Completion Tracker290719
Completion Tracker290719
Total summary
1 total documetns 24
2 work completed 11
3 Balance to complete 13
4 critical and not yet started 5
nark riva - Completion certificate tracker
29/07/19 authority for issue.
Files are ready for handover to
liasoning agent. Konark karia builders
Pune municipal corporation
Keshavnagar grampanchayat
JW consultants llp
In house
owc vendor finalised and po to be
issued. OWC vendor
In house
stp material received at site except
blower. Stp supply Vendor.
delayed purcahse DG supply vendor.
In house
Remark
Liasoning agency contacted and he
started his working.
.