PART 7 Attachment - HSE Critical Task Allocation
PART 7 Attachment - HSE Critical Task Allocation
Prepare site and area specific emergency response plan Emergency Response Emerg. Resp. Exercise
Project Manager Prepare emergency response plan detailing the external emergency response to an emergency at Plans/Procedures Review by EOFS Head
the rig site which cannot be dealt with by onsite facilities office
Review,approve and audit Security Plan and related Services. EOFS Security Plan Audit Team
Project Manager Ensure the condition of the proposed Security Service is acceptable on behalf of EOFS.
Competency of Project Team CV and Performance Rprts Peer review and end-of-year
Project Manager Ensure all Project Team Members are competent in his role Experience Level performance review
Maintain, inspect and certify BOPs in accordance with PMS Well Control Manuals Rig Manager
Project Manager Inspect BOP in line with standards by authorsied institution. Repair should only make use of HBRS Drilling SOP
approved spares
Emergency response training for Supervisory staff ERP Plan Emerg. Resp. Exercise
Project Manager Ensure that personnel involved in implementing emergency response are adequately trained HSE Induction Training Periodic checks
Conduct formal assessment of all proposed changes Drilling SOP Policy and Audit Team
Project Manager Formal assessment of all changes to procedures and equipment should be conducted by a multi- Procedures
displinary team to address all hazards
Dedicated and certified trucks and drivers for hazardous goods transport HSE Policy / Plan Audit Team
Project Manager Ensure transportation of hazardous goods is carried out by certified trucks and using trained / Road Transport Management
drivers only Plan
Trucks for diesel/OBM transport to carry absorbant material HSE Policy / Plan Audit Team
Project Manager Ensure that trucks transporting diesel/OBM carry adequate quantity of absorbant material (pads / Road Transport Management
and/or bags) to minimise the effect to the environment Plan
Trucks for diesel/OBM transport to carry barrier tape HSE Policy / Plan Audit Team
Project Manager Ensure that trucks transporting diesel/OBM carry adequate quantity of barrier tape to restrict / Road Transport Management
access of people passing by or interfering when spillage occurs Plan
Dedicated buses and drivers HSE Policy / Plan Audit Team
Project Manager Ensure only vehicles approved and drivers trained in defensive driving are used for transportation / Road Transport Management
of crews Plan
Site Access Road Markings HSE Policy / Plan Audit Team
Transportation will be undertaken at night (only by exception) and possibly during periods of poor / Road Transport Management
Project Manager visibility (fog, storm or rain). Therefore the site access road must be marked with luminescent Plan
posts at close intervals that the
RESPONSIBILITY DESCRIPTION INPUT/DOCUMENTATION VERIFICATION
Set up Camp Hospital HSE Policy / Plan Audit Team
Project Manager Ensure camp hospital is provided with adequate facilities to treat potential accidents /Garraf Medical Emergencies
Plan
Competency of Location Manager Contract obligations Periodic assessment by
Project Manager
Location Manager to be competent in his role, including emergency response Experience level EOFS Management staff
Competency of Mud Loggers (provisionally) Sub-contract obligations Periodic assessment by
Project Manager Ensure Mud Loggers are competent in their role, including kick detection, communication, Experience levels EOFS Rig Manager
monitoring of pressures and recording
Competency of Casing Crew (provisionally) Sub-contract obligations Periodic assessment by
Project Manager Ensure Casing Crew are competent in their role, including power unit control, casing/completion Experience levels EOFS Rig Manager
make-up, stabbing etc and safe working practices
Competency of Cementing Crew (provisionally) Sub-contract obligations Periodic assessment by
Project Manager Ensure Cementing Crew are competent in their role, including bulk control, density & pumping rate Experience levels EOFS Rig Manager
control, additives control etc and safe working practices
Doctor availability ER Plan Contract.
Project Manager Ensure that a qualified doctor is available on 24 hrs duty in the Camp and at the well site Emerg. Resp. Exercise
Working Cycle Drilling SOP Policy and Wells Team Leader and IFS
Project Manager Ensure that working cycle for crews and supervisors is appropriate to cope with severe hot Procedures
conditions
Competency of medic HSE Policy / Plan Audit Team
Project Manager Ensure medic is competent to deal with oilfield injuries Contract obligations/ Medical
Emergencies Plan
Train personnel in the application of Medical Emergencies Plan Emergency Response Emerg. Resp. Exercise
DSV Ensure those staff authorised to call for Medivac understand the arrangements Plans with Medivac
Capacity markings on lifting equipment HSE Policy / Plan Checks by HSE Coordinator,
Rig Manager Ensure only lifting equipment marked as certified is used on the site Rigging / Slinging Training HSE Manager, Toolpusher
RESPONSIBILITY DESCRIPTION INPUT/DOCUMENTATION VERIFICATION
Enforce rig site smoking policy HSE Policy / Plan Checks by HSE Coordinator,
Rig Manager Smoking on rig site to be allowed in specified areas only Appropriate signs posted HSE Manager, Toolpusher
Use Unsafe Act Auditing Process HSE Policy / Plan Checks by HSE Manager
Rig Manager Encourage use of Unsafe Act Auditing Process at the rig site and camp and during transportation HSE and Induction Training
Wear Personal Protective Equipment HSE Policy / Plan Checks by HSE Coordinator,
Rig Manager Ensure all staff (also third party) to wear appropriate Personal Protective Equipment for all tasks HSE and Induction Training HSE Manager, Toolpusher
Prevent smoking during transportation HSE Policy / Plan Checks by Safety Coordinator
Rig Manager Enforce no smoking rules during transportation to prevent discarded cigarette being thrown away HSE and Induction Training
in the surrounding area
Fire Extinguisher on crew vehicle(PSD) HSE Policy / Plan Checks by Safety Coordinator
Rig Manager Ensure a fire extinguisher is in place on the bus and is inspected regularly. Ensure driver is aware /Garraf Road Transport
of its operation Management Plan
Weekly review of vehicle condition HSE Policy / Plan Record of daily bus checklist
Rig Manager Review of daily vehicle checklists /Garraf Road Transport
Management Plan
Fire fighting equipment (rig site) HSE Policy / Plan Contract PM/Checks by Mech.
HSE Coordinator Ensure fire-fighting equipment is installed at the rig site and inspected on a regular basis obligations Engineer. Inspection by HSE
Coordinator
Fire fighting equipment (camp site) HSE Policy / Plan Contract PM/Checks by Mech. Eng
Ensure camp is provided with fire fighting equipment which is checked on a regular basis obligations assisted by Campboss.
