school project upper chitral Baseline vs.

Current 21/10/22 14:34


Activity Name Variance - BL1 BL1 Start Start BL1 Finish Finish Variance - Resources
Labor Units BL1 Finish
Date
school-100 school project upper chitral 0.00 27/09/22 27/09/22 21/07/23 21/07/23 0.0d
school-100.1 preliminary work 0.00 27/09/22 27/09/22 29/09/22 29/09/22 0.0d
initial prepatory work 0.00 27/09/22 27/09/22 29/09/22 29/09/22 0.0d LABOR
project start 0.00 27/09/22 27/09/22 0.0d
school-100.3 substructure work 0.00 29/09/22 29/09/22 23/11/22 23/11/22 0.0d
excavation 0.00 29/09/22 29/09/22 13/10/22 13/10/22 0.0d LABOR
foundation masonry 0.00 13/10/22 13/10/22 23/11/22 23/11/22 0.0d LABOR, MASON
school-100.2 super structural work 0.00 27/09/22 27/09/22 20/07/23 20/07/23 0.0d
school-100.2.2 structural works 0.00 23/11/22 23/11/22 20/03/23 20/03/23 0.0d
plinth beams 0.00 23/11/22 23/11/22 01/12/22 01/12/22 0.0d MASON, LABOR
block masonry in super structure 0.00 01/12/22 01/12/22 09/01/23 09/01/23 0.0d LABOR, MASON
steel work in column 0.00 09/01/23 09/01/23 12/01/23 12/01/23 0.0d STEEL FIXER
form work for column 0.00 12/01/23 12/01/23 17/01/23 17/01/23 0.0d CARPENTER
concrete work for column 0.00 17/01/23 17/01/23 25/01/23 25/01/23 0.0d MASON, LABOR
beam and slab steel work 0.00 25/01/23 25/01/23 06/02/23 06/02/23 0.0d STEEL FIXER
beam and slab formwork 0.00 06/02/23 06/02/23 02/03/23 02/03/23 0.0d CARPENTER
beam and slab concrete work 0.00 02/03/23 02/03/23 20/03/23 20/03/23 0.0d MASON, LABOR
school-100.2.1 architectural work 0.00 27/09/22 27/09/22 20/07/23 20/07/23 0.0d
door and window fixing 0.00 27/09/22 27/09/22 10/10/22 10/10/22 0.0d WINDOW AND DOOR FIXER
plaster work 0.00 20/03/23 20/03/23 29/05/23 29/05/23 0.0d LABOR, MASON
flooring work 0.00 29/05/23 29/05/23 14/06/23 14/06/23 0.0d MASON, LABOR
Paint work 0.00 14/06/23 14/06/23 20/07/23 20/07/23 0.0d PAINTER
school-100.4 final commissioning work 0.00 20/07/23 20/07/23 21/07/23 21/07/23 0.0d
last check list 0.00 20/07/23 20/07/23 21/07/23 21/07/23 0.0d
school-100.5 project close out 0.00 21/07/23 21/07/23 21/07/23 21/07/23 0.0d
project finish 0.00 21/07/23 21/07/23 0.0d

Remaining Level of Effort Primary Bas... Page 1 of 5 TASK filter: All Activities
Actual Level of Effort Actual Work © Oracle Corporation
school project upper chitral Baseline vs. Current 21/10/22 14:34

Remaining Level of Effort Primary Bas... Page 2 of 5 TASK filter: All Activities
Actual Level of Effort Actual Work © Oracle Corporation
school project upper chitral Baseline vs. Current 21/10/22 14:35

Remaining Level of Effort Primary Bas... Page 3 of 5 TASK filter: All Activities
Actual Level of Effort Actual Work © Oracle Corporation
school project upper chitral Baseline vs. Current 21/10/22 14:35

Remaining Level of Effort Primary Bas... Page 4 of 5 TASK filter: All Activities
Actual Level of Effort Actual Work © Oracle Corporation
school project upper chitral Baseline vs. Current 21/10/22 14:35

Remaining Level of Effort Primary Bas... Page 5 of 5 TASK filter: All Activities
Actual Level of Effort Actual Work © Oracle Corporation