LABOR AND EQUIPMENT PRODUCTION RATES

8 HRS
RESOURCES - LABOR AND EQUIPMENT
Sr. No. ITEM PRODUCTIVITY
Unit Qty LABOR EQUIPMENT

EXCAVATION & EARTHWORKS Operator Helper Labour Mason Shovel Digger Roller Compactor

Excavation for foundation


m3 150 1 1 1
pits in normal ground
1
Excavation for foundations
in strips/trenches in normal m3 130 1 1 1
2 ground
Hand excavation in normal
m3 3 1
ground upto 1.5m lift
3
Foundation bed levelling &
m2 90 2 1
compaction
4
Backfilling in 150mm layers
in buildings below slab on m3 180 2 1 0.75 1
5 grade
Backfilling around building
m3 200 2 1 0.75 1
in 150mm layers
6
DISMANTLING & DISPOSAL (Manual) Labour Concrete Breaker Rapid Breaker

Plain concrete / Block walls m3 5 2 1


1
Hard Rock/ Reinforced
m3 2 2 2
2 concrete
3 Concrete paving m2 100 2 1

4 Asphalt & Subase m2 16 1 1


Pile Head Cutting - 300 mm
5 No 5 1 1
Dia
Pile Head Cutting - 600 mm
6 No 5 2 1
Dia

MISCELLANEOUS Waterproofer Labour Mason

1 Waterproofing Membrane m2

2 Polythene Sheets m2

3 Protection Screed m2

4 Tower Crane Erection No


Shutter Making Carpenter Helper Wood Cutting Machine

1 Columns (Square or Rectangular) m2 14 1 1 1


2 Wall shutter m2 22 1 1 1
3 Beam Bottom m2 14 1 1 1

Marvin Fernandez-CE Page 1 of 2


4 Beam Sides m2 20 1 1 1
5 Stair case /steps m2 8 1 1 1

Marvin Fernandez-CE Page 2 of 2