HSE Coordinator Inspection by HSE
Coordinator
Install and test fire alarm HSE Policy / Plan Daily activity sheet Campboss
HSE Coordinator
Ensure fire alarm is installed at the camp and regularly tested
Maintain Breathing Apparatus HSE Policy / Plan PM/Checks by Mech. Eng
HSE Coordinator Ensure breathing apparatus sets are certified assisted. Inspection by HSE
Coordinator
RESPONSIBILITY DESCRIPTION INPUT/DOCUMENTATION VERIFICATION
Hold HSE Meetings involving all of the crew HSE Policy / Plan/ HSE Alerts Report by Rig Mangr and
HSE Coordinator HSE meetings will be held as a forum for discussion of HSE concerns and to feed back HSE HSE Coordinator
statistics for the operations to the Project Manager
Transportation policy HSE Policy / Plan /Garraf Journey Management record
Implement transportation policy detailing required behaviour of passengers and driver (i.e. Road Transport Management sheets.
HSE Coordinator maximum working hours, speed limit, no alcohol for driver, no talking to driver by passengers Plan Periodic Audits by
except in an emergency, wearing of seatbelts, etc) Project Management
Control of Portable electrical equipment HSE Policy / Plan Induction Checks by Toolpusher
Ensure that signs are posted warning people not to carry portable electrical equipment (including Training
Toolpusher mobile phones and walkie talkies) into Hazardous Areas (as defined by Area Classification) unless Safety Meetings
suitably rated for Warning Signs
Rotary Table centred over well bore Drilling Ops Policy Checks by Rig Manager
Toolpusher Ensure that substructure/mast is centred and level, such that rotary table is centred over well bore Drilling Programme Handover Notes
to minimise casing wear
Install BOPs Well Control Manuals Checks by Rig Manager
Toolpusher Correctly install BOPs and related equipment e.g. degasser, poorboy, choke manifold, remote Drilling SOP Policy
panel
Maintain and Inspect BOPs Well Control Manuals PM/Checks by Rig Manager
Toolpusher
BOPs and related equipment to be inspected on a weekly basis Drilling SOP Policy
Ensure use of portable gas detectors Permit-to-Work System PM/Checks on electrical
Toolpusher Portable gas detection to be used when fixed system is being maintained and/or when area has to equipment
be checked to perform hot work Periodic Audits on PtW
Operate Degassing equipment Well Control Manuals Handover Notes
Toolpusher Ensure degassing equipment is operated while drilling hydrocarbon bearing zones and if gas cut Drilling SOP Policy PM/Checks on Degasser
mud is observed System
Spot checks of Drilling Process Drilling SOP Policy Checks by Toolpusher / Rig
Toolpusher Perform spot checks to confirm accurate interpretation of mud monitoring system data by driller Manager
Cessation of operations during extreme weather Drilling SOP Policy Checks by Rig Manager
Toolpusher Operations to be suspended during extremes of weather if safety of the operation threatened
RESPONSIBILITY DESCRIPTION INPUT/DOCUMENTATION VERIFICATION
Mud checks verification Drilling SOP Policy Checks by Rig Manager
Toolpusher Spot check measurement of mud weight and viscosity periodically during a tour
Prepare Trip Sheet Drilling SOP Policy Checks by Rig Manager
Toolpusher
Trip sheet to be prepared before every trip to manage the tripping
Conduct well control drills Drilling SOP Policy Checks by Rig Manager
Conduct BOP, pit drills and strip drills regularly to measure alertness of driller, mudlogger and crew Standing Instructions
Toolpusher to kicks and to ensure that appropriate responses are made
Install and test crown-o-matic Drilling SOP Policy Checks by Toolpusher & Rig
Toolpusher Ensure crown-o-matic system is installed to guard against pulling travelling blocks into crown block Manager
Safety factor on drill line Drilling SOP Policy Checks by Toolpusher & Rig
Toolpusher Confirm that drill line has safety design factor appropriate for operations, compared to expected Manager
loading
Installation of drill string weight indicator Drilling SOP Policy Checks by Toolpusher & Rig
Toolpusher
Verify installation and calibration of weight indicator for drill Manager
Weight Indicator Redundant System Drilling SOP Policy Checks by Toolpusher & Rig
Toolpusher Ensure that string weight can be verified with redundant (hydraulic-electric) system as provided by Manager
Mud Loggers
Drill line inspection program Drilling SOP Policy Checks by Toolpusher & Rig
Wear of drilling line controlled by ton mile program and drilling line inspection program to Manager
Toolpusher determine realistic goal for cut-off. Inspections performed by Toolpusher or driller and to include
drilling line and anchor points
Inspection of cables and slings HSE Policy / Plan Checks by Safety
Toolpusher Cables and slings condition to be visually inspected weekly Coordinator, Rig Manager,
Toolpusher
RESPONSIBILITY DESCRIPTION INPUT/DOCUMENTATION VERIFICATION
Inspection of mast HSE Policy / Plan Checks by Derrickman and
Toolpusher Mast inspected for loose objects, correct placement of safety pins and chains and potential failure Driller.
during weekly rig inspection Handover Notes.
