METHOD STATEMENT
1. SCOPE:&
This document describe construction methodology for carrying out Brick Masonry
Works To meet technical requirements, suitable construction methodology has been
adopted in all the works to ensure quality and safety apart from the speedy
construction. A commitment to maintain the highest possible standards has played a
2. REFERENCE DOCUMENT:
Following documents in totality or in part should form the reference documents:
1. Layout for the respective floor for should be marked with thread and checked for
right angles/ dimension and opening.
2. Ensure the Hacking and wire pulling8
4. Before preparing cement sand mortar, cement should be mixed with non-shrinkage
additives.
115mm 1:4
230mm 1:6
6. Joints should be packed with mortar and hollow spaces should not be left.
7. After 1st course of brick work, checklist for layout should be signed off from clients [EHRLI
8. Brick work should be buit up in uniform layers and no portion of a wall should
raise more than 1 metre of level in a day.
. Aoplication of cement mortar between two bricks should be uniform and the
thickness of joints should be neither less than 6mm nor more than 10mm.
10. Brick work should be in plumb, in line and as
per the dimensions shown. Vertical
joints in alternate courses should come directly one over the other and be in line.
12. Curingshould be done at intervals time for [7-days|. Raking is mandatory on post
completion of days.
5. SAFETY PRECAUTION:
to be used.
1.Proper manual handling technique
at height.
2. Proper platform should be used while working
should be used.
3.Proper job specific PPE
while brick shifting.
4.Safe method should be used
must be provided.
5.Proper certified loading platform
7.RECORDS:
work.
1) Checklist for Brick