Professional Documents
Culture Documents
Assignment-1
Braja M. Das
Q1. From Advanced Soil Mechanics, 3rd Edition, Braja Das (Solve Problem 6.4, 6.6,
6.7, 6.8, 6.9, 6.10, 6.14)
6.4. A25 cm total consolidation settlement of the two clay layers shown in Figure P6.1is expected owing
to the application of the uniform surcharge q. Find the duration after the load application at which 12.5
cm of total settlement would take place.
Given
2-clay layer
ST = 25 cm,
Sd = 12.5 cm
Cv1 = 0.13cm2/min
Cv2 = 0.13cm2/min
Solution
Settlement = Uav*ST
12.5 = Uav*25
12.5
Uav= x100
25
Uav= 0.5x100≈ 50%
π Uav% 2
From Terzaghi's suggested that for Uav = 0-50%, Tv= 4( )
100
π 50 3+1.5
Tv = 4(100)2 = 0.1963 , H = =2.25m
2
𝐶𝑣𝑡𝑐 Tv(H/2)2 0.1963x(225cm)2
Tv=(𝐻/2)2, ∴ t = =
𝐶𝑣 (0.13cm2/min)
t = 76463.04min = 1274.38 hours
= 53.1 days…………………… (ANSWER)
6.6. Due to a certain loading condition, the initial excess pore water pressure distribution in a 4-m-thick
clay layer is shown in Figure P6.2. Given that Cv=0.3mm2/s, determine the degree of consolidation after
100 days of load application.
A2
A1
Given
Solution
𝑚𝑚2
𝐶𝑣𝑡 (0.3( )𝑥100𝑥24𝑥60𝑥60)
TV = (H/2)2 = 𝑠 ⁄ = 0.648
(2000)2
∴ Tv = 0.648
A1 = 100KN/m2 x 4m = 400KN/m
4 𝜋𝑧
A2 = ∑𝑧=4
𝑧=0 ∫0 80 sin 4 dz
4 𝜋𝑧 4 320
= 80x𝜋 (-cos 4 ) = (1+1) = 203.72 KN/m
0 𝜋
For A1, Tv= 0.648 from table 6.1 --------> Uav1 = 83.6% (Constant ui)
For A2, Tv= 0.648 from table 6.1 --------> Uav2 = 79.8% (Sinusoidal ui)
6.7 A uniform surcharge of 96kN/m2 is applied at the ground surface of a soil profile, as shown in Figure
below. Determine the distribution of the excess pore water pressure in the 3m thick clay layer after 1 year
of load application. Use the numerical method of calculation given in Sec. 6.4. Also calculate the average
degree of consolidation at that time using the above results.
Given
Let zR = 3m and UR = 0.96
3 𝑈 96 zR 1
So z̅ =3 = 1, U̅ = UR =0.96 = 100, and∆z̅ = = 3 = 0.333
z̅
Cv=9.3 x 103 cm2/yr
Let ∆t = 0.25 yr
Solution
1
(∆z̅)2= 3= 0.333 (∆zR)2
Cv∆t (9.3𝑥(10)3 c𝑚2𝑥0.25𝑦𝑟
∆t̅ = = = 0.0258
(zR)2 (300)2
∆ t̅ 0.0258
= = 0.233< 0.5 ……..ok!!!
(∆z̅ )2 (0.333 )2
For t = 0.25yr
At z̅ = 0, U̅0,t̅ +∆t = 0
∆𝑡
At z̅ = 0.333, U̅0,t̅ +∆t = (U̅1,t+ U̅3,t -2U̅0,t)+ U̅0,t = 0.233(0+100-2(100)) +100 = 76.7
(∆zR)2
∆𝑡
At z̅ = 0.666, U̅0,t̅ +∆t = (U̅1,t+ U̅3,t -2U̅0,t)+ U̅0,t = 0.233(100+0-2(100)) +100 = 76.7
(∆zR)2
At z̅ = 1.0, U̅0,t̅ +∆t = 0
For t = 0.5yr
At z̅ = 0, U̅0,t̅ +∆t = 0
∆𝑡
At z̅ = 0.333, U̅0,t̅ +∆t = (U̅1,t+ U̅3,t -2U̅0,t)+ U̅0,t = 0.233(0+76.7-2(76.7)) +76.7 = 58.83
(∆zR)2
∆𝑡
At z̅ = 0.666, U̅0,t̅ +∆t = (U̅1,t+ U̅3,t -2U̅0,t)+ U̅0,t = 0.233(76.7+0-2(76.7)) +76.7 = 58.83
(∆zR)2
At z̅ = 1.0, U̅0,t̅ +∆t = 0
For t = 0.75yr
At z̅ = 0, U̅0,t̅ +∆t = 0
∆𝑡
At z̅ = 0.333, U̅0,t̅ +∆t = (U̅1,t+ U̅3,t -2U̅0,t)+ U̅0,t = 0.233(0+58.83-2(58.83)) +58.83 = 45.12
(∆zR)2
∆𝑡
At z̅ = 0.666, U̅0,t̅ +∆t = (U̅1,t+ U̅3,t -2U̅0,t)+ U̅0,t = 0.233(58.83+0-2(58.83)) +58.83 = 45.12
(∆zR)2
At z̅ = 1.0, U̅0,t̅ +∆t = 0
For t = 1.0yr
At z̅ = 0, U̅0,t̅ +∆t = 0
∆𝑡
At z̅ = 0.333, U̅0,t̅ +∆t = (∆zR)2 (U̅1,t+ U̅3,t -2U̅0,t)+ U̅0,t = 0.233(0+45.12-2(45.12)) +45.12 = 34.61
∆𝑡
At z̅ = 0.666, U̅0,t̅ +∆t = (∆zR)2 (U̅1,t+ U̅3,t -2U̅0,t)+ U̅0,t = 0.233(45.12+0-2(45.12)) +45.12 = 34.61
At z̅ = 1.0, U̅0,t̅ +∆t = 0
6.8 A two-