Competency of crew in lifting operations HSE Policy / Plan Checks by Safety
Toolpusher Toolpusher to observe crew during slinging operations to ensure they are competent Rigging / Slinging Training Coordinator, Rig Manager,
Toolpusher
Issue PtW for Hot Work HSE Policy / Plan Checks by Safety Coordinator
Toolpusher Issuing and performing of Permit to Work for Hot Work Induction and HSE Training and Rig Manager
Issue PtW for Use of Explosives HSE Policy / Plan Checks by Safety
Issue Permit to Work covering logging operations involving explosives E-logging Company Policy and Coordinator, Rig Manager,
Toolpusher Procedures Toolpusher
Induction and HSE Training
Training in use of lifting gear HSE Policy / Plan Checks by Safety
Toolpusher Rig crew members to be trained in correct way to fix slings to loads, as appropriate Rigging / Slinging Training Coordinator, Rig Manager,
Toolpusher
Competency of Driller Contract obligations IADC/IWCF Certificate
Driller to be competent in his role and to hold a well control certificate Experience level Periodic assessment by
Toolpusher Well Control Training Toolpusher and Rig Manager
Close in well using secondary well control Well Control Training and IADC Drilling Report
Driller Actions to maintain well control by closing in the well using BOP’s after detecting inflow Compentency
Stab-in Safety Valve (Kelly Cock) Well Control Manuals Checks by Toolpusher & Rig
Driller Stab-in safety valve to be on the drill floor during tripping to prevent flow up the drill string if the Drilling SOP Policy Manager
well flows
Functional test of crown-o-matic Drilling SOP Policy IADC Drilling Report
Driller
Crown-o-matic system to be given daily functional test
Monitor trip tank during a trip Drilling SOP Policy Checks by Toolpusher & Rig
Mudman Comparison of actual volume required to fill well with calculated volume from trip sheet on a Standing Instructions Manager
continuous basis
Monitor mud system Drilling SOP Policy Checks by Toolpusher & Rig
Mudman Monitoring of the mud properties, system flows and pit levels every 15-30 minutes Standing Instructions Manager
Maintain water tank levels Drilling SOP Policy Checks by Toolpusher & Rig
Mudman Water tank levels to be maintained at set level to ensure sufficient supplies available Standing Instructions Manager
RESPONSIBILITY DESCRIPTION INPUT/DOCUMENTATION VERIFICATION
Confirm trip tank valve alignments Drilling SOP Policy Checks by Toolpusher & Rig
Mudman Confirm that valves between flow line and shakers is shut to prevent loss of fluid to active pits Standing Instructions Manager
Inspect and maintain power package Drilling SOP Policy Mechanical PM/Checks on mech &
Maintain adequate fuel, lub oil and water level to ensure dependability of electrical generation. and Rotating Equipment rotating equipment
Mechanical Engineer Verify that water supply to engine exhaust is functional Recorded on daily activity list
Maintain water transfer system Drilling SOP Policy Mechanical PM/Checks on mech &
Maintain water transfer system in good repair and Rotating Equipment rotating equipment
Mechanical Engineer Recorded on daily activity list
Maintain and inspect trip tank Drilling SOP Policy Mechanical PM/Checks on mech &
Maintain and inspect trip tank equipment, especially prior to each tripping operation and Rotating Equipment rotating equipment
Mechanical Engineer Recorded on daily activity list
Inspect and maintain centrifugal pumps Drilling SOP Policy Mechanical PM/Checks on mech &
Inspect and maintain mud system pumps (mud pumps, trip tank pump and mud mixing pumps) and Rotating Equipment rotating equipment
Mechanical Engineer Recorded on daily activity list
Calibrate pressure gauges Drilling SOP Policy Mechanical PM/Checks on mech &
Regular calibration of pressure gauges to ensure annular and drill pipe pressures is accurately and Rotating Equipment rotating equipment
Mechanical Engineer known during drilling operations Recorded on daily activity list
Inspect and maintain accumulator Well Control Manuals PM/Checks on mech &
Accumulator to be inspected and maintained on a regular basis GWDC Policy Mechanical and rotating equipment
Rotating Equipment Checks by Toolpusher & Rig
Mechanical Engineer Manager
Recorded on daily activity list
Calibration of crane load indicator Drilling SOP Policy Mechanical PM/Checks on mech &
Load indicator fitted to crane to be calibrated prior to installation at site and Rotating Equipment rotating equipment
Mechanical Engineer Recorded on daily activity list
Lubrication of mechanical/rotating equipment (summer/winter periods) Drilling SOP Policy Verification by Rig Manager
Mechanical Engineer Ensure that all mechanical/rotating equipment will be lubricated with the appropriate oils/lubricants PM Programme
during summer and winter periods
RESPONSIBILITY DESCRIPTION INPUT/DOCUMENTATION VERIFICATION
Mud Loggers continuous density recording sensor Contract obligations Real time Monitor
Mud Logger Mud Loggers to use continuous density recording sensor to provide a diverse means of assessing Mudloggers report
mud weight
Monitoring of trip tank by mudloggers Contract obligations Real time Monitor
Mud Logger Mudloggers also monitor the trip tank during a trip to provide redundancy in measurement of mud Mudloggers report
volume
Inspect and maintain continuous density recorder Mud Loggers equipment PM/Checks by Mud Loggers
Mud Logger Inspection and maintenance of the continuous density recorder to ensure diverse means of maintenance manual Mudloggers report
determining mud weight available Checks by Rig Manager
Inspect, maintain, calibrate mud logging equipment Mud Loggers equipment PM/Checks by Mud Loggers
Mud logging equipment, including gas detectors to be calibrated as per manufacturer's maintenance manual Mudloggers report
Mud Logger
requirements Checks by Rig Manager
Monitor mud logging gas detector readings Contract obligations Real time Monitor
Mud Logger
Gas detectors to be monitored continuously to warn of a kick being taken Mudloggers report
Monitor drilling parameters Contract obligations Real time Monitor
Mud Logger
Drilling parameters to be continuously monitored to warn of kick occurence Mudloggers report
Optimise fresh water/chemical flush ahead of cement Drilling Programme To be verified by Rig
Cement Engineer Limit hydrostatic reduction in wellbore during cementing by optimising amount of fresh water and Calculations Manager
chemical pre-flush
Pressure test well test equipment Well Test Programme Recorded on activity sheet by
Ensure well test equipment is pressure tested to at least the maximum anticipated pressure of Well Test Eng.
Well Test Engineer operations before the well is flowed Checks by Operation
Manager
Flare stack location Well Test Programme Recorded on activity sheet by
Flare stack to be installed down wind (as much as practically possible) of the rig site where SIMOPS Procedures Well Test Eng.
Well Test Engineer topography and rig layout allows Checks by Operation
Manager
Well test configuration alteration procedures Well Test Programme Recorded on activity sheet by
Written procedures to be followed for alterations required to well test (clean-up) equipment SIMOPS Procedures Well Test Eng.
Well Test Engineer configuration Checks by Operation
Manager
Continuous monitoring during test Well Test Programme Recorded on activity sheet by
Continuous monitoring of parameters to take place during run of clean-up test to indicate operation Well Test Eng.
