TIME FRAME PEKERJAAN REPAIRE UNIT SITE DONDANG

No Code Unit Problem Deskription Pekerjaan Estimasi Pekerjaan Manpower PIC Remark
Breakdown Major-Pit 5
1 DT23026 Overhoul Engine & Completed Unit - Overhoul Engine 12 Days
- Rajab
- Completed Engine 2 Days 3
- Budi
- Completed Unit 7 days
- Yudi

2 DT23019 Vessel Damage - Repaire Vessel 7 Days untuk vessel sudah selesai pengerjaan,
- Rahmanto
- Completed Unit 2 Days 2 tinggal proses kompleted unit
- Wahyudi
3 DT23012 Overhoul Engine & Completed Unit - Overhoul Engine 12 Days
- Yudi
- Completed Engine 2 Days
3 - Misran
- Completed Unit 2 days
- Rama
4 DT23028 Overhoul Engine & Completed Unit - Overhoul Engine 12 Days Saat ini engine sudah terpasang, proses
- Rajab
- Completed Engine 2 Days lanjut completed engine & unit
3 - Yudi
- Completed Unit 2 days
- Rifai
5 DT23011 Repaire Seal Cylinder - Remove Cylinder 2 Days
- Yudi
- Reseal Cylinder 2 Days
3 - Misran
- Instal Cylinder 2 days
- Rama
6 EX30001 Engine Problem -Troubelshooting Engine 10 Days Trobleshooting Engine selesai, continue
- Trouble Shooting Hydraulic 4 Days pengecekan Hydraulic & final check
3 - Vendor
-Final Check Unit 2 days

7 EX90001 Hydraulic nternal Leaking - Trouble Shooting Hydraulic 2 Days Saat ini progress resel hydraulic componen,
- Recommendasi Part 2 Days lanjut instalasi ke unit & final check
- Reseal Hydraulic Control Valve 14 days
3 - Vendor
- Instalasi part 3 Days
- Final Check 2 Days