Professional Documents
Culture Documents
Revision 2
07-13-2023
50-QAIP-00030
REVISION HISTORY
REV Brief Description of Reason for Changes
2 Top left key code matrix was revised adding Exhibit W items, and added items 1.2 through 1.5 for
MOC, QSR, calibration, and storage control. Removed old 2.1 for duplicate Build it Clean storage
inspection now on 1.5.
1 Section 2.5 revised ITR naming removing testing. Section 3.4 added new testing ITR.
0 Added additional supporting specifications to 2.5. Issued for Construction
BB Corrected grammar 2.4, corrected verbiage in 3.2, changed client inspection code on 3.6.
AA Initial draft, review and issue.
Orange, Texas
Revision 2
07-13-2023
prepared by
Company QC Inspection
inspection presence. Reinforced Concrete and Corrugated
Inspect Work (I) Company Inspection requirement per Exhibit “W” Responsibility Matrix. Notification is not required, signature is required. Company signature not required for contractor to
meeting requirement
HDPE Piping Inspection and Test
BMZ QC Inspection
continue work and go to the next step, only Contractor signature is required to proceed.
Review (R): A review of documentation (auditing of data, drawings, procedures, or field installation). Signature not required.
Monitor (M): Verifying work and testing activities on an ongoing random basis. Owner signature not required. Plan
Requirement
Front Line Supervisor (FLS): Foreman (F), General Foreman (GF), Superintendent (SUP), Subcontract Manager (SCM), Project Quality Manager (PQM), Field Quality Manager (FQC),
or any designated employee that has been trained to oversee the installation or signoff of work activities.
Comments and Inspection Frequencies
Acceptance Criteria (Code, Standard, ITR Required
Activity ID No. / Activity Description
Specification, SOP, Drawing, etc.) See Note 2
Company QC Inspection
inspection presence. Reinforced Concrete and Corrugated
Inspect Work (I) Company Inspection requirement per Exhibit “W” Responsibility Matrix. Notification is not required, signature is required. Company signature not required for contractor to
meeting requirement
HDPE Piping Inspection and Test
BMZ QC Inspection
continue work and go to the next step, only Contractor signature is required to proceed.
Review (R): A review of documentation (auditing of data, drawings, procedures, or field installation). Signature not required.
Monitor (M): Verifying work and testing activities on an ongoing random basis. Owner signature not required. Plan
Requirement
Front Line Supervisor (FLS): Foreman (F), General Foreman (GF), Superintendent (SUP), Subcontract Manager (SCM), Project Quality Manager (PQM), Field Quality Manager (FQC),
or any designated employee that has been trained to oversee the installation or signoff of work activities.
Comments and Inspection Frequencies
Acceptance Criteria (Code, Standard, ITR Required
Activity ID No. / Activity Description
Specification, SOP, Drawing, etc.) See Note 2
50-QAIR-00003 Set
Reference the following ITP for
Pre-Cast Concrete
inspection details and required ITRs: Craft
2.3 Installation of precast concrete structures. Structures W M N/A This ITR is to be filled out per tag item.
Earthworks Inspection and Test Plan Foreman
Inspection Test
50-QAIP-00002
Report
50-QAIR-000041
Infiltration &
Exfiltration
Installation
Inspection Test
Manufactures Specifications, 50-STES- Project
Report This is to be filled out by Craft, either per work package
2.4 Joint assembly per manufacturer requirements. 00003, PIP STS03001, PIP STS03600 Quality M M N/A
Or as applicable.
& PIP STS03601 Manager
50-QAIR-00048
HDPE Corrugated
Pipe Installation
Inspection Test
Report
Project See: 50-QAIP-00002 Earthworks Inspection and Test
2.5 Ensure installation of flowfill is per the Project 50-QAIP-00002 Earthworks Inspection
N/A Quality H M N/A Plan for hold points and the required Inspection and Test
specifications. and Test Plan
Manager Reports
3.0 Pipe Joint Testing Activities:
Concrete or cement components will absorb water, so the
Supplier shall fill the system and let it stand for a
minimum of 4 hours to a maximum 72 hours before
topping off and testing. All couplings, bells, joints, etc.,
shall remain exposed (for observation during exfiltration
2.6 Testing of process and sanitary sewers, catch basins and Infiltration & Exfiltration Testing Piping Test Project testing).
sumps shall be in accordance with the project per ASTM C969 Package Quality H W N/A
specification(s). Manager Measure the leakage loss over a timed test period. The
minimum test period shall be 4 hours and the maximum
shall not exceed 24 hours. If the measured rate of
leakage is less than or equal to the allowable leakage in
accordance with 8.2 of ASTM C969, the section of sewer
tested is acceptable.
Company QC Inspection
inspection presence. Reinforced Concrete and Corrugated
Inspect Work (I) Company Inspection requirement per Exhibit “W” Responsibility Matrix. Notification is not required, signature is required. Company signature not required for contractor to
meeting requirement
HDPE Piping Inspection and Test
BMZ QC Inspection
continue work and go to the next step, only Contractor signature is required to proceed.
Review (R): A review of documentation (auditing of data, drawings, procedures, or field installation). Signature not required.
Monitor (M): Verifying work and testing activities on an ongoing random basis. Owner signature not required. Plan
Requirement
Front Line Supervisor (FLS): Foreman (F), General Foreman (GF), Superintendent (SUP), Subcontract Manager (SCM), Project Quality Manager (PQM), Field Quality Manager (FQC),
or any designated employee that has been trained to oversee the installation or signoff of work activities.
Comments and Inspection Frequencies
Acceptance Criteria (Code, Standard, ITR Required
Activity ID No. / Activity Description
Specification, SOP, Drawing, etc.) See Note 2
Company QC Inspection
inspection presence. Reinforced Concrete and Corrugated
Inspect Work (I) Company Inspection requirement per Exhibit “W” Responsibility Matrix. Notification is not required, signature is required. Company signature not required for contractor to
meeting requirement
HDPE Piping Inspection and Test
BMZ QC Inspection
continue work and go to the next step, only Contractor signature is required to proceed.
Review (R): A review of documentation (auditing of data, drawings, procedures, or field installation). Signature not required.
Monitor (M): Verifying work and testing activities on an ongoing random basis. Owner signature not required. Plan
Requirement
Front Line Supervisor (FLS): Foreman (F), General Foreman (GF), Superintendent (SUP), Subcontract Manager (SCM), Project Quality Manager (PQM), Field Quality Manager (FQC),
or any designated employee that has been trained to oversee the installation or signoff of work activities.
Comments and Inspection Frequencies
Acceptance Criteria (Code, Standard, ITR Required
Activity ID No. / Activity Description
Specification, SOP, Drawing, etc.) See Note 2