Gore-Masha –Tepi Design and Build Road Project Structural monthly report

1. Pipe production
Pipe Produced Consumed Balance
size
previous This To previous This To 691
month date month date
48” 3596 213 3809 3046 73 3119
2. Pipe culvert construction
 Section A1 (from km 0 + 000 to km 20 + 000)
 Pipe culvert work volume on this month

1 From Oct, 26 to Nov,25


2022
Gore-Masha –Tepi Design and Build Road Project Structural monthly report

Pc Station Excavation(m3) Bedding with Masonry(head/wing Stone Pipe Backfill


lean wall construction) pitching(m2) installation(no.) (m3) Pipe culvert
concrete(m3) (m3)
construction
progress
status of sec
A1

Total

 
Masona
Actual beddin ry/
  Type No. Pipe Achievement
Design Station No. of diam Excavt g headwa stone
of of Install Backfill Remark
N Station [On- pipe eter ion L.conc ll pitching
cell Cell ation
o. Site] rete constru
ction this
  previous to date
month
`     1 24 48''             0% 0% 0% Not started
1

2 From Oct, 26 to Nov,25


2022
Gore-Masha –Tepi Design and Build Road Project Structural monthly report

0+426   pc 1 24 48''             0% 0% 0% Not started


2
1+187   pc 1 27 48''             0% 0% 0% Not started
3
1+620   pc 1 25 48''             0% 0% 0% Not started
4
1+862   pc 1 24 48''             0% 0% 0% Not started
5
3+195   pc 1 12 48''             0% 0% 0% Not started
6
3+530   pc 1 12 48''             0% 0% 0% Not started
7
3+763   pc 1 10 48''             0% 0% 0% Not started
8
4+375 4+410 pc 1 23 48''             0% 0% 0% Not started
9
4+642 4+643 pc 1 15 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
10
5+292 5+292 pc 1 15 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
11
6+341 6+350 pc 1 35 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
12
6+940 6+939 pc 1 31 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
13
7+167 7+165 pc 1 14 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
14
7+256 7255 pc 1 14 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
15
7+365 7+365 pc 1 26 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
16
7+820 7+820 pc 1 20 48''             0% 0% 0% Not started
17
8+340 8+329 pc 1 32 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
18
8+470 8+468 pc 2 41 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
19

3 From Oct, 26 to Nov,25


2022
Gore-Masha –Tepi Design and Build Road Project Structural monthly report

8+751 8+748 pc 1 15 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
20
9+271 9+271 pc 1 25 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
21
9+432 9+431 pc 1 17 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
22
9+769 9+787 pc 1 49 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
23
10+016 10+016 pc 1 16 48'' 50% 50% 50% 50% 50% 75% 54% 0% 54% On progress
24
10+258     1 15               0% 0% 0% Not started
25
10+683 10+683 pc 1 28 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
26
11+038 11+032 pc 1 36 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
27
11+752     1 23               0% 0% 0% Not started
28
12+139 12+138 pc 1 16 48''             0% 0% 0% Not started
29
12+222 12+222 pc 1 17 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
30
12+598 12+582 pc 1 25 48'' 50% 50% 50% 50% 50%   8% 33% 42% On progress
31
13+668 13+668 pc 1 14 48'' 100% 100% 100% 100% 100%   83% 0% 83% On progress
32
15+453 15+451 pc 1 17 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
33
15+854 15+854 pc 1 40 48'' 50% 50% 50% 50% 50% 50% 50% 0% 50% On progress
34
16+759 16+764 pc 2 59 48''             0% 0% 0% Not started
35
17+058     1 14               0% 0% 0% Not started
36
17+551 17+551 pc 1 18 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
37

4 From Oct, 26 to Nov,25


2022
Gore-Masha –Tepi Design and Build Road Project Structural monthly report

17+880 17+880 pc 1 33 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
38
18+164 18+163 pc 1 20 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
39
18+620 18+592 pc 1 18 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
40

Pipe culvert construction summary on sec A1


Number of pipe culverts not started 15
Number of pipe culverts on progress 4
Number of pipe culverts completed 22
Total Number of pipe culverts on section A1 41
 Pipe culvert construction achievements on sec A1
previous This month To date
59.25% 0.% 59.25%

