization with


19
blind flanges
* 1.00 0.00

Flue gas recirculation duct from ID Fan outlet to


20
furnace right and left side wall bottom.
* 1.00 0.00

Corex gas fuel line from boiler front column to


21 each burner with provision for valves and * 1.00 0.00
fittings

22 Expansion joints - metallic and non metallic type * 1.00 0.00

23 Instruments tapping & accessories * 1.00 0.00

Page 9 of 13
CLIENT BWE Energy India
PROJECT HAZIRA DELIVERABLE SCHEDULE AND PROGRESS REPORT - DUCTING
PROJECT NUMBER
Detail Engineering
Progress Overall
Basic Inputs received on Total IBR 2nd unit
% as per drawing Rev 0
Sl.No Drawing Title Drawing Number Schedule Weightag Rev 1 Rev 2 Approval Completio Remarks
completio approva (95%)
e (0%) n (5%)
n l status
Rev 0 Rev 1 Rev 2 Rev 3 Planned Actual

24 Supports for all ducting - Spring type * 1.00 0.00

25 Supports for all ducting - Rigid type * 1.00 0.00

Necessary supporting structure for Ducting &


26
Hoppers
* 1.00 0.00

Lifting structures with mono rail beam for Fans,


27
Mills, etc.
* 0.50 0.00

28 Terminal Point Drawing * 0.50 0.00

27.00

Total Progress 0.0

Page 10 of 13
CLIENT BWE Energy India
PROJECT HAZIRA
DELIVERABLE SCHEDULE AND
PROGRESS REPORT
PROJECT NUMBER

Total Weightage Progress % as


Sl. No. Description Planned Actual Remarks
10% per completion

I HYDROTEST FOR UNIT 1 (or) 30th Jan 2012 (Which ever is early) 5%

1 Pressure Parts 3% 0

2 Piping 2% 0

II As Built Drawings Unit 1 2.5%

Final Document (IBR)


1 Completion of IBR Final Document of Pressure Parts 1.0% 0 approvals itself shall
be considerd as built

2 As built updation of Unit-1 Piping 1.0% 0

3 As built updation of Unit-1 Ducting 0.5% 0

III As Built Drawings Unit 2 2.5%

Final Document (IBR)


1 Completion of IBR Final Document of Pressure Parts 1.0% 0 approvals itself shall
be considerd as built

2 As built updation of Unit-2 Piping 1.0% 0

3 As built updation of Unit-2 Ducting 0.5% 0

Total weigtage ( Hydro test of unit-1 and as-built of unit 1&2) 10%

Page 11 of 13
CLIENT BWE Energy India
PROJECT HAZIRA
DELIVERABLE SCHEDULE AND
PROGRESS REPORT
PROJECT NUMBER

TOTAL PROGRESS 0

Page 12 of 13
CLIENT BWE Energy India
PROJECT HAZIRA DELIVERABLE SCHEDULE AND PROGRESS REPORT - PRESSURE PARTS
PROJECT NUMBER

Mile stone billing for each deliverbales

IBR REV or 2nd unit IBR Asbuilt Asbuilt


Sl.No Total Billing Break up Weightage in % 1st Iuuse Hydro test Total
approval DCN submission unit 1 unit 2

1 Pressure Parts & Non pressure parts 50 90% 5% 0% 5% 100%

2 Piping 23 90% 5% 0% 5% 100%

3 Ducting 17 95% 0% 0% 5% 100%

4 Hydrotest 5 0% 0% 0% 100% 100%

5 As Built 5 50% 50% 100%

Total 100.00

Sl.No Department Monthly Progress


Total
Progress
Nov' 10 Dec'10 Jan'11 Feb'11 Mar'11 April'11 May'11 June'11 July'11 Aug'11 Sep'11 Oct'11 Nov'11 Dec'11 Jan'12

1 Pressure Parts 0

2 Piping 0

3 Ducting 0

4 Hydrotest 0

5 As Built 0

Monthly over progress 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Notes Cumulative 0
1 Over all weightage (55+27+18) of each discipline are distributed to each deliverables (50+23+17=90%) and Hydro test (3% +2% =5%) and asbuilt drgs weightage 2.5% for unit1 + 2.5% for unit2, in total 100%.

2 Hydro test weightage 5% are considered only for pressure part (3%) and piping (2%) of unit 1 only.

3 As-Built Weightage of 5% are considered 2.5% for each unit.

4 As-Built Weightage of each unit 2.5% are distributed to pressure part (1%) + Piping (1%) + Ducting (0.5%)

5 As built of pressure Parts shall be claimed after updation of DCN and final ducuments submussion to IBR by fabricator.

Page 13 of 13

You might also like