Deliverable Schedule and Progress Report - Pressure Parts: I Steam Drum 2.00
Deliverable Schedule and Progress Report - Pressure Parts: I Steam Drum 2.00
Wt x
50.00 %progress
II EVAPORATOR 15.00
5 Furnace front wall panel (tube to fin to tube weld) * 1.00 0.00
20 Access door, Seal boxes for left side wall * 0.50 0.00
Page 1 of 13
CLIENT BWE Energy India
PROJECT HAZIRA DELIVERABLE SCHEDULE AND PROGRESS REPORT - PRESSURE PARTS
PROJECT NUMBER
Detail Engineering
Progress Overall
Basic Inputs received on Total IBR 2nd unit
% as per drawing Rev 0
Sl.No Drawing Title Drawing Number Schedule Weightag Rev 1 Rev 2 Approval Completio Remarks
completio approva (90%)
e (5%) n (5%)
n l status
Rev 0 Rev 1 Rev 2 Rev 3 Planned Actual
Page 2 of 13
CLIENT BWE Energy India
PROJECT HAZIRA DELIVERABLE SCHEDULE AND PROGRESS REPORT - PRESSURE PARTS
PROJECT NUMBER
Detail Engineering
Progress Overall
Basic Inputs received on Total IBR 2nd unit
% as per drawing Rev 0
Sl.No Drawing Title Drawing Number Schedule Weightag Rev 1 Rev 2 Approval Completio Remarks
completio approva (90%)
e (5%) n (5%)
n l status
Rev 0 Rev 1 Rev 2 Rev 3 Planned Actual
V Re Heaters 2.00
VI Economiser 1.50
Page 3 of 13
CLIENT BWE Energy India
PROJECT HAZIRA DELIVERABLE SCHEDULE AND PROGRESS REPORT - PRESSURE PARTS
PROJECT NUMBER
Detail Engineering
Progress Overall
Basic Inputs received on Total IBR 2nd unit
% as per drawing Rev 0
Sl.No Drawing Title Drawing Number Schedule Weightag Rev 1 Rev 2 Approval Completio Remarks
completio approva (90%)
e (5%) n (5%)
n l status
Rev 0 Rev 1 Rev 2 Rev 3 Planned Actual
73 Down comer, down comer bottle & supply piping * 0.30 0.00
Page 4 of 13
CLIENT BWE Energy India
PROJECT HAZIRA DELIVERABLE SCHEDULE AND PROGRESS REPORT - PRESSURE PARTS
PROJECT NUMBER
Detail Engineering
Progress Overall
Basic Inputs received on Total IBR 2nd unit
% as per drawing Rev 0
Sl.No Drawing Title Drawing Number Schedule Weightag Rev 1 Rev 2 Approval Completio Remarks
completio approva (90%)
e (5%) n (5%)
n l status
Rev 0 Rev 1 Rev 2 Rev 3 Planned Actual
Page 5 of 13
CLIENT BWE Energy India
PROJECT HAZIRA DELIVERABLE SCHEDULE AND PROGRESS REPORT - PRESSURE PARTS
PROJECT NUMBER
Detail Engineering
Progress Overall
Basic Inputs received on Total IBR 2nd unit
% as per drawing Rev 0
Sl.No Drawing Title Drawing Number Schedule Weightag Rev 1 Rev 2 Approval Completio Remarks
completio approva (90%)
e (5%) n (5%)
n l status
Rev 0 Rev 1 Rev 2 Rev 3 Planned Actual
50.00
Page 6 of 13
CLIENT BWE Energy India
PROJECT HAZIRA DELIVERABLE SCHEDULE AND PROGRESS REPORT - PIPING
PROJECT NUMBER
Detail Engineering
Progress Overall
Basic Inputs received on IBR 2nd unit
Total % as per drawing Rev 0
Sl.No Drawing Title Drawing Number Schedule Rev 1 Rev 2 Approval Completio Remarks
Weightage completio approva (90%)
