In Phase One, we are going to use one hundred thousand pesos (P100,000) of our budget for planning

and supervision of the space. In Phase Two, we will use ten million pesos (P10,000,000) for the
constructions including the labors and materials needed. In Phase Three, in implementing of building
designs and auditing we will use three million pesos (P3,000,000) of the budget. We intend to buy
cheap but good quality materials from trusted company that sells constructions materials here in the
Philippines.

DESCRIPTION OF WORK START AND END DATES BUDGET


PHASE ONE Planning and supervision 1st week of January-3rd 100K
of the space week of March, 2022
PHASE TWO Construction 4th week of March-1st 10M
week of November,
2022
PHASE THREE Implementation of 1st week of November- 3M
building designs and 4th week of
auditing December,2022
Total: ₱ 13,100,000