5 From Oct, 26 to Nov,25


2022
Gore-Masha –Tepi Design and Build Road Project Structural monthly report

 Section A2 (from km 20 + 000 to km 39 + 500)


Pipe culvert work volume on this month

Pc Station Excavation(m3) Bedding with Masonry(head/wing Stone Pipe Backfill


lean wall construction) pitching(m2) installation(no.) (m3)
concrete(m3) (m3)

Total

Pipe culvert construction progress status of sec A2


  Maso
  No. beddi nary/ Achievement
Design Actual Type No. dia Pipe
of Excavt ng head stone Backf
No. concept Station of of mete Installa Remark
Cel ion L.con wall pitching ill
Station [On-Site] cell pipe r tion previo this
  l crete constr to date
uction us month
21+562 Ext. pipe pc 2 19 48             0% 0% 0% Not started
41
21+854 21+842 pc 1 20 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
42
23+157 23+152 pc 1 18 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
43

6 From Oct, 26 to Nov,25


2022
Gore-Masha –Tepi Design and Build Road Project Structural monthly report

23+531 23+530 pc 1 20 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
44
24+384 24+383 pc 1 17 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
45
24+566 24+565 pc 1 16 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
46
25+206     1 21               0% 0% 0% Not started
47
25+625     1 20               0% 0% 0% Not started
48
26+289     1 20               0% 0% 0% Not started
49
27+387     1 23               0% 0% 0% Not started
50
28+029 28+030 pc 2 22 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
51
28+725 28+724 pc 1 37 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
52
29+263 29+267 pc 1 30 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
53
29+848 29+848 pc 1 23 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
54
30+484
100% 100%
55 30+485 Extend pc 1 11 48'' 100% 100% 100% 100% 100% 0% 100% Completed

30+931 30+931 pc 1 25 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
56
31+339                       0% 0% 0% Omited
57
31+841 31+841 pc 1 50 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
58
32+393 32+392 pc 1 25 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
59
32+722 32+713 pc 1 57 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
60
61 33+231 Aban exi                     0% 0% 0% Omited

7 From Oct, 26 to Nov,25


2022
Gore-Masha –Tepi Design and Build Road Project Structural monthly report

pipe

33+864 33+844 pc 1 23 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
62
34+584 34+584 pc 1 27 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
63
Aban exi
   
64 35+521 pipe                 0% 0% 0% Omited

35+735 35+735 pc 1 56 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
65
36+122 36+123 pc 1 39 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
66
36+516 36+515 pc 1 21 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
67
36+717 36+737 pc 1 18 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
68
37+124 37+123 pc 1 19 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
69
37+295 37+308 pc 1 21 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
70
37+677 37+676 pc 1 14 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
71
37+902 37+902 pc 1 18 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
72
38+487 38+579 pc 1 18 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
73

Pipe culvert construction summary on sec A2

Number of pipe culverts not started 5


Number of pipe culverts on progress 0
Number of pipe culverts completed 25
8 From Oct, 26 to Nov,25
2022
Gore-Masha –Tepi Design and Build Road Project Structural monthly report

Total Number of pipe culverts on section A2 30


Pipe culvert construction achievements on sec A2

previous This month To date


83.33% 0.00% 83.33%

Section B1 ( from km 39 + 500 to km 53+ 200)


Pipe culvert work volume on this month

Pc Station Excavation(m3) Bedding with Masonry(head/wing Stone Pipe Backfill


lean wall construction) pitching(m2) installation(no.) (m3)
concrete(m3) (m3)
44+772 102

total 102

Pipe culvert construction progress status of sec B1


  Design Actual Type No. No. beddin Masona Pipe
diam Excav stone
  concept Station of of of g ry/ Installa Backfill Achievement Remark
eter tion pitching
No. Station [On- cell Cell pipe L.conc headwa tion

9 From Oct, 26 to Nov,25


2022
Gore-Masha –Tepi Design and Build Road Project Structural monthly report

previou this
  to date
Site] rete ll s month
constru
40+092 40+092 pc 1 21 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
74
40+370 40+370 pc 1 28 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
75
40+829 40+831 pc 1 27 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
76
42+576 42+576 pc 1 19 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
77
43+046 43+058 pc 1 33 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
78
43+600 43+621 pc 1 26 48''             0% 0% 0% Not started
79
44+229 44+230 pc 1 19 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
80
44+606(E
100% 100%
81 44+610 xtend) pc 2 27 48'' 100% 100% 100% 100% 100% 0% 100% Completed