Well Test Engineer close to design limits Checks by Operation
Manager
Install grounding straps Logging Company Manual and Checks by Electrical Engineer
Installation of grounding straps to guard against stray currents when explosives are armed Procedures for use and Recorded on activity sheet
Well Logging Engnr storage of Explosives
Control and inventory of radios Logging Company Manual and Checks by Location Manager
Control of inventory and collection of hand held radios/phones to guard against stray currents Procedures for use and & Toolpusher
Well Logging Engnr when explosives are armed storage of Explosives Recorded on activity sheet
PtW System and PtW form(s)
Visual checks on weather conditions Logging Company Manual and Checks by Rig Manager and
Visual checks on weather conditions to guard against stray currents when explosives are armed Procedures for use and Logging Engineer
Well Logging Engnr (i.e. lightning) storage of Explosives
HSE Policy / Plan
Shut down logging unit Logging Company Manual and Recorded on activity sheet by
Well Logging Engnr Logging unit shut down, safety switch locked and key removed to guard against stray currents Procedures for use and Logging Engineer
when explosives are armed storage of Explosives
RESPONSIBILITY DESCRIPTION INPUT/DOCUMENTATION VERIFICATION
Use safety tube for blasting caps Logging Company Manual and Recorded on activity sheet by
Well Logging Engnr Safety tube to be used for all armed blasting caps. If one is not available, operations will be shut Procedures for use and Logging Engineer
down storage of Explosives
Check resistance of detonator Logging Company Manual and Recorded on activity sheet by
Well Logging Engnr Resistors in detonator will be checked using a safety meter prior to electrical connection Procedures for use and Logging Engineer
storage of Explosives
Connection or disconnection of blasting cap Logging Company Manual and Recorded on activity sheet by
Well Logging Engnr Blasting cap to be connected electrically then ballistically. If pulling from hole then disarmed Procedures for use and Logging Engineer
ballistically them electrically storage of Explosives
Safe handling of explosives Logging Company Manual and Recorded on activity sheet by
Charges to be moved to hole (and from - in the case of pulling from hole) hole using safe handling Procedures for use and Logging Engineer
Well Logging Engnr procedures, including use of dedicated battery powered winch (to guard against stray currents) storage of Explosives
Physical check of safety key Logging Company Manual and Recorded on activity sheet by
Presence of safety key i.e. removed from logging unit, to be checked prior to moving charge to Procedures for use and Logging Engineer
Well Logging Engnr guard against premature explosion storage of Explosives Checks by Rig Manager
Daily chlorine dosing of sewage discharge HSE Policy Recorded on daily activity
Rig Medic Responsible for daily checks on discharge quality from sewage unit and for chlorine dosing as Waste Management sheet
required
Use of breathalyser equipment HSE Policy Check by Location Manager
Rig Medic Drivers will be breathalysed to check for alcohol use (only when reasonable doubt exists that driver (if so required)
is refraining from alcohol)
Preventative health programme HSE Plan/Policy Daily POB list with relevant
Rig Medic All camp and rig site workers have to undergo medical checks and receive immunisations as Medical ERP Plan health check information
required
Ensure first aid kits are appropriate for Chinese/Arabic speaking crew HSE Plan/Policy Check by Rig Manager
Rig Medic Instructions on medicines must be in Chinese, English and Arabic for the crew to administer the Medical ERP Plan
correct first aid
Provision of first aid kits HSE Plan/Policy Periodic checks
Rig Medic Ensure first aid kits are available at the rigsite, camp and the PSD vehicles (crew change and Medical ERP Plan
transportation)
Daily inspection of crew vehicle(PSD) HSE Policy / Plan Vehicle check lists and
Daily inspection of crew vehicle according to a defined checklist (i.e. oil and water levels, brakes /Garraf Road Transport Journey Management record
Driver operable, lights operable, horn operable, windscreen wipers operable, tyres inflated, etc.) Management Plan sheets
Periodic Audits by Project
Management
Check trucks prior to transport HSE Policy / Plan Vehicle check lists and
Check car every day or before long trip /Garraf Road Transport Journey Management record
Driver Ensure truck is checked as roadworthy before transportation of hazardous cargoes (diesel, crude Management Plan sheets
oil, explosives, and radioactive sources) Periodic Audits by Project
Management
HSE Critical Task Allocation
All Supervisors Pre-Job Safety Meetings EOFS and GWDC HSE Policy Project Manager
Supervisors to ensure pre-job safety meetings (Toolbox Meetings) are held before all
non-routine tasks
Page 16 of 41
HSE Critical Task Allocation
Project Manager Prepare site and area specific emergency response plan Emergency Response Emerg. Resp. Exercise
Prepare emergency response plan detailing the external emergency response to an Plans/Procedures Review by EOFS Head
emergency at the rig site which cannot be dealt with by onsite facilities office
Project Manager Review,approve and audit Security Plan and related Services. EOFS Security Plan Audit Team
Ensure the condition of the proposed Security Service is acceptable on behalf of EOFS.
Project Manager Competency of Project Team CV and Performance Rprts Peer review and end-of-
Ensure all Project Team Members are competent in his role Experience Level year performance review
Project Manager Maintain, inspect and certify BOPs in accordance with PMS Well Control Manuals Rig Manager
Inspect BOP in line with standards by authorsied institution. Repair should only make Drilling SOP
use of HBRS approved spares
Project Manager Emergency response training for Supervisory staff ERP Plan Emerg. Resp. Exercise
Ensure that personnel involved in implementing emergency response are adequately HSE Induction Training Periodic checks
trained
Project Manager Conduct formal assessment of all proposed changes Drilling SOP Policy and Audit Team
Formal assessment of all changes to procedures and equipment should be conducted Procedures
by a multi-displinary team to address all hazards
Project Manager Dedicated and certified trucks and drivers for hazardous goods transport HSE Policy / Plan Audit Team
Ensure transportation of hazardous goods is carried out by certified trucks and using / Road Transport Management
trained drivers only Plan
Project Manager Trucks for diesel/OBM transport to carry absorbant material HSE Policy / Plan Audit Team
Ensure that trucks transporting diesel/OBM carry adequate quantity of absorbant / Road Transport Management
material (pads and/or bags) to minimise the effect to the environment Plan
Project Manager Trucks for diesel/OBM transport to carry barrier tape HSE Policy / Plan Audit Team
Ensure that trucks transporting diesel/OBM carry adequate quantity of barrier tape to / Road Transport Management
restrict access of people passing by or interfering when spillage occurs Plan
Project Manager Dedicated buses and drivers HSE Policy / Plan Audit Team
