Consultant Client Contractor

TESSCO. AACM-DMT HPEGC

SCHEDULED ACTIVITIES

Project: G-432023 Rehabilitation of Boundary Walls of Graveyards of Al Ain Region.

REPORT NUMBER DATE DAY

HEGC/G-432023/DPR-055 21-Jan-24 Sunday

LOCATION SITE ACTIVITIES PLANNED OFFICE ACTIVITIES PLANNED ASSIGNED TO

• Preparation for temporary fence.


MAZYAD -019
• Ground Levelling.

• Complete erecting temporary fence.

MAZYAD -112 • Complete Ground Levelling.

• Removing chain-link fence.


• Preparing AL MUTARED -123
existing and OGL drawing. Draftsmen

• Preparing MEP drawings for


AL MUTARED MAZYAD -019 and -112.
Maintanance Work.
123

Demarcation
MAZYAD -168
of
AL MUTARED -123
Obstructions
AL QATTARA -115
and OGL

REMARKS

G-432023 Rehabilitation of The Boundary Walls of Graveyards in Al Ain Region