44+765 44+772 pc 1 40 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
82
45+150 45+151 pc 1 15 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
83
45+523 45+476 pc 1 21 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
84
45+882 45+871 pc 1 22 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
85
46+210 46+150 pc 1 18 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
86
46+480 46+476 pc 1 20 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
87
47+260 47+097 pc 1 17 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
88
47+456 47+452 pc 1 20 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
89
90 48+614 48+624 pc 1 17 48" 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed

10 From Oct, 26 to Nov,25


2022
Gore-Masha –Tepi Design and Build Road Project Structural monthly report

49+855 49+884 pc 1 19 48" 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
91
50+352 50+357 pc 1 24 48" 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
92
50+913 50+912 PC 1 26 48" 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
93
52+583 52+582 pc 1 16 48" 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
94

Pipe culvert construction summary on sec B1

Number of pipe culverts not started 1


Number of pipe culverts on progress 0
Number of pipe culverts completed 20
Total Number of pipe culverts on section B1 21
Pipe culvert construction achievements on sec B1

previous This month To date


95.24% 0.00% 95.24%

 Section B2 (from km 53 + 200 to km 70 + 000)


11 From Oct, 26 to Nov,25
2022
Gore-Masha –Tepi Design and Build Road Project Structural monthly report

Pipe culvert work volume on this month

Pc Station Excavation(m3) Bedding with Masonry(head/wing Stone Pipe Backfill


lean wall construction) pitching(m2) installation(no.) (m3)
concrete(m3) (m3)

Pipe culvert
construction
progress
Total
status of sec
B2

NO. Masona
Ty beddin ry/
Design Actual No NO. dia Pipe Achievement
  pe Excav g headwa stone
concept Station Cel of met Installa Backfill Remark
  of tion L.conc ll pitching
Station [On-Site] l pipe er tion
cell rete constru this
  ction previous to date
month
`     1 18               0% 0% 0% Not started
95
53+631     1 30               0% 0% 0% Not started
96
53+965     1 27               0% 0% 0% Not started
97
54+250     1 28               0% 0% 0% Not started
98
54+612     1 25               0% 0% 0% Not started
99
100 55+194     1 32               0% 0% 0% Not started
12 From Oct, 26 to Nov,25
2022
Gore-Masha –Tepi Design and Build Road Project Structural monthly report

55+735     1 27               0% 0% 0% Not started


101
55+980     1 27               0% 0% 0% Not started
102
56+556     1 28               0% 0% 0% Not started
103
57+575     1 27               0% 0% 0% Not started
104
58+078     1 31               0% 0% 0% Not started
105
58+413 58+413 pc 1 19 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
106
58+736 58+736 pc 1 28 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
107
59+230 59+232 pc 2 37 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
108
59+562 59+564 pc 1 24 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
109
59+958 59+956 pc 1 24 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
110
60+495 60+491 pc 1 37 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
111
Aban exi
   
112 60+754 pipe                 0% 0% 0% Omited

60+902 60+902 pc 1 17 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
113
61+243 61+241 pc 1 41 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
114
61+423 61+427 pc 1 14 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
115
61+746 61+742 pc 1 15 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
116
61+961 61+962 pc 1 17 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
117

13 From Oct, 26 to Nov,25


2022
Gore-Masha –Tepi Design and Build Road Project Structural monthly report

62+339 62+343 pc 1 20 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
118
62+833 62+832 pc 1 29 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
119
63+183 63+187 pc 1 14 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
120
63+440 63+440 pc 1 16 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
121
63+526 63+526 pc 1 15 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
122
Aban exi
   
123 64+449 pipe                 0% 0% 0% Omited

64+619 64+600 pc 2 36 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
124
64+845 64+818 pc 1 21 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
125
65+029 65+029 pc 1 34 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
126
65+229 65+229 pc 1 27 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
127
65+429 65+431 pc 1 46 48'' 50% 50% 50% 50% 50%   42% 0% 42% On progress
128
65+545 65+547 pc 1 21 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
129
66+516 66+516 pc 1 15 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
130
67+085 67+123 pc 2 42 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
131
68+215 68+213 pc 1 28 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
132
68+599 68+608 pc 1 72 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
133
69+062 69+062 pc 1 28 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
134
69+208 69+209 pc 1                 0% 0% 0% Omited
135

