You are on page 1of 1

Plant Maintenance Work Order

Lab No:
WO NO.
1969300
Priority : P1 < 7 Hari
Reference :
Unit No : EXC101-6 Component: FINAL DRIVE LH Sample Date: 13-May-23
Location : SLK-AKM Lab Received Date: 18-May-23 Date Raise Rekom: 20-May-23

ASSIGMENTS ESTIMATED
Originator : Conmon HO Estimated Duration :
Assigned To : Januar / Widaja Schedule Start Date :
Actioned By : Labour Internal Schedule Completed :
Comp Group :
Work Order Description
Viscosity low Contaminant in above normal PQ Fe above standard. wear Gears Bearings Splines housing Shafts Check oil
level and leakage. Check abnormal noise. Check magnetic plug and debris. Inspect inner part. Repair necessary or flush to
remove particle.Possible dirt. Check seal leaking. Check contaminant source. Check operating temperature. Check oil mix/
transfer. Check oil grade.oil already change. (nugroho)

Fe debris, silica, Al, Iron tinggi


1. Cek adanya kebocoran FD
2. resample oli
3. cek abnormal noise FD
4. cek magnetic plug rating
5. Drain sebagian oli untuk cek kandungan gram kasar, flushing oli bila terdapat gram kasar

Dilengkapi oleh Tradeperson / Supervisor


ACTUAL
Start Date: Completion Date: Current (SMU):
Start Time: Completion Time: Total Actual Duration:

After Maintenance Remarks / Job yang dilakukan & Temuan saat pengecekan-Repair

Delay Reasons

Nama Mekanik:
Mekanik TTD: Date:
Leader/SPV TTD: Date:

You might also like