(5%) n (5%)
n l status
Rev 0 Rev 1 Rev 2 Rev 3 Planned Actual
Wt x
23 %progress
7 All steam & water drains to blow down tank * 0.50 0.00
Page 7 of 13
CLIENT BWE Energy India
PROJECT HAZIRA DELIVERABLE SCHEDULE AND PROGRESS REPORT - PIPING
PROJECT NUMBER
Detail Engineering
Progress Overall
Basic Inputs received on IBR 2nd unit
Total % as per drawing Rev 0
Sl.No Drawing Title Drawing Number Schedule Rev 1 Rev 2 Approval Completio Remarks
Weightage completio approva (90%)
(5%) n (5%)
n l status
Rev 0 Rev 1 Rev 2 Rev 3 Planned Actual
30 Boiler initial filling piping with valves and fittings * 0.50 0.00
22.00
Page 8 of 13
CLIENT BWE Energy India
PROJECT HAZIRA DELIVERABLE SCHEDULE AND PROGRESS REPORT - DUCTING
PROJECT NUMBER
Detail Engineering
Progress Overall
Basic Inputs received on Total IBR 2nd unit
% as per drawing Rev 0
Sl.No Drawing Title Drawing Number Schedule Weightag Rev 1 Rev 2 Approval Completio Remarks
completio approva (95%)
e (0%) n (5%)
n l status
Rev 0 Rev 1 Rev 2 Rev 3 Planned Actual
Wt x
17 %progress
4 Hot air duct from SCAPH to common bus duct * 1.00 0.00
14 Hot flue gas duct from RAPH outlet to ESP inlet * 1.00 0.00
16 Hot flue gas duct from ESP outlet to ID Fan inlet * 1.00 0.00
Page 9 of 13
CLIENT BWE Energy India
PROJECT HAZIRA DELIVERABLE SCHEDULE AND PROGRESS REPORT - DUCTING
PROJECT NUMBER
Detail Engineering
Progress Overall
Basic Inputs received on Total IBR 2nd unit
% as per drawing Rev 0
Sl.No Drawing Title Drawing Number Schedule Weightag Rev 1 Rev 2 Approval Completio Remarks
completio approva (95%)
e (0%) n (5%)
n l status
Rev 0 Rev 1 Rev 2 Rev 3 Planned Actual
27.00
Page 10 of 13
CLIENT BWE Energy India
PROJECT HAZIRA
DELIVERABLE SCHEDULE AND
PROGRESS REPORT
PROJECT NUMBER
I HYDROTEST FOR UNIT 1 (or) 30th Jan 2012 (Which ever is early) 5%
1 Pressure Parts 3% 0
2 Piping 2% 0
Total weigtage ( Hydro test of unit-1 and as-built of unit 1&2) 10%
Page 11 of 13
CLIENT BWE Energy India
PROJECT HAZIRA
DELIVERABLE SCHEDULE AND
PROGRESS REPORT
PROJECT NUMBER
TOTAL PROGRESS 0
Page 12 of 13
CLIENT BWE Energy India
PROJECT HAZIRA DELIVERABLE SCHEDULE AND PROGRESS REPORT - PRESSURE PARTS
PROJECT NUMBER
Total 100.00
1 Pressure Parts 0
2 Piping 0
3 Ducting 0
4 Hydrotest 0
5 As Built 0
Notes Cumulative 0
1 Over all weightage (55+27+18) of each discipline are distributed to each deliverables (50+23+17=90%) and Hydro test (3% +2% =5%) and asbuilt drgs weightage 2.5% for unit1 + 2.5% for unit2, in total 100%.
2 Hydro test weightage 5% are considered only for pressure part (3%) and piping (2%) of unit 1 only.
4 As-Built Weightage of each unit 2.5% are distributed to pressure part (1%) + Piping (1%) + Ducting (0.5%)
5 As built of pressure Parts shall be claimed after updation of DCN and final ducuments submussion to IBR by fabricator.
Page 13 of 13