14 From Oct, 26 to Nov,25


2022
Gore-Masha –Tepi Design and Build Road Project Structural monthly report

69+376 69+371 pc 1 13 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
136
69+585 69+574 pc 1 27 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
137

Pipe culvert construction summary on sec B2

Number of pipe culverts not started 11


Number of pipe culverts on progress 1
Number of pipe culverts completed 28
Total Number of pipe culverts on section B1 42
Pipe culvert construction achievements on sec B1

previous This month To date


71.% 0.00% 71.%

 Section C (from km 70 + 000 to km 100 + 000)


Pipe culvert work volume on this month

15 From Oct, 26 to Nov,25


2022
Gore-Masha –Tepi Design and Build Road Project Structural monthly report

Pc Station Excavation(m3) Bedding with Masonry(head/wing Stone Pipe Backfill


lean wall construction) pitching(m2) installation(no.) (m3)
concrete(m3) (m3)
76+750 86
77+964 190
87+487 156 1.6 4 3 26 120
88+402 122 1.8 4 3 10 102
89+071 142 1.4 4 3 9 96
89+457 88
Total 508 4.8 12 9 45 504

NO. Mason
beddi ary/
Design Actual Type NO. stone Pipe Achievement
  No diame Exca ng headw Back
concept Station of of pitchin Installati Remark
  Cell ter vtion L.con all fill
Station [On-Site] cell pipe g on
crete constr this
  uction previous to date
month
70+215     1 13               0% 0% 0% Not started
139
70+433     1 31               0% 0% 0% Not started
140
70+578     1 19               0% 0% 0% Not started
141
70+714     1 24               0% 0% 0% Not started
142
70+978     1 20               0% 0% 0% Not started
143
71+636 71+636 pc 1 24 48''             0% 0% 0% Not started
144
71+998 71+998 pc 1 15 48''             0% 0% 0% Not started
145

16 From Oct, 26 to Nov,25


2022
Gore-Masha –Tepi Design and Build Road Project Structural monthly report

72+459 72+459 pc 1 22   100% 100% 100% 100% 100% 70% 95% 0% 95% On progress
146
72+772 72+772 pc 1 44 48'' 100% 100% 100% 100% 100% 50% 92% 0% 92% On progress
147
73+232 73+232 pc 1 17 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
148
73+696 73+694 pc 1 30 48 50% 50% 50% 50% 50% 25% 46% 0% 46% On progress
149
73+882 73+882 pc 1 41 48 50% 50% 50% 50% 50%   42% 0% 42% On progress
150
74+807 74+806 pc 2 31 48 50% 50% 50% 50% 50%   42% 0% 42% On progress
151
75+393 75+394 pc 1 29 48 50% 50% 50% 50% 50%   42% 0% 42% On progress
152
76+424 76+426 pc 1 20 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
153
76+750 76+750 pc 1 34 48'' 100% 100% 100% 100% 100% 100% 75% 25% 100% Completed
154
77+519 77+519 pc 1 35 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
155
77+963 77+964 pc 2 36 48'' 100% 100% 100% 100% 100% 100% 88% 13% 100% Completed
156
78+263 78+263 pc 1 23 48'' 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
157
78+836 extend pc 1 7 48''             0% 0% 0% Not started
158
79+700     1 12               0% 0% 0% Not started
159
80+111 80+111 pc 1 23 48''             0% 0% 0% Not started
160
80+601 80+601 pc 1 18               0% 0% 0% Not started
161
80+810     1 14               0% 0% 0% Not started
162
80+937     1 14               0% 0% 0% Not started
163
164 81+477 81+460 pc 2 14 48'' 100%           17% 0% 17% On progress

