You are on page 1of 2

Date of Systra Dates for

Drawing Requirement List Requirement submission


S.No. Structure Name Drawing Name
1 SECOND FLOOR LEVEL SECTIONS 15th April'23 Received
2 SECOND FLOOR BEAM REINFORCEMENT DETAILS 15th April'23 Received Submitted Final Design to
GMRC on 16 March'23
3 SECOND FLOOR SLAB REINFORCEMENT DETAILS 15th April'23 Received
4 THIRD FLOOR LEVEL FRAMING PLAN 30th April'2023 Advance
5 THIRD FLOOR LEVEL SECTIONS 30th April'2023 Advance
by 25 March'23
6 THIRD FLOOR BEAM REINFORCEMENT DETAILS 30th April'2023 Advance
7 THIRD FLOOR SLAB REINFORCEMENT DETAILS 30th April'2023 Advance
8 TERRACE LEVEL FRAMING PLAN 30th April'2023 Advance
Metro Bhawan
9 TERRACE FLOOR LEVEL SECTIONS 30th April'2023 Advance
by 30 March'23
10 TERRACE FLOOR BEAM REINFORCEMENT DETAILS 30th April'2023 Advance
11 TERRACE FLOOR SLAB REINFORCEMENT DETAILS 30th April'2023 Advance
12 MUMTY LEVEL FRAMING PLAN & SECTIONS 30th April'2023 Advance
13 MUMTY BEAM REINFORCEMENT DETAILS 30th April'2023 Advance by 31 March'23
14 MUMTY SLAB REINFORCEMENT DETAILS 30th April'2023 Advance
15 RAMP & PULPIT DETAILS & SECTIONS 31st March'2023 Received Submitted GFC to GMRC
on 28 Nov'22
16 SECOND FLOOR LEVEL SECTIONS 15th April'23
17 SECOND FLOOR BEAM REINFORCEMENT DETAILS 15th April'23 by 30 March'23
18 SECOND FLOOR SLAB REINFORCEMENT DETAILS 15th April'23
19 TERRACE LEVEL FRAMING PLAN 30th April'2023
20 TERRACE FLOOR LEVEL SECTIONS 30th April'2023
Work Shop cum by 31 March'23
21 TERRACE FLOOR BEAM REINFORCEMENT DETAILS 30th April'2023
Administrative
22 Building TERRACE FLOOR SLAB REINFORCEMENT DETAILS 30th April'2023
23 MUMTY LEVEL FRAMING PLAN & SECTIONS 30th April'2023
24 MUMTY BEAM REINFORCEMENT DETAILS 30th April'2023 by 12 April '23
25 MUMTY SLAB REINFORCEMENT DETAILS 30th April'2023
26 STAIRCASE PLAN & SECTIONS (SH. 01 OF 02) 31st March'2023 Received
by 6 March'23
27 STAIRCASE REINFORCEMENT DETAILS 31st March'2023 Received
28 PLINTH LEVEL FRAMING PLAN & SECTION DETAILS 15th April'23 Received
29 PLATFORM LEVEL FRAMING PLAN & SECTION DETAILS 15th April'23 Received
30 Heavy Cleaning Plant & PLINTH & PLATFORM BEAM REINFORCEMENT DETAILS 15th April'23 Received Submitted GFC to GMRC
Blow Down Plant on 28 Dec '22
31 PLATFORM SLAB REINFORCEMENT DETAIL 15th April'23 Received
32 GRADE SLAB REINFORCEMENT DETAILS & SECTIONS & RAM15th April'23 Received
33 PLATFORM LEVEL FRAMING PLAN (SH. 01 OF 02) 31st March'2023
34 PLATFORM LEVEL FRAMING PLAN (SH. 02 OF 02) 31st March'2023
Covered Stabling by 26 March '23
35 PLATFORM BEAM REINFORCEMENT DETAIL 31st March'2023
36 PLATFORM SLAB REINFORCEMENT DETAIL 31st March'2023