Ensure only vehicles approved and drivers trained in defensive driving are used for / Road Transport Management
transportation of crews Plan
Project Manager Site Access Road Markings HSE Policy / Plan Audit Team
Transportation will be undertaken at night (only by exception) and possibly during / Road Transport Management
periods of poor visibility (fog, storm or rain). Therefore the site access road must be Plan
marked with luminescent posts at close intervals that the
Project Manager Set up Camp Hospital HSE Policy / Plan Audit Team
Ensure camp hospital is provided with adequate facilities to treat potential accidents /Garraf Medical Emergencies
Plan
Page 17 of 41
HSE Critical Task Allocation
Project Manager Competency of Mud Loggers (provisionally) Sub-contract obligations Periodic assessment by
Ensure Mud Loggers are competent in their role, including kick detection, Experience levels EOFS Rig Manager
communication, monitoring of pressures and recording
Project Manager Competency of Casing Crew (provisionally) Sub-contract obligations Periodic assessment by
Ensure Casing Crew are competent in their role, including power unit control, Experience levels EOFS Rig Manager
casing/completion make-up, stabbing etc and safe working practices
Project Manager Competency of Cementing Crew (provisionally) Sub-contract obligations Periodic assessment by
Ensure Cementing Crew are competent in their role, including bulk control, density & Experience levels EOFS Rig Manager
pumping rate control, additives control etc and safe working practices
Page 18 of 41
HSE Critical Task Allocation
Page 19 of 41
HSE Critical Task Allocation
HSE Manager Prepare rigsite and camp emergency response plan ER Plan Bridging Documents
Prepare emergency response plan detailing the external emergency response to an Review
emergency together with PCIHBV’s and Garraf ER Plans Emerg. Resp. Exercise
HSE Manager Inspect/verify test certification of all lifting/hoisting equipment HSE Policy / Plan Checks by Rig Manager
Inspection and verification of lifting equipment certification prior to Garraf well Lifting Equipment Register and Project Manager
operations to ensure that documentation is valid and equipment is marked Lifting / Hoisting Plan
HSE Manager Maintenance and inspection of Crew Vehicle HSE Policy / Plan PM/Checks on Road
Ensure the crew vehicle undergoes regular maintenance and equipment is operable /Garraf Road Transport Transport System
and in accordance with local regulations Management Plan
HSE Manager Speed Limit HSE Policy / Plan PM/Checks on Road
Ensure speed limits signs are posted at the start of the site access road to remind /Garraf Road Transport Transport System
drivers of the maximum allowable speed of travel Management Plan
HSE Manager Train crew in first aid HSE Policy / Plan Contract Site Doctor
Ensure all crew members are trained in first aid
HSE Manager Non-smoking campaign HSE Policy / Plan HSE Team Leader
Promote campaign to stop smoking
HSE Manager Competency of crew members in Basic or Advanced First Aid HSE Policy / Plan
Ensure all crew members have attended Basic First Aid Training and a minimum of 2 Contract obligations/ Audit
(two) on each shift have attended Advanced First Aid Training Medical Emergencies Plan
Page 20 of 41
HSE Critical Task Allocation
Rig Manager Run formation integrity test Drilling Programme IADC Drilling reports
Test formation to leak off after drilling out the shoe to determine maximum allowable Well Control Manuals
mud weight and kick tolerance for drilling each section of the well
Rig Manager Prepare Well Killing Sheet Well Control Manuals IADC Drilling reports
Well kill sheet to be prepared after a kick has been detected based on the kill method Drilling SOP Policy
agreed by supervisors and kept up to date during well killing process
Rig Manager Well Kill Operations Well Control Manuals IADC Drilling reports
Following well shut-in due to kick, kill the well according to the Kill Sheet (as agreed Drilling SOP Policy
between supervisors)
Rig Manager Communications ERP Plans Check on ERP contact list
Emergency contacts posted / Periodical revision of the
list
Rig Manager Emergency Response Plan readiness ERP Plans Ongoing review/revision
Confirm that Garraf Rig ERP covers all eventualities and assigns appropriate roles and Training/Induction for all Emerg. Resp. Exercise
responsibilities, read and understood by all for Medivac/Environm.
event
Rig Manager Capacity markings on lifting equipment HSE Policy / Plan Checks by HSE
Ensure only lifting equipment marked as certified is used on the site Rigging / Slinging Training Coordinator, HSE
Manager, Toolpusher
Rig Manager Enforce rig site smoking policy HSE Policy / Plan Checks by HSE
Smoking on rig site to be allowed in specified areas only Appropriate signs posted Coordinator, HSE
Manager, Toolpusher
Rig Manager Use Unsafe Act Auditing Process HSE Policy / Plan Checks by HSE Manager
Encourage use of Unsafe Act Auditing Process at the rig site and camp and during HSE and Induction Training
transportation
Rig Manager Wear Personal Protective Equipment HSE Policy / Plan Checks by HSE
Ensure all staff (also third party) to wear appropriate Personal Protective Equipment for HSE and Induction Training Coordinator, HSE
all tasks Manager, Toolpusher
Rig Manager Prevent smoking during transportation HSE Policy / Plan Checks by Safety
Enforce no smoking rules during transportation to prevent discarded cigarette being HSE and Induction Training Coordinator
thrown away in the surrounding area
Rig Manager Fire Extinguisher on crew vehicle(PSD) HSE Policy / Plan Checks by Safety
Ensure a fire extinguisher is in place on the bus and is inspected regularly. Ensure /Garraf Road Transport Coordinator
driver is aware of its operation Management Plan
Rig Manager Weekly review of vehicle condition HSE Policy / Plan Record of daily bus
Review of daily vehicle checklists /Garraf Road Transport checklist
Management Plan
Page 21 of 41
HSE Critical Task Allocation
Page 22 of 41
HSE Critical Task Allocation
HSE Coordinator Fire fighting equipment (rig site) HSE Policy / Plan Contract PM/Checks by Mech.
Ensure fire-fighting equipment is installed at the rig site and inspected on a regular obligations Engineer. Inspection by
basis HSE Coordinator
HSE Coordinator Fire fighting equipment (camp site) HSE Policy / Plan Contract PM/Checks by Mech. Eng
Ensure camp is provided with fire fighting equipment which is checked on a regular obligations assisted by Campboss.
basis Inspection by HSE
Coordinator
HSE Coordinator Install and test fire alarm HSE Policy / Plan Daily activity sheet
Ensure fire alarm is installed at the camp and regularly tested Campboss
HSE Coordinator Maintain Breathing Apparatus HSE Policy / Plan PM/Checks by Mech. Eng
Ensure breathing apparatus sets are certified assisted. Inspection by
HSE Coordinator
HSE Coordinator Hold HSE Meetings involving all of the crew HSE Policy / Plan/ HSE Alerts Report by Rig Mangr and
HSE meetings will be held as a forum for discussion of HSE concerns and to feed back HSE Coordinator
HSE statistics for the operations to the Project Manager
HSE Coordinator Transportation policy HSE Policy / Plan /Garraf Journey Management
Implement transportation policy detailing required behaviour of passengers and driver Road Transport Management record sheets.