17 From Oct, 26 to Nov,25


2022
Gore-Masha –Tepi Design and Build Road Project Structural monthly report

82+275 82+275 pc 1 16 48''             0% 0% 0% Not started


165
82+445 82+442 pc 1 44 48'' 100%           17% 0% 17% On progress
166
82+624 82+623 pc 1 20 48'' 100%           17% 0% 17% On progress
167
83+175     1 12               0% 0% 0% Not started
168
83+686     1 49               0% 0% 0% Not started
169
83+829     1 21               0% 0% 0% Not started
170
84+495 84+650 pc 1 19               0% 0% 0% Not started
171
85+154     1 56               0% 0% 0% Not started
172
85+339 85+339 pc 1 49   100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
132
85+983 86+170 pc 1 21   100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
174
87+487 87+489 pc 2 37   50% 50% 50% 50% 50% 50% 0% 50% 50% On progress
175
87+744 87+744 pc 1 16   100% 100% 100% 50% 50% 50% 75% 0% 75% On progress
176
88+402 88+402 pc 1 17   50% 50% 50% 50% 50% 50% 0% 50% 50% On progress
177
88+519 88+518 pc 1 20 48 100% 100% 100% 100% 100% 100% 100% 0% 100% Completed
178
89+071 89+071 pc 1 25   50% 50% 50% 50% 50% 50% 0% 50% 50% On progress
179
89+284     1 22               0% 0% 0% Not started
180
89+454 89+457 pc 1 29   50%           0% 8% 8% On progress
181
182 89+733 89+739 pc 3 25               0% 0% 0% Not started

18 From Oct, 26 to Nov,25


2022
Gore-Masha –Tepi Design and Build Road Project Structural monthly report

90+138     1 16               0% 0% 0% Not started


183
90+902     1 23               0% 0% 0% Not started
184
92+240     1 24               0% 0% 0% Not started
185
92+325     2 28               0% 0% 0% Not started
186
94+208 94+210 pc 3 31               0% 0% 0% Not started
187
94+665 94+667 pc 1 42 48             0% 0% 0% Not started
188
94+907     3 25               0% 0% 0% Not started
189
95+221     1 28               0% 0% 0% Not started
190
95+582 95+586 pc 2 43 48             0% 0% 0% Not started
191
95+824 95+842 pc 2 30               0% 0% 0% Not started
192
96+042 96+042 pc 2 43 48             0% 0% 0% Not started
193
96+660 96+659 pc 1 27 48             0% 0% 0% Not started
194
97+187 97+187 pc 3 47 48             0% 0% 0% Not started
195
97+298 97+298 pc 1 17 48             0% 0% 0% Not started
196
97+467 97+470 pc 1 22 48             0% 0% 0% Not started
197
97+676 97+677 pc 1 62 48             0% 0% 0% Not started
198
97+983     1 16               0% 0% 0% Not started
199
200 98+194     1 23               0% 0% 0% Not started

19 From Oct, 26 to Nov,25


2022
Gore-Masha –Tepi Design and Build Road Project Structural monthly report

98+745     1 15               0% 0% 0% Not started


201
98+883     1 17               0% 0% 0% Not started
202
99+017     1 17               0% 0% 0% Not started
203
99+169     1 17               0% 0% 0% Not started
204
99+485     1 12               0% 0% 0% Not started
205

Pipe culvert construction summary on sec C

Number of pipe culverts not started 44


Number of pipe culverts on progress 14
Number of pipe culverts completed 9
Total Number of pipe culverts on section B1 67
Pipe culvert construction achievements on sec C

previous This month To date


20.07% 2.92% 23.0%

20 From Oct, 26 to Nov,25


2022
Gore-Masha –Tepi Design and Build Road Project Structural monthly report

Section D1 (from km 100 + 000 to km 120 + 000)


 There is no any minor and major structural activity on section D1

NO.
Masonar
  Actual beddin Achievement
Design Type NO. y/ stone Pipe
Station No diamet Excavti g Backf
concept of of headwall pitchin Installati Remark
  [On- Cell er on L.conc ill
Station cell pipe construc g on
Site] rete
tion this
previou to
  mont
s date
h
100+670     3 38               0% 0% 0% Not started
204
101+115     2 16               0% 0% 0% Not started
205
102+609     1 19               0% 0% 0% Not started
206
103+904     2 26               0% 0% 0% Not started
207
104+770     1 14               0% 0% 0% Not started
208
106+443     1 31               0% 0% 0% Not started
209
106+590     1 14               0% 0% 0% Not started
210
108+057     1 24               0% 0% 0% Not started
211
108+572     1 27               0% 0% 0% Not started
212
108+735     1 19               0% 0% 0% Not started
213