37 PLINTH BEAM REINFORCEMENT DETAILS (SH. 01 OF 02) 15th April'23 Received Submitted GFC to GMRC
38 PLINTH BEAM REINFORCEMENT DETAILS (SH. 02 OF 02) 15th April'23 Received on 21 Feb'23
39 TERRACE BEAM REINFORCEMENT DETAILS (SH. 01 OF 02) 30th April'2023
40 Traction Store TERRACE BEAM REINFORCEMENT DETAILS (SH. 02 OF 02) 30th April'2023 by 24 April'23
41 TERRACE SLAB REINFORCEMENT DETAILS 30th April'2023
42 GRADE SLAB REINFORCEMENT DETAILS & RAMP DETAILS 15th April'23 Received Submitted GFC to GMRC
on 21 Feb'23
43 COLUMN LAYOUT PLAN (SH. 01 OF 02) 31st March'2023
44 COLUMN LAYOUT PLAN (SH. 02 OF 02) 31st March'2023
45 FOUNDATION LAYOUT PLAN (SH. 01 OF 02) 31st March'2023
46 Open Stabling FOUNDATION LAYOUT PLAN (SH. 02 OF 02) 31st March'2023 by 26 March '23
47 COLUMN & FOUNDATION REINFORCEMENT DETAILS 31st March'2023
48 PLATFORM LEVEL FRAMING PLAN & SECTIONS 31st March'2023
49 PLATFORM BEAM & SLAB REINFORCEMENT DETAIL 31st March'2023
50 TERRACE LEVEL FRAMING PLAN & SECTIONS 31st March'2023
51 TERRACE BEAM REINFORCEMENT DETAILS (SH. 01 OF 02) 31st March'2023 by 6 April '23
52 TERRACE BEAM REINFORCEMENT DETAILS (SH. 02 OF 02) 31st March'2023
53 Inspection Office cum MUMTY LEVEL FRAMING PLAN & SECTIONS 31st March'2023
54 Bay MUMTY BEAM & SLAB REINFORCEMENT DETAILS 31st March'2023 by 9 April '23
55 TERRACE FLOOR SLAB REINFORCEMENT DETAILS 31st March'2023
56 RAMP & PULPIT DETAILS & SECTIONS 31st March'2023 Submitted GFC to GMRC
on 9 Dec '22
57 COLUMN REINFORCEMENT DETAILS 15th April'23
58 FOUNDATION REINFORCEMENT DETAILS 15th April'23
59 FOUNDATION REINFORCEMENT DETAILS 15th April'23
60 RCC WALL REINFORCEMENT DETAIL 15th April'23
61 SECTION DETAILS 15th April'23 GMRC/ITD to provide
62 Autocoach Washinng PLINTH & TERRACE LEVEL FRAMING PLAN & SECTIONS 15th April'23 Vendor Inputs on or
Plant & Control Room before 25 March '23
63 PLINTH BEAM REINFORCEMENT DETAILS 15th April'23
64 TERRACE BEAM REINFORCEMENT DETAILS 30th April'23
65 PLINTH SLAB REINFORCEMENT DETAILS 15th April'23
66 TERRACE FLOOR SLAB REINFORCEMENT DETAILS 30th April'23
Autocoach Washinng GMRC/ITD to provide
Plant & Control Room Vendor Inputs on or
before 25 March '23
Date of Systra Dates for
Drawing Requirement List Requirement submission
S.No. Structure Name Drawing Name
67 MISCELLANEOUS DETAILS 15th April'23
68 TERRACE LEVEL FRAMING PLAN & SECTIONS 30th April'2023
69 MUMTY LEVEL FRAMING PLAN & SECTIONS 30th April'2023 by 20 April'23
70 SECTION DETAILS 15th April'23
71 PLINTH BEAM REINFORCEMENT DETAILS 15th April'23 Submitted FD to GMRC
on 21 Dec'22
72 TERRACE BEAM REINFORCEMENT DETAILS 30th April'2023
73 P-way & Traction TERRACE SLAB REINFORCEMENT DETAILS 30th April'2023
