Method Statement

Job, Contract, or Project Name Cast house vdc1 pit cleaning by super sucker (PO No. 4600002133- HP Jetting
& Vacuum Contract)
Company AL GHAITH
Expected Date & Time: Start: 22/04/2022 End: 23/04/2022
Prepared by: Name: Ibrahim Signature & date:
Position: Project Manager
Approved by: Name: Signature & date:
Position:
Description of Work:

Cast house vdc1 pit cleaning by using super sucker.

Sequence of job/task:

- Obtain necessary permits.


- Perform PSTA
- Mobilization of super sucker and manpower
- Position in super sucker cast house area and barricade the place
- Aluminium chips and sludge sucking & cleaning pit using by super sucker.
- Housekeeping, cleaning area after the job completion and hand over.

Labour (number of person required) Tools & Equipment Material


- 1 Supervisor - Super sucker with
- 1 Operator Accessories. Aluminium Chips, Sludge.
- 5 Industrial cleaner - Hand tools