21 From Oct, 26 to Nov,25


2022
Gore-Masha –Tepi Design and Build Road Project Structural monthly report

108+859     1 22               0% 0% 0% Not started


214
109+024     1 17               0% 0% 0% Not started
215
109+132     2 17               0% 0% 0% Not started
216
109+307     1 19               0% 0% 0% Not started
217
109+657     1 29               0% 0% 0% Not started
218
109+815     2 27               0% 0% 0% Not started
219
109+930     1 17               0% 0% 0% Not started
220
110+274     1 18               0% 0% 0% Not started
221
110+755     1 14               0% 0% 0% Not started
222
111+091     1 26               0% 0% 0% Not started
223
111+249     3 20               0% 0% 0% Not started
224
111+356     1 27               0% 0% 0% Not started
225
111+566     2 18               0% 0% 0% Not started
226
111+690     1 17               0% 0% 0% Not started
227
111+916     1 16               0% 0% 0% Not started
228
112+224     1 24               0% 0% 0% Not started
229
112+350     1 21               0% 0% 0% Not started
230
112+805     2 21               0% 0% 0% Not started
231

22 From Oct, 26 to Nov,25


2022
Gore-Masha –Tepi Design and Build Road Project Structural monthly report

112+942     1 16               0% 0% 0% Not started


232
113+080     1 15               0% 0% 0% Not started
233
113+220     1 15               0% 0% 0% Not started
234
113+339     1 14               0% 0% 0% Not started
235
113+480     1 23               0% 0% 0% Not started
236
113+642     1 15               0% 0% 0% Not started
237
113+932     1 14               0% 0% 0% Not started
238
114+405     1 14               0% 0% 0% Not started
239
114+550     1 44               0% 0% 0% Not started
240
114+714     1 52               0% 0% 0% Not started
241
114+989     1 52               0% 0% 0% Not started
242

115+276     1 12               0% 0% 0% Not started


243
244 117+361     1 12               0% 0% 0% Not started

118+239     1 14               0% 0% 0% Not started


245
246 119+233     3 30               0% 0% 0% Not started

119+656     1 24               0% 0% 0% Not started


247
   

       
 

23 From Oct, 26 to Nov,25


2022
Gore-Masha –Tepi Design and Build Road Project Structural monthly report

       
 
       
 
   

SECTION D2Pipe culvert construction status (from KM,120+000 to 141+000)


NO.
Masona
Ty
Actual ry/
  Design pe No bedding Pipe Achievement
Station NO. of diamet Excavt headwa stone Back
concept of Cel L.concr Installat Remark
[On- pipe er ion ll pitching fill
  Station cel l ete ion
Site] constru
l
ction previou this to
 
s month date
248
121+542       13               0% 0% 0% Not started
249    
124+927       39           0% 0% 0% Not started
250    
127+070       19           0% 0% 0% Not started
251    
127+494       22           0% 0% 0% Not started
252    
130+861       23           0% 0% 0% Not started
253    
132+064       23           0% 0% 0% Not started
254    
132+895       19           0% 0% 0% Not started
255    
133+515       19           0% 0% 0% Not started
256    
134+108       20           0% 0% 0% Not started
257    
134+623       22           0% 0% 0% Not started

24 From Oct, 26 to Nov,25


2022
Gore-Masha –Tepi Design and Build Road Project Structural monthly report

258
134+968       24               0% 0% 0% Not started
259        
135+511   20           0% 0% 0% Not started
260          
136+008   32         0% 0% 0% Not started
261 136+362            
34         0% 0% 0% Not started
262          
136+690   30         0% 0% 0% Not started
263          
137+515   23         0% 0% 0% Not started
264          
137+829   26         0% 0% 0% Not started
265    
139+224       25           0% 0% 0% Not started

Section D2 (from km 120 + 000 to km 141 + 000)

