You are on page 1of 4

The following steps may be adopted in the design of a Given: Size of slab = 7.5 m x 3.5 m.

Live load = 5 kN/m


simply supported one way slab; To Find: Design the one way slab
Step 1: Effective Span: The effective span to be taken as 1. Effective Depth and Span: ly/lx=7.5/3.5>2 hence it is
centre to centre distance between bearings. one way slab

Step 2: Thickness of the Slab: The thickness of slab is Assuming total depth, D= 150 mm
governed by deflection consideration rather than flexural d= 150-20-5=125 mm
strength consideration. Clear cover 20 mm and diameter of main bar = 10 mm

Step 3: Actual Effective Span of Slab: Actual effective ii. Effective Span Length (leff): It should be least of the
span of the slab is the lesser of the following: following:
I. Distance between centres of bearings. a. Centre to centre distance = 3.5+0.2 8.7 m
ii. Clear span + effective depth. b. Clear span + effective depth 3.5+0.125-3.625 m
Effective span, leff =3.625 m
Step 4: Loads on the Slab: Estimate the total load on the
slab, per square meter. 2 Design Load (wu), Factored Moment (Mu), and Shear
Force (Vu):
Step 5: Factored Load and Factored Bending Moment: I. i. Load for 1 m width of slab:
The factored load, Wu= 1.5 W Self weight of slab = 25 bD=25 x 1 x 0.15 3.75 kN/m
ii. Factored moment is given by, Mu=Wu.l^2/8 where’ll= Live load= 5 kN/m
Effective span of the slab. Total load 5+3.75 8.75 kN/m
ii. Design load, w=1.5x8.75=13.125 kN/m
Step 6: Required Effective Depth:
iii. Factored moment, M= w, 13.125 (3.625)
I. the required effective depth to be obtained by equating
iv. Factored shear
the limiting moment resistance to the factored bending
force,Vu=Wul/2=13.125x3.5/2=22.97kN
moment.
ineffective depth from flexural strength consideration: 3. Check for Effective Depth of Slab:
Effective depth required,dreq=√Mu,lim/Ru.b Effective depth required, (For Fe415 and M20, Ru=2.76)
dreqd=√Mu/Rub=√21.6x10^6/2.76x1000
Step 7: Area of Steel Required Per Metre Width of Slab:
= 88.5 mm < 125 mm
Area of steel required per m width, Ast
Hence provide 125 mm thick slab of one way slab.
Mu,lim=0.87fyxAstxd(1-(fyxast/fckxbd)
4. Area of Tensile Steel (Ast):
Step 8: Spacing of Reinforcements:
i. Mu=0.87.Fy.Ast.d(1-(Ast.fy/fck.bd)
By assuming diameter of bar, the spacing of bars are
21.6 x 10^6= 0.87x415x Ast x125x(1-
computed as,
(Astx415/20x1000x125))=Ast=524.2mm2
Spacing of bars=Area of one bar x b/Ast,req
ii.using 10mm diameter
Provide 8 mm diameter bars of Fe415 or 10 mm diameter
bars,Afie=(3.14/4)x10^2=78.5mm2
bars to 12 mm diameter bars of Fe250.
iii.Spacing of 10 mm diameter bars =1000x Afie/Ast=
Step 9: Check for Serviceability: Find the percentage of 1000x78.5/524.2=150mm2
steel provided. This should not be greater than the Provide 10 mm diameter bar @ 150 mm c/c, Ast=524.2
percentage of steel assumed initially. However if the mm².
percentage of steel exceed the values assumed initially iv. Bending alternate bars at 510
then find the actual modification factor corresponding to mm(l/7=3625/7=517mm)from cente of support or 410
the percentage of steel provided and find the depth mm from the face of support (Ast/2=524.2/2=262.1)
required for serviceability.
5. Distribution Steel:
Step 10: Distribution Steel: Provide distribution steel Distribution reinforcement is provided in the longer
running at right angles to the main steel. The distribution direction i.e., 7.5 m, = 0.12% of cross-sectional area
steel shall be 0.12% of the gross area of the slab when =0.12/100x1000x150=180mm2
Fe415 steel is used and 0.15% of the gross area of the Using 6 mm diameter bar
slab when Fe250 steel is used. Spacing,S=1000xAfie/Ast=1000x28.3/180=157.22mm
Provide 6mm diameter bar@150mm c/c in the longer
Step 11: Check for Shear: Generally shear stresses in a direction
slab are quite low. However if it is desired to check for
shear, the nominal shear stress tau.v, at the support 6.Check for Shear
should be lesser of design shear strength. i Factored shear force,Vu=22970N
ii. Nomial shear stress tau.v,
Step 12: Check for Development Length: According to tau.v=Vu/bd=22970/1000x125=0.184N/mm2
IS: 456-2000, the condition to be satisfied is iii. Design shear strength of concrete (tc):
pt=100xAst/bd=100x262.1/1000x125=0.21%
Ld<1.3(Mr/Vu)+Lo
For percentage of steel and M20 concrete
Step 13: Anchorage Length: All bars must be taken into 𝜏c=0.28+
the support at least for a distance equal to Ld/3.
(0.36-0.28/0.25-0.15)x(0.21-0.15)=0.328N/mm² support, each bar should be embedded into the support by
𝜏v>𝜏c ,hence design is safe. a length equal to Ld= 45fie= 45 x 8 = 360 mm.

