You are on page 1of 5

Update Mine Readiness

Engineering Dept. BMSS

February 2023
MINE READINESS 2023

MINE READINESS ALL OPU 2023


120% 101% 102%
96% 98% 100% 101%
88% 93%
100% 84%
77%
80%
59%
60%
40% 33%34%
26%
18%
20% 7% 5% 5% 3% 2% 2% 0% 0% 0%
0%
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Plan Monthly Act Monthly Cumulative Plan Cumulative Act
MINE READINESS 2023
• Actual Cumulative Progress January
Cumulative Progress
Mining Legal/Permit Land Infras % Complete
Actual
MA 19% #N/A #N/A 100% <5
PMSS 25% 40% #N/A #N/A 5 - 25
MAS 35% #N/A 51% #N/A 26 - 50
AGM 26% 80% 32% 23% 51 - 75
BSSR #N/A #N/A #N/A #N/A 76 - 95
BSEE 30% #N/A 25% #N/A > 95

• Gap Plan vs Actual January

Gap Mining Legal/Permit Land Infras % Complete (gap)


MA 4% #N/A #N/A 0% > 10% behind
PMSS 8% 26% #N/A #N/A 5 - 10% behind
MAS 11% #N/A -13% #N/A 1 - 5% behind
AGM -16% 10% -18% 1% On track/Complete
BSSR #N/A #N/A #N/A #N/A
BSEE -17% #N/A -27% #N/A

Notes :
• BSSR progress collect data
HIGHLIGHT ISSUE
OPU Aspect of Readiness Issue Due Date PIC Status

Pembebasan lahan Pit Alam 6 seluas 7.57 Ha 28-Feb-23 Santos Act progress end of Jan 66%
Pembebasan lahan Disposal Timur seluas 15.59
MAS Land 28-Feb-23 Santos Act progress end of Jan 24%
Ha
Pembebasan lahan Disposal Selatan seluas 42.8
28-Feb-23 Santos Act progress end of Jan 15%
Ha

Batubara produk blok 2 smu menumpuk di LBCT Propose market untuk GAR 6700 dari Blok 2
17-Feb-23 Marketing
dan stockpile SKB karena market GAR 6700 segera atau blending maret dengan produk Blok 4
Mining
belum ada/belum terjual. Di Pit sudah terbentuk
pilar coal expose dan mengganggu sequence Membuat alternatif sequence agar produksi tetap
17-Feb-23 Riky, Ismu
AGM continue (percepatan pemompaan)
Pembebasan lahan area disposal OPD Blok 4
28-Feb-23 Dewa Act progress end of Jan 19%
(BAS) seluas 42.65 Ha
Land
Pembebasan lahan area disposal OPD Blok 4
31-Mar-23 Dewa Act progress end of Jan 0%
(HRS) seluas 4.95 Ha (Lahan Sisir)
Zulkipli, - Progress perbaikan operasional SSM
Mining Achievement produksi underplan 31-Mar-23
Haizal - Progress preparasi untuk kontraktor baru
BSEE Pembebasan lahan seluas 7.51 Ha area Pit 28-Feb-23 Gerry Act progress end of Jan 51%
Land
Pembebasan lahan seluas 32.25 Ha area Disposal 28-Feb-23 Gerry Act progress end of Jan 0%