(i.e. maximum working hours, speed limit, no alcohol for driver, no talking to driver by Plan Periodic Audits by
passengers except in an emergency, wearing of seatbelts, etc) Project Management
Page 23 of 41
HSE Critical Task Allocation
Toolpusher Control of Portable electrical equipment HSE Policy / Plan Induction Checks by Toolpusher
Ensure that signs are posted warning people not to carry portable electrical equipment Training
(including mobile phones and walkie talkies) into Hazardous Areas (as defined by Area Safety Meetings
Classification) unless suitably rated for Warning Signs
Toolpusher Rotary Table centred over well bore Drilling Ops Policy Checks by Rig Manager
Ensure that substructure/mast is centred and level, such that rotary table is centred Drilling Programme Handover Notes
over well bore to minimise casing wear
Toolpusher Install BOPs Well Control Manuals Checks by Rig Manager
Correctly install BOPs and related equipment e.g. degasser, poorboy, choke manifold, Drilling SOP Policy
remote panel
Toolpusher Maintain and Inspect BOPs Well Control Manuals PM/Checks by Rig
BOPs and related equipment to be inspected on a weekly basis Drilling SOP Policy Manager
Toolpusher Ensure use of portable gas detectors Permit-to-Work System PM/Checks on electrical
Portable gas detection to be used when fixed system is being maintained and/or when equipment
area has to be checked to perform hot work Periodic Audits on PtW
Toolpusher Operate Degassing equipment Well Control Manuals Handover Notes
Ensure degassing equipment is operated while drilling hydrocarbon bearing zones and Drilling SOP Policy PM/Checks on Degasser
if gas cut mud is observed System
Toolpusher Spot checks of Drilling Process Drilling SOP Policy Checks by Toolpusher /
Perform spot checks to confirm accurate interpretation of mud monitoring system data Rig Manager
by driller
Toolpusher Pressure test BOPs Drilling SOP Policy Controlled through
BOPs and related equipment to be pressure tested on installation and every two weeks Drilling Program Standing Instructions by
subsequently Rig Manager
Toolpusher Function test BOPs Drilling SOP Policy Checks by Toolpusher &
BOPs function tested during tripping operations Rig Manager
Toolpusher Determine maximum pull on drill line Drilling SOP Policy Checks by Rig Manager
Determine maximum pull that can be exerted on drill line and advise driller accordingly Standing Instructions
Toolpusher Cessation of operations during extreme weather Drilling SOP Policy Checks by Rig Manager
Operations to be suspended during extremes of weather if safety of the operation
threatened
Toolpusher Mud checks verification Drilling SOP Policy Checks by Rig Manager
Spot check measurement of mud weight and viscosity periodically during a tour
Toolpusher Prepare Trip Sheet Drilling SOP Policy Checks by Rig Manager
Trip sheet to be prepared before every trip to manage the tripping
Page 24 of 41
HSE Critical Task Allocation
Toolpusher Calculate space out Drilling SOP Policy Checks by Rig Manager
Toolpusher to calculate maximum height of stump above the rotary table to permit Standing Instructions
correct closure of pipe rams on the drill pipe
Toolpusher Pump fresh water down back side of drill string Drilling SOP Policy Checks by Rig Manager
Pump fresh water down back side of drill string in response to loss of fluid in attempt to Standing Instructions
maintain hydrostatic control of annulus
Toolpusher Conduct emergency evacuation drill (rig site) HSE Policy / Plan Periodic rig site audits
Emergency evacuation drills to be performed regularly to ensure personnel are aware of ER Plans Emerg. Resp. Exercise
appropriate response to different situations
Toolpusher Install and test braking system Drilling SOP Policy Checks by Toolpusher &
Primary and secondary braking system for the drawworks to be installed and tested Standing Instructions Rig Manager
prior to drilling
Toolpusher Install and test crown-o-matic Drilling SOP Policy Checks by Toolpusher &
Ensure crown-o-matic system is installed to guard against pulling travelling blocks into Rig Manager
crown block
Toolpusher Safety factor on drill line Drilling SOP Policy Checks by Toolpusher &
Confirm that drill line has safety design factor appropriate for operations, compared to Rig Manager
expected loading
Toolpusher Installation of drill string weight indicator Drilling SOP Policy Checks by Toolpusher &
Verify installation and calibration of weight indicator for drill Rig Manager
Toolpusher Weight Indicator Redundant System Drilling SOP Policy Checks by Toolpusher &
Ensure that string weight can be verified with redundant (hydraulic-electric) system as Rig Manager
provided by Mud Loggers
Toolpusher Drill line inspection program Drilling SOP Policy Checks by Toolpusher &
Wear of drilling line controlled by ton mile program and drilling line inspection program Rig Manager
to determine realistic goal for cut-off. Inspections performed by Toolpusher or driller and
to include drilling line and anchor points
Toolpusher Inspection of cables and slings HSE Policy / Plan Checks by Safety
Cables and slings condition to be visually inspected weekly Coordinator, Rig
Manager, Toolpusher
Toolpusher Inspection of mast HSE Policy / Plan Checks by Derrickman
Mast inspected for loose objects, correct placement of safety pins and chains and and Driller.
potential failure during weekly rig inspection Handover Notes.