7. Check for Deflection: ii. This could be best achieved by providing one bend of
i. pt=100.Ast/bd=100x524.2/1000x125=0.42% 90°where anchorage valueof thisbend=8fie=8x8=64 mm.
ii. Fs=0.58.fy.(Ast req/Ast iii. Thus, total anchorage value achieved
provide)=0.58x415(524.2/524.2)=240N/mm2 =(300-20)+64+(150-2x20-4)=45mm>Ld
iii. For pt=0.4%,and fs=240N/mm2.kt=1.55
iv. (l/d)max=20xkt=20x1.55=31 5. Check for Shear:
v. (l/d) provide=3625/125=29 Neglecting the taper and taking an average, d= 110 mm
vi. (l/d)max>(l/d)provided,Hence design is safe. Nominal shear stress,
𝜏v=Vu/bd=1.5x4730/1000x110=0.0645N/mm2
8 Check for Development Length: ii. This is much less than the permissible value of
i Moment of resistance at support by 10 mm diameter 𝜏c= 1.3 x 0.18 =0.234 N/mm² for M 20 concrete
bars. @300 mm c/c. pt=100.As/bd=100x201.2/1000x110 =0.183% hence safe
Reinforcement at supports, (300-20)+64 + (150-2x 20-4) = 450 mm > L eries
Provide , Ast= 524.2/2 =262.1 mm²
Mr= 0.87y.Ast.d(1-(fy.Ast/fck.bd) 6. Distribution Reinforcement:
=0.87x415x262.1x125x(1-(415x262.1/20x1000x125)) i. Asd=0.126D/100= 0.12 x 1000D/100
=11.30x10^6 N-mm = 1.2 D mm² = 1.2 x 150 = 180 mm²
ii.Factored shear force Vu=22970N Using 8 mm fie bars, each having Afie,=50.3 mm².
iii. Providing no hooks, lo=0 Spacing, S=1000 Afie/Asd=1000 x 50.3/180=280 mm.
iv. Mr/V+lo=11.30x10^6/22970=492mm
A Serviceability of Limit State:
Ld=(0.87fy)fie/4.taubd=0.87x415x10/4x1.2x1.6=470mm
1.A structure must fulfill three basic requirements,
=Mr/v + Lo>Ld
namely, structural, functional and aesthetic, during its life
Hence slab is safe.
span under normal service conditions.
Given: Overhang length = 1.1 m, Load = 1000 N/m², 2. Excessive deflection and cracking of the concrete
Finishing load = 800 N/m², fck=20 N/mm², fy=415 adversely affect the appearance and efficiency of the
N/mm². To Find: Design cantilever slab. structure and cause discomfort the user.
3. Excessive deformation may lead to local damage to
1. Bending Moment and Shear Force: Assume the finishes. Excessive cracking leads to corrosion and
cantilever to be of average total thickness of 100 mm. adversely affects the appearance.
Dead weight =0.1 x 1 x 25000 = 2500 N/m 4. The deflection that occurs in case of structure can be
Total weight, w = 2500+800+ 1000 = 4300 N/m divided into the following types: i Short term deflection.
Moment, M= wL2/2= 4300(1.1)^2/2 Ii. Long term deflection,
=2601.5 N-m=2.6015 x 10^6 N-mm B. Short Term Deflection
Factored bending moment 1. The short term or instantaneous deflection occurs due
Mu lim = 1.5 x 2.6015= 4 kN-m to initial elastic deformation of member under dead load
Vmax =wL = 4300 x 1.1 = 4730 N and permanent imposed load under service condition.
2 The factors affecting the short term deflection are as
2. Design of Section by LSM: under:
d =√(Mu lim/0.138.fck.b) = √(4x10^6/(0.138x20x 1000) i Span and supporting conditions.
=38.07 mm ii. Magnitude and distribution of live load.
Hence, provide overall depth of beam, D = 150 mm iii. Cross-sectional dimension.
Keeping nominal cover of 20 mm and using 8 mm & iv. Tension and compression reinforcements.
bars,Effective depth, d=150-20-8/2-126 mm. Reduce v. Stress in steel.
D=100 mm at free end vi. Grade of concrete.
3. Area of Reinforcement: C. Long Term Deflection: 1. Long term deflection occurs
Mulim=0.87.Ast.fy.d.(1-(fy.Ast/bd.fck) due to creep and shrinkage under sustained load and
4x10^6=0.87x415xAstx126x(1-(Astx415/1000x126x20) additional elastic deflection due to temporary live loads.
Ast=89.24mm2 2. It is about two to three times larger than the short-term
Minimum area of reinforcement=0.12% of X-sectional deflection.
area=(0.15x1000x150)/100=180mm2 3. The main factors that affect long term deflection are as
Choosing 8 mm & bars, A, = (n/4) x 82=50.3 mm² follows:
ii. Spacing, S=1000 Afie/Asd=1000 x 50.3/180=280 mm i. Age of concrete at the time of loading.
iii. Maximum permissible spacing = 3d or 300 mm ii. Humidity and temperature condition at the time of
whichever is smaller. Hence provide 8 mm fie bars @ curing.
250 mm c/c. iii. All other factors affecting creep and shrinkage.
Actual, Ast = (1000 x 50.3)/250=201.2 mm².
4. This type of deflection causes local damage like
4. Embedment of Reinforcement in the Support: cracking of partition walls etc.
i.In order to develop full tensile strength at the face of the D. Total Deflection: The total deflection inclusive of
short-term and long-term deflection is a quantity which beam=450mm To Find : Design of continuous two way
requires overall control. slab

