Category of building: B ...Access area in public and administration building [EBCS-1 Table2.9]
Slab Load
Dead Load
- Own wt. of RC slab = 25KN/m3 x 0.15 = 3.75
- 48mm thick cement screed = 23KN/m3 x 0.048 = 1.104
- 2mm PVC thick floor finish = 16KN/m3 x 0.002 = 0.032
4.886
External wall
- 200mm thick HCB wall = 14KN/m3 x 0.20 x 1= 2.800
- 25mm thick plastering on both side= 23KN/m3 x 0.05 x 1= 1.150
- Wt. of glass = 25KN/m3x0.006x 2.0= 0.300
- Wt. of window including with frame= 0.300 x 1.2 = 0.360
4.310
Internal wall
- 150mm thick HCB wall = 14KN/m3 x 0.15 x 3.52= 7.392
- 25mm thick plastering on both side= 23KN/m3 x 0.05 x 3.52= 4.048
11.440
--------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
NATIONAL CONSULTANTS TEL. 510544 FAX 514933
Project EEPCO District Office Addis Ababa Date
Description Loading By
Chkd
--------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
NATIONAL CONSULTANTS TEL. 510544 FAX 514933
Project EEPCO District Office Addis Ababa Date
Description Loading By
Chkd
H I
--------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
NATIONAL CONSULTANTS TEL. 510544 FAX 514933
Project EEPCO District Office Addis Ababa Date Apr-04
Description Loading By Thomas S.
Chkd
Category of building: B ...Access area in public and administration building [EBCS-1 Table2.9]
Slab Load
Dead Load
- Own wt. of RC slab = 25KN/m3 x 0.15 = 3.75 KN/m2
- 48mm thick cement screed = 23KN/m3 x 0.048 = 1.104 KN/m2
- 2mm PVC thick floor finish = 16KN/m3 x 0.002 = 0.032 KN/m2
4.886 KN/m2
External wall
- 200mm thick HCB wall = 14KN/m3 x 0.20 x 1= 2.800 KN/m
- 25mm thick plastering on both side= 23KN/m3 x 0.05 x 1= 1.150 KN/m
- Wt. of glass = 25KN/m3x0.006x 2.0= 0.300 KN/m
- Wt. of window including with frame= 0.300 x 1.2 = 0.360 KN/m
4.310 KN/m
Internal wall
- 150mm thick HCB wall = 14KN/m3 x 0.15 x 3.52= 7.392 KN/m
- 25mm thick plastering on both side= 23KN/m3 x 0.05 x 3.52= 4.048 KN/m
11.440 KN/m
--------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
NATIONAL CONSULTANTS TEL. 510544 FAX 514933
Project EEPCO District Office Addis Ababa Date Apr-04
Description Loading By Thomas S.
Chkd
H I
--------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
NATIONAL CONSULTANTS TEL. 510544 FAX 514933