RABIGH SITE ISSUE

1. Service Order - Tank 14 additional job - Work completed 3


months before - not received either P.O or invoice

2. Service Order - Water tank #3, NDT P.O/S.O not received

3. Safety first set of Requirements - confined space, work at


height 3 rd party - 3 weeks idle at site - provided from
GEMS side

4. Safety second set of Requirement - medical certificate, 3


rd party first aid training, rescue team - 3 weeks idle and
confined space activities are on hold.

5. Safety third set of Requirement - Diesel barrel cannot be


used inside the power plant instead use the diesel trucks
- work has been stopped for 2 days.
SAFETY OBSERVATIONS FROM SEC SAFETY
DEPARTMENT
Status
# Detail of Observations Action taken
(Open/Closed)
DATE
Acetylene and organ gas Immediately removed from site 06-09-2022
1 closed
cylinders in direct sunlight. and shifted to storage are.
Unwanted material and poor Unwanted material removed 06-09-2022
2 closed
housekeeping at workplace. from site and cleaned the area.
Old green mash around the Immediately removed the old 06-09-2022
3 scaffold platform obstructing the green mash and clear the closed
access. (LADDER) access. (ladder)
Immediately instruct to build 07-09-2022
Paint storage in open area
the proper paint storage shelter
4 without shelter and proper closed
and provide fire extinguisher
arrangements.
and safety data sheet.
Immediately build the shelter 07-09-2022
for temporary diesel storage,
Diesel drums in direct sunlight cover the sides by using green
5 closed
with proper arrangements. mash and diesel drum placed
inside dip tray to avoid any
spillage.

CLOSE OUT PHOTOS


BEFORE AFTER
1
2

4
5