Given: Effective span,lcc=6 m,Imposed load =15kN/m, 1.Note : Figure is not given in the questions.so,Assume
fck=25N/mm2,fy,415 N/mm,Width of wall = 230 mm, dimension of two ways slab is 4mx5m as shown in fig
Effective cover-50 mm 3.11.1
To Find: Design the beam and check only for deflection. 2. From fig 3.11.1. ly/lx=5/4=1.25<2
Assuming, total depth D= 500mm(l/12=6000/12=500mm i.hence this slab is a two way slab. Assuming
Width of beam, b = 250 mm l/d=25=d=4000/25=160mm
Effective depth, d= 500-50-450 mm ii. Overall depth ,D=160+20mm=180mm (cover=20mm)
1. Effective Span (l): The effective span is least of 3.Effective span :- Effective span in X-direction,lex
following: i. Centre to centre =4+0.23=4.23
i. Centre to centre of supports = 6.0 m ii. Clear span+ Effective depth=4+0.16=4.16m
ii. Clear span+d=5.77+0.45(Clear span=6.0-0.23=5.77m) iii. Similarly effective span in Y-direction ,ly=5.16m
= 6.22 m Hence, effective span, l = 6.0 m 4. Design load (w):
2. Design Load (wu) and Factored Moment (Mu): i. self weight of slab =0.18x1x25=4.5kN/m
i. Self weight of beam = 0.5 x 0.25 x 25=3.125 kN/m ii. Floor finishing load = 1x1 =1kN/m
ii. Imposed load= 15 kN/m iii. Live load =3x1=3kN/m
iii. Total load, w= 3.125+15= 18.125 kN/m iv.total load =8.5kN/m
Factored design load=w x 1.5=18.125 x 1.5 v.factored or design load =1.5x8.5=12.75kN/m.
wu=27.2 kN/m vi.Since the slab is supported on all four side and its edge
iv. Factored bending moment, Mu=wuxl2/8 is continuous.it corresponding to case-1 of IS code
=27.26^2/8=122.4kN-m 5.Moment coefficients :
3.Minimum Effective Depth Required: i.for negative moment coefficient at continuous edge,
For Fe415, xumax/d=0.48 ax=0.043+(0.047-0.043)/(1.3-1.2)x(1.25x1.2)=0.045
Ru=0.36.fck.xumax/d.(1-0.42xu.max/d) ii. For positive moment coefficient at mid span,
=0.36x25x0.48x(1-0.42x0.48) ax=0.032+(0.036-0.032)/(1.3-1.2)x(1.25-1.2)=0.034
Ru=3.45 iii.For negative moment coefficient at continuous edge
Effective depth required, ay=0.032
dreqd=√Mu/Ru.b=√122.4x10^6/3.45x250 iv. For negative moment coefficient at mid span
dreqd= 376.7 mm < 450 mm, hence OK ay=0.024
Since the depth of section is more than that required for 6.Design Moment and Shear
