Network Diagram
Network Diagram
Sub structure RCC Excavation Earth dressing PCC foundation RCC of foundation Column up to plinth Plinth beam Rcc
Complition of Sub structure
Start: 9/18/2023 ID: 3 Start: 9/18/2023 ID: 4 Start: 9/26/2023 ID: 5 Start: 9/29/2023 ID: 6 Start: 10/3/2023 ID: 7 Start: 10/13/2023 ID: 8 Start: 10/17/2023 ID: 9
Finish: 10/26/2023 Dur: 28.88 days Finish: 9/26/2023 Dur: 7 days Finish: 9/29/2023 Dur: 3 days Finish: 10/3/2023 Dur: 3 days Finish: 10/13/2023 Dur: 7 days Finish: 10/17/2023 Dur: 3 days Finish: 10/26/2023 Dur: 7 days Milestone Date: 10/26/2023
Comp: 0% Res: Site engineer, Excavator Res: Site engineer Res: CA[1], cement[1], sand[1], Site engineer Res: CA[1], cement[1], sand[1], Site engineer, steel[1] Res: CA[1], cement[1], sand[1], Site engineer, steel[1] Res: CA[1], cement[1], sand[1], Site engineer, steel[1] ID: 10
Super structure RCC Ground floor Column up to slab Ground floor Slab
Start: 10/27/2023 ID: 11 Start: 10/27/2023 ID: 12 Start: 10/27/2023 ID: 13 Start: 11/1/2023 ID: 14
Finish: 1/10/2024 Dur: 53.63 days Finish: 11/14/2023 Dur: 12.81 days Finish: 11/1/2023 Dur: 4 days Finish: 11/14/2023 Dur: 10 days
Comp: 0% Comp: 0% Res: CA[1], cement[1], sand[1], Site engineer, steel[1] Res: CA[1], cement[1], sand[1], Site engineer, steel[1]
Page 1
Project: Project1 Critical Noncritical Critical Milestone Milestone Critical Summary Summary Critical Inserted Inserted Critical Marked Marked Critical External External Project Summary Highlighted Critical Highlighted Noncritical