25 From Oct, 26 to Nov,25


2022
Gore-Masha –Tepi Design and Build Road Project Structural monthly report

 There is no any minor and major structural activity on section D2

Total pipe culvert construction summary from sec A1 to sec. D2 (Km 0+000 to 141+000)
Description Quantity(No.)
No. of pipe culvert Not started 137
No. of pipe culvert On progress 19
No. of pipe culvert Completed 104
Total no. of pipe culvert from KM 0+00 to 141+000 260
Total no. of pipes Installed from KM 0+00 to 141+000 3119
Total no. of pipes Installed (including backfill) from KM 0+00 to 141+000 2998
Pipe culvert construction achievements from sec. A1 to sec. D2 (Km 0+000 to 141+000)

previous This month To date


47.03% 0.38% 47.41%

26 From Oct, 26 to Nov,25


2022
Gore-Masha –Tepi Design and Build Road Project Structural monthly report

3. Box culvert construction progress status ( Km 0+000 to


141+000)
BC Excavation(m3) Bedding with Rebar (Kg) Formwork Concrete (m3) Backfill
Station lean (M2) (m3)
concrete(m3)
77+283 93.11
85+551 94.4 4 1076 80 14.543
85+933 100.06 7
Total 194.46 11 1076 80 14.54 93.11

Rebar
Excavtion Concrete work Backfill Achievement
Actual arrangement
Span;
Design Station Type
Sec Heigh Remark
Station [On- of cell thi
t pre this pre this this this
Site] to s to previ to previ to previ to
viou mo viou mont mo mo
date mo date ous date ous date os date
s nth s h nth nth
nth

27 From Oct, 26 to Nov,25


2022
Gore-Masha –Tepi Design and Build Road Project Structural monthly report

13+133 0% 0% 0% Not started


67.5
A1 BC New 2.5:2. 75 75 0%
14+047 14+048 67.5% % On progrss
15+855 0% 0% 0% Not started
% 100
A2 BC Rep 2.5:2.5 100 100 100 100 100 100 100 100
38+783 38+780 100% % Cmpleted
12.5
SC new 2.5:2.5 0%
49+221 49+221 12.5% % On progress
B1
100
BC new 2.5:2.5 100 100 100 100 100 100 0%
52+092 52+092 100 100 100% % Cmpleted
54+776 BC Rep 2.5:2 0% 0% 0% Not started
B2 56+882 BC Exte 3.5:2.3 0% 0% 0% Not started
63+349 63+349 BC Ex 2.5:2.5 0% 0% 0% On progress
77+281 77+281 BC Ex 2.5:2. 0% 0% 0% copleted
85+364 885+551 BC 0% 0% 0% ON progress

85+746 85+933 BC Ex 2.5:2. 0% 0% 0% On progrsss


89+066 0% 0% 0% Not started
89+169 0% 0% 0% Not started

92+325 0% 0% 0% Not started


C 93+139 0% 0% 0% Not started

93+831 0% 0% 0% Not started


94+208 0% 0% 0% Not started
94+906 0% 0% 0% Not started

95+824 0% 0% 0% Not started


96+560 0% 0% 0% Not started
97+187 0% 0% 0% Not started
100+670 0% 0% 0% Not started
D1 101+421 0% 0% 0% Not started
101+580 0% 0% 0% Not started

28 From Oct, 26 to Nov,25


2022
Gore-Masha –Tepi Design and Build Road Project Structural monthly report

101+678 0% 0% 0% Not started


101+883 0% 0% 0% Not started
102+796 0% 0% 0% Not started
103+453 0% 0% 0% Not started
104+770 0% 0% 0% Not started
107+070 0% 0% 0% Not started
111+249 0% 0% 0% Not started
114+066 0% 0% 0% Not started
119+233 0% 0% 0% Not started
120+513 0% 0% 0% Not started
122+303 0% 0% 0% Not started
D2
123+872 0% 0% 0% Not started
138+309 0% 0% 0% Not started

29 From Oct, 26 to Nov,25


2022
Gore-Masha –Tepi Design and Build Road Project Structural monthly report

Box culvert construction summary on from km 0+000 to 141 + 000

Number of box culverts not started 20


Number of box culverts on progress 5
Number of box culverts completed 3
Total Number of box culverts from sec A1 to D2 28

Box culvert construction achievements from sec. A1 to D2

previous This month To date


13.83% 0.78% 14.62%

30 From Oct, 26 to Nov,25


2022
Gore-Masha –Tepi Design and Build Road Project Structural monthly report

31 From Oct, 26 to Nov,25


2022