balanced setion. The section is designed as an under- i. Negative moment at continuous edge,
reinforced section. Mux=ax.wu.lex^2=0.045x12.75x4.16^2=9.93kN-m
AdoptD=500mmandb=250mm,d=500-20-8-20/2=462m ii. Positive moment at mid-span,
Assuming clear cover as 20 mm, 8 mm as dia of stirrups Mux=ax.wu.lex^2=0.034x12.75x4.16^2=7.5kN-m
and 20 mm dia main bars iii. Negative moment at continuous edge
4. Area of Steel Required: Muy=ay.wu.lex^2=0.032x12.75x4.16^2=7.06kN-m
For an under reinforced section the area of steel required iv.Postive moment at mid-span,
is calculated as follows: Mu=ay.wu.lex^2=0.024x12.75x4.16^2=5.3kN-m
Mu=0.87fyxAstxd(1-(fy.Ast/bd.fck) v. Maximum shear force,
122.4x10^6=-0.87x415Astx462(1- (415Ast/250x462x25) Vu=wu.lx/2=12.75x4.16/2=26.52kN
Ast.reqd=834 mm² 7. Minimum depth requires (dreqd) :
5. Minimum area of steel (As): dreqd=root(9.93x10^6/3.45x1000=53.7mm
As=0.85bd/fy=0.85x250x462/415 (Ru=3.45 for M25 and fe415)dassumed >dreq hence safe
As= 236.56mm2<834mm2,hence OK 8.Design of Main reinforcement
Using 20mm dia bars,Afie =3.14/4 x20^2=314mm2 i.Along shorter span in X-direction (middle strip)
Number of bars requires,n=Ast/Afie =834/314=2.66 say3 a. width of middle strip=(3/4)ly=(3/4)x5.16=3.87m
Hence provide 3-20mm dia bars, b. width of edge strip = (5.16-3.87)/2=0.65m
Ast= 3x314=942mm2 c. Area of reinforcement along shorter span,
6. Check for Deflection: Mu =0.87.fy.Ast.d(1-(Ast.fy/bd.fck))
Percentage of steel,Pt = 100x942/250x462 =0.815% 9.93x10^6
fs=0.58.fy.(Ast reqd/Ast provided) =0.58 x415 (834/942) =0.87x415xAstx160(1-(Astx415)/1000x160x25))
=213.1N/mm2 Ast= 173.28 mm2
Interpolating for fs=212 N/mm² and pt = 0.815% d. Minimum reinforcement,
kt=1.35-(1.35-1.2)/(240-190)x(212-190) (for Ast=0.12x1000x180/100=216mm2
fs=190,kt=1.35 and fs=240,kt=1.2) (kt=1.29) e. using 8mm fie bars,
(l/d)max=20x1.29=25.8 (l/d)provided=6000/462=12.9 spacing Sv=3.14x8^2x1000/216 =232.7mm
(l/d)max >(l/d)provided, Hence OK ii. Along Longer Span Y-direction (Middle Strip )

Given : imposed load = 3kN/m2,Surface finished


load=1kN/m2,Width of beam = 230mm,Depth of
.

You might also like