Toolpusher Competency of crew in lifting operations HSE Policy / Plan Checks by Safety
Toolpusher to observe crew during slinging operations to ensure they are competent Rigging / Slinging Training Coordinator, Rig
Manager, Toolpusher
Page 25 of 41
HSE Critical Task Allocation
Page 26 of 41
HSE Critical Task Allocation
Page 27 of 41
HSE Critical Task Allocation
Page 28 of 41
HSE Critical Task Allocation
Mudman Monitor trip tank during a trip Drilling SOP Policy Checks by Toolpusher &
Comparison of actual volume required to fill well with calculated volume from trip sheet Standing Instructions Rig Manager
on a continuous basis
Mudman Monitor mud system Drilling SOP Policy Checks by Toolpusher &
Monitoring of the mud properties, system flows and pit levels every 15-30 minutes Standing Instructions Rig Manager
Mudman Maintain water tank levels Drilling SOP Policy Checks by Toolpusher &
Water tank levels to be maintained at set level to ensure sufficient supplies available Standing Instructions Rig Manager
Mudman Confirm trip tank valve alignments Drilling SOP Policy Checks by Toolpusher &
Confirm that valves between flow line and shakers is shut to prevent loss of fluid to Standing Instructions Rig Manager
active pits
Page 29 of 41
HSE Critical Task Allocation
Electrical Engineer Zoned electrical equipment Drilling SOP Policy Electrical Checks by Toolpusher
Ensure that electrical equipment installed on the rig site is appropriate installed and Equipment Periodic Audits
maintained to area classification (including telephone handsets) PM/Checks on electrical
equipment
Electrical Engineer Camp electrical equipment Drilling SOP Policy Electrical Recorded on daily activity
Inspection of initial installation of electrical equipment within camp area to verify correct Equipment list
functioning of camp area circuit
Electrical Engineer Grounding of camp accommodation Drilling SOP Policy Electrical Recorded on daily activity
Verifications that camp accommodation buildings are grounded on initial installation and Equipment list
weekly thereafter
Electrical Engineer Maintain PVT system Drilling SOP Policy Electrical PM/Checks on electrical
Maintenance of pit volume totalizers to ensure accurate volume measurement Equipment equipment
Recorded on daily activity
list
Electrical Engineer Maintain flow indicator Drilling SOP Policy Electrical PM/Checks on electrical
Maintenance of flow indicators to ensure accurate volume Equipment equipment
Recorded on daily activity
list
Electrical Engineer Gas detection equipment Well Control Manuals PM/Checks on electrical
Gas detection equipment to be installed beneath rig floor, drillers console and shaker Drilling SOP Policy Electrical equipment
area of pits and tested on a regular basis Equipment Recorded on daily activity
list
Electrical Engineer Portable gas detectors Permit-to-Work System PM/Checks on electrical
Portable gas detection to be used when fixed system is being maintained and/or when equipment
area has to be checked to perform hot work Periodic Audits on PtW
Electrical Engineer Lightning protection of camp accommodation Drilling SOP Policy Electrical Periodic Audits
Verifications that camp accommodation buildings are protected against lightning strikes Equipment PM/Checks on electrical
equipment
Electrical Engineer Ventilation and air extraction system Drilling SOP Policy Electrical Verification by Rig
Ensure that kitchens have adequate ventilation and air extraction system Equipment Manager
Electrical Engineer Smoke Detectors Drilling SOP Policy Electrical Verification by Rig
Ensure that all rooms and facilities are fitted with smoke detectors Equipment Manager
Page 30 of 41
HSE Critical Task Allocation
Mechanical Engineer Install spark arrestors on generator engine exhausts Drilling SOP Policy Mechanical PM/Checks on mech. &
Fit spark arrestors on generator engine exhausts to prevent sparks igniting and Rotating Equipment rotating equipment
Checks by Toolpusher
Recorded on daily activity
list
Mechanical Engineer Inspect and maintain power package Drilling SOP Policy Mechanical PM/Checks on mech &
Maintain adequate fuel, lub oil and water level to ensure dependability of electrical and Rotating Equipment rotating equipment
generation. Verify that water supply to engine exhaust is functional Recorded on daily activity
list
Mechanical Engineer Maintain water transfer system Drilling SOP Policy Mechanical PM/Checks on mech &
Maintain water transfer system in good repair and Rotating Equipment rotating equipment
Recorded on daily activity
list
Mechanical Engineer Maintain and inspect trip tank Drilling SOP Policy Mechanical PM/Checks on mech &
Maintain and inspect trip tank equipment, especially prior to each tripping operation and Rotating Equipment rotating equipment
Recorded on daily activity
list
Mechanical Engineer Inspect and maintain centrifugal pumps Drilling SOP Policy Mechanical PM/Checks on mech &
Inspect and maintain mud system pumps (mud pumps, trip tank pump and mud mixing and Rotating Equipment rotating equipment
pumps) Recorded on daily activity
list
Mechanical Engineer Calibrate pressure gauges Drilling SOP Policy Mechanical PM/Checks on mech &
Regular calibration of pressure gauges to ensure annular and drill pipe pressures is and Rotating Equipment rotating equipment
accurately known during drilling operations Recorded on daily activity
list
Mechanical Engineer Inspect and maintain accumulator Well Control Manuals PM/Checks on mech &
Accumulator to be inspected and maintained on a regular basis GWDC Policy Mechanical and rotating equipment
Rotating Equipment Checks by Toolpusher &
Rig Manager
Recorded on daily activity
list
Mechanical Engineer Calibration of crane load indicator Drilling SOP Policy Mechanical PM/Checks on mech &
Load indicator fitted to crane to be calibrated prior to installation at site and Rotating Equipment rotating equipment
Recorded on daily activity
list
Mechanical Engineer Lubrication of mechanical/rotating equipment (summer/winter periods) Drilling SOP Policy Verification by Rig
Ensure that all mechanical/rotating equipment will be lubricated with the appropriate PM Programme Manager
oils/lubricants during summer and winter periods
Page 31 of 41
HSE Critical Task Allocation
Mud Logger Mud Loggers continuous density recording sensor Contract obligations Real time Monitor
Mud Loggers to use continuous density recording sensor to provide a diverse means of Mudloggers report
assessing mud weight
Mud Logger Monitoring of trip tank by mudloggers Contract obligations Real time Monitor
Mudloggers also monitor the trip tank during a trip to provide redundancy in Mudloggers report
measurement of mud volume
Mud Logger Inspect and maintain continuous density recorder Mud Loggers equipment PM/Checks by Mud
Inspection and maintenance of the continuous density recorder to ensure diverse maintenance manual Loggers
means of determining mud weight available Mudloggers report
Checks by Rig Manager
Mud Logger Inspect, maintain, calibrate mud logging equipment Mud Loggers equipment PM/Checks by Mud
Mud logging equipment, including gas detectors to be calibrated as per manufacturer's maintenance manual Loggers
requirements Mudloggers report
Checks by Rig Manager
Mud Logger Monitor mud logging gas detector readings Contract obligations Real time Monitor
Gas detectors to be monitored continuously to warn of a kick being taken Mudloggers report
Mud Logger Monitor drilling parameters Contract obligations Real time Monitor
Drilling parameters to be continuously monitored to warn of kick occurence Mudloggers report
Page 32 of 41
HSE Critical Task Allocation
Mud Engineer Monitoring of Discharges HSE Policy / Plan Checks by Rig Manager
Liquid discharges to be minimised. Liquids to be re-used as much as practically Waste Management Plan
possible
Mud Engineer Calibration of mud scales Contract obligations Recorded on daily mud
Calibration of mud scales weekly to ensure accurate measurement of mud density check sheets
Mud Engineer Maintain appropriate mud weight Well Control Manuals IADC reports
Maintain mud weight at a value less than the maximum mud weight determined by the Drilling Programme
formation integrity test
Mud Engineer Maintain adequate mud stocks Well Control Manuals IADC reports
Maintain adequate reserve mud and ensure that sufficient stores of mud and water are Drilling Programme Recorded on daily mud
available to maintain drilling fluid properties. Levels determined by mud engineer check sheets
Mud Engineer Monitor mud properties Standing Order Recorded on daily mud
Monitor of mud properties on a tourly basis check sheets
Page 33 of 41
HSE Critical Task Allocation
Cement Engineer Monitor cement samples Mud Lab for properties Representative samples
Cement samples to be monitored at surface to determine properties/setting time Drilling Programme
Cement Engineer Use of appropriate formulation Drilling and Cementation Test Reports
Cement formulation to be chosen to ensure that required setting time is minimised to Programme
reduce the possibilities for annular flow of gas from the formation
Cement Engineer Optimise fresh water/chemical flush ahead of cement Drilling Programme To be verified by Rig
Limit hydrostatic reduction in wellbore during cementing by optimising amount of fresh Calculations Manager
water and chemical pre-flush
Page 34 of 41
HSE Critical Task Allocation
Well Test Engineer Pressure test well test equipment Well Test Programme Recorded on activity
Ensure well test equipment is pressure tested to at least the maximum anticipated sheet by Well Test Eng.