by 20 April'23
74 MUMTY BEAM & SLAB REINFORCEMENT DETAILS 30th April'2023
75 TERRACE SLAB REINFORCEMENT DETAILS 30th April'2023
76 GRADE SLAB REINFORCEMENT DETAILS 15th April'23 Submitted FD to GMRC
77 RAMP & STEPS DETAILS & SECTIONS 15th April'23 on 21 Dec'22
78 STAIRCASE PLAN & SECTIONS 15th April'23
by 15 April'23
79 STAIRCASE REINFORCEMENT DETAILS 15th April'23
80 FOUND. & COL. REINFORCEMENT DETAILS 30th April'2023 Submitted GFC to GMRC
RRV Parking
on 20 Feb'23
81 FOUND. & COL. LAYOUT AND PLINTH & ROOF GA PLAN 30th April'2023
82 SECTION DETAILS 30th April'2023
83 FOUND. & COL. REINFORCEMENT DETAILS 30th April'2023
84 Cleaners Room PLINTH & ROOF BEAM AND REINF. DETAILS 30th April'2023 by 19 April'23
85 GRADE & ROOF SLAB REINF. DETAILS 30th April'2023
86 PIT PLAN & SECTIONS & DETAILS 30th April'2023
87 PIT SECTIONS REINF. DETAILS 30th April'2023
88 ROOF SLAB & SECTIONS REINF. DETAILS 31st March'2023 Received
89 ASS/TSS PULPIT ,RAMP & STEPS GA & REINF. DETAILS 31st March'2023 Received Submitted FD to GMRC
on 14 March'23
90 CANOPY & PENTHOUSE DETAILS, SECTIONS & REINFORCEM31st March'2023 Received
91 EXTERNAL MANHOLE RCC DETAILS (VEHICULAR LOAD) 31st March'2023
92 EXTERNAL MANHOLE RCC DETAILS (NON-VEHICULAR LOAD)31st March'2023
93 EXTERNAL CABLE TRENCH & PRECAST COVER RCC DETAILS 31st March'2023
94 EXTERNAL SEWERAGE/EFFLUENT MANHOLE RCC DETAILS 31st March'2023
95 STORM WATER DRAIN RCC DETAILS 31st March'2023
96 STORM WATER DRAIN RCC DETAILS (FOR VEHICULAR LOAD)31st March'2023
97 STORM WATER MANHOLE RCC DETAILS 31st March'2023
98 STORM WATER DESILTING CHAMBER & CATCH BASIN RCC D31st March'2023
99 HARVESTING PIT RCC DETAILS 31st March'2023
External Work by 31 March'23
100 GULLY & GREASE TRAP RCC DETAILS 31st March'2023
101 TYPICAL MULLION & LINTEL BEAM RCC DETAILS (SH. 01 OF 031st March'2023 received
102 TYPICAL MULLION & LINTEL BEAM RCC DETAILS (SH. 01 OF 031st March'2023 received
103 GATE COLUMN, FOOTING GA & REINF.DETAILS 31st March'2023
104 CULVERT DETAILS 1 31st March'2023
105 CULVERT DETAILS 2 31st March'2023
106 ADDITIONAL DETAIL 1 31st March'2023
107 ADDITIONAL DETAIL 2 31st March'2023
108 ADDITIONAL DETAIL 3 31st March'2023
109 ETP/STP FOUNDATION DETAIL IMMEDIATE received BY 28 March'2023
110 DEPOT RAMP RP-11 FOUNDATION DETAIL IMMEDIATE BY 30 March'2023
111 RP-12 FOUNDATION DETAIL IMMEDIATE BY 30 March'2023

Note: Total No. of Drawing = 111 no's


Balance Drawing to be issued = 81 no's
Drawing to be issued by 31.03.2023 = 31 no's
Drawing to be issued by 15.04.2023 = 15 no's
Drawing to be issued by 30.04.2023 = 32 no's
Drawing to be issued immediately = 03 no's