COMMENTS RESOLUTION FORM

Project Name: Design & Build Data Centers -Tier III- in Riyadh & Jeddah”
Project Code : 068/2022
DCRJ-RIY3-MAT-EL-014 DCRJ-RIY3-MS FOR ACCESS CONTROL SYSTEM-01-231129

New Submittal Resubmittal Date: 30-Nov-23 Revision No. 01


Architectural Structural Electrical Mechanical General

Materials Calculations Design Document Sample

Submitted by: Contractor MMR Recived by: Consultant- EGEC

30-Nov-23
Project Engineer Project Manager Date Name Signature Date

Item No. Document Subject Details Remarks

1 MATERIAL SUBMITTAL MS FOR ACCESS CONTROL SYSTEM FOR ACCESS CONTROL

Contractor Highlights

Document / Drawing No. / Document/DrawingTitle Relevant Comments Initial Responded Revised


No. Stage REV. Mobily/ EGEC Comments
Section/ Page Discipline made by Status Originator Response By Status
1. MMR shall follow Mobily vendor list As per our meeting , all CCTV and Access
MS FOR ACCESS CONTROL
1 M.S DCRJ-RIY3-MAT-EL-014 00 ELE EGEC D door system materials are part of
SYSTEM
approved Vendors
MS FOR ACCESS CONTROL 2. Compliance with Mobily specification is missed.
2 M.S DCRJ-RIY3-MAT-EL-014 00 ELE EGEC D Done as part of approved Vendor list
SYSTEM
MS FOR ACCESS CONTROL 3. Access Control system material submittal shall be
3 M.S DCRJ-RIY3-MAT-EL-014 00 prepared and stamped from vendor ELE EGEC D As attached
SYSTEM
4. Schematic drawings are not defining the complete
MS FOR ACCESS CONTROL system, Approved detailed design drawings shall be
4 M.S DCRJ-RIY3-MAT-EL-014 00 ELE EGEC D To be submitted as part of shop drawing
SYSTEM submitted.

5. Access Control system material submittal shall include:


Company profile & brochure, company documents, tests
certificates and reports, warranty certificates, previous As per our meeting , all CCTV and Access
MS FOR ACCESS CONTROL
5 M.S DCRJ-RIY3-MAT-EL-014 00 projects approvals and pre-qualifications,ISO certificates, ELE EGEC D door system materials are part of
SYSTEM
certificate of origin, manufacturer recommendations for approved Vendors
installations.

6. Data sheet shall be complete, there are many devices


MS FOR ACCESS CONTROL missed such as Access control panel, card readera, push
6 M.S DCRJ-RIY3-MAT-EL-014 00 button, wheather proof devices, Xray detection, Metal ELE EGEC D Please refer to updated materials
SYSTEM
detector, Turn style, servers…etc.

MS FOR ACCESS CONTROL 7. Method of statement for access control system shall be
7 M.S DCRJ-RIY3-MAT-EL-014 00 submitted. ELE EGEC D To be submitted as part of shop drawing
SYSTEM
8. Warrenty shall starts after integration and handing over,
MS FOR ACCESS CONTROL
8 M.S DCRJ-RIY3-MAT-EL-014 00 that is from contract completion date. ELE EGEC D Comply
SYSTEM

Consultant Engineer Project Manager Date

Approval Code Legend

A Approved
B Approved with comments
C Resubmit as Noted
D Rejected

File: DCRJ-RIY3-MS FOR ACCESS CONTROL SYSTEM-01-231129 1 11/29/2023