pressure of operations before the well is flowed Checks by Operation
Manager
Well Test Engineer Flare stack location Well Test Programme Recorded on activity
Flare stack to be installed down wind (as much as practically possible) of the rig site SIMOPS Procedures sheet by Well Test Eng.
where topography and rig layout allows Checks by Operation
Manager
Well Test Engineer Well test configuration alteration procedures Well Test Programme Recorded on activity
Written procedures to be followed for alterations required to well test (clean-up) SIMOPS Procedures sheet by Well Test Eng.
equipment configuration Checks by Operation
Manager
Well Test Engineer Continuous monitoring during test Well Test Programme Recorded on activity
Continuous monitoring of parameters to take place during run of clean-up test to sheet by Well Test Eng.
indicate operation close to design limits Checks by Operation
Manager
Page 35 of 41
HSE Critical Task Allocation
Well Logging Engnr Install grounding straps Logging Company Manual and Checks by Electrical
Installation of grounding straps to guard against stray currents when explosives are Procedures for use and Engineer
armed storage of Explosives Recorded on activity
sheet
Well Logging Engnr Control and inventory of radios Logging Company Manual and Checks by Location
Control of inventory and collection of hand held radios/phones to guard against stray Procedures for use and Manager & Toolpusher
currents when explosives are armed storage of Explosives Recorded on activity
PtW System sheet and PtW form(s)
Well Logging Engnr Visual checks on weather conditions Logging Company Manual and Checks by Rig Manager
Visual checks on weather conditions to guard against stray currents when explosives Procedures for use and and Logging Engineer
are armed (i.e. lightning) storage of Explosives
HSE Policy / Plan
Well Logging Engnr Shut down logging unit Logging Company Manual and Recorded on activity
Logging unit shut down, safety switch locked and key removed to guard against stray Procedures for use and sheet by Logging
currents when explosives are armed storage of Explosives Engineer
Well Logging Engnr Use safety tube for blasting caps Logging Company Manual and Recorded on activity
Safety tube to be used for all armed blasting caps. If one is not available, operations will Procedures for use and sheet by Logging
be shut down storage of Explosives Engineer
Well Logging Engnr Check resistance of detonator Logging Company Manual and Recorded on activity
Resistors in detonator will be checked using a safety meter prior to electrical connection Procedures for use and sheet by Logging
storage of Explosives Engineer
Well Logging Engnr Connection or disconnection of blasting cap Logging Company Manual and Recorded on activity
Blasting cap to be connected electrically then ballistically. If pulling from hole then Procedures for use and sheet by Logging
disarmed ballistically them electrically storage of Explosives Engineer
Well Logging Engnr Safe handling of explosives Logging Company Manual and Recorded on activity
Charges to be moved to hole (and from - in the case of pulling from hole) hole using Procedures for use and sheet by Logging
safe handling procedures, including use of dedicated battery powered winch (to guard storage of Explosives Engineer
against stray currents)
Well Logging Engnr Physical check of safety key Logging Company Manual and Recorded on activity
Presence of safety key i.e. removed from logging unit, to be checked prior to moving Procedures for use and sheet by Logging
charge to guard against premature explosion storage of Explosives Engineer
Checks by Rig Manager
Page 36 of 41
HSE Critical Task Allocation
Page 37 of 41
HSE Critical Task Allocation
Rig Medic Daily chlorine dosing of sewage discharge HSE Policy Recorded on daily activity
Responsible for daily checks on discharge quality from sewage unit and for chlorine Waste Management sheet
dosing as required
Rig Medic Use of breathalyser equipment HSE Policy Check by Location
Drivers will be breathalysed to check for alcohol use (only when reasonable doubt Manager (if so required)
exists that driver is refraining from alcohol)
Rig Medic Preventative health programme HSE Plan/Policy Daily POB list with
All camp and rig site workers have to undergo medical checks and receive Medical ERP Plan relevant health check
immunisations as required information
Rig Medic Ensure first aid kits are appropriate for Chinese/Arabic speaking crew HSE Plan/Policy Check by Rig Manager
Instructions on medicines must be in Chinese, English and Arabic for the crew to Medical ERP Plan
administer the correct first aid
Rig Medic Provision of first aid kits HSE Plan/Policy Periodic checks
Ensure first aid kits are available at the rigsite, camp and the PSD vehicles (crew Medical ERP Plan
change and transportation)
Page 38 of 41
HSE Critical Task Allocation
Driver Daily inspection of crew vehicle(PSD) HSE Policy / Plan Vehicle check lists and
Daily inspection of crew vehicle according to a defined checklist (i.e. oil and water /Garraf Road Transport Journey Management
levels, brakes operable, lights operable, horn operable, windscreen wipers operable, Management Plan record sheets
tyres inflated, etc.) Periodic Audits by Project
Management
Driver Check trucks prior to transport HSE Policy / Plan Vehicle check lists and
Check car every day or before long trip /Garraf Road Transport Journey Management
Ensure truck is checked as roadworthy before transportation of hazardous cargoes Management Plan record sheets
(diesel, crude oil, explosives, and radioactive sources) Periodic Audits by Project
Management
Page 39 of 41
HSE Critical Task Allocation
Page 40 of 41
HSE Critical Task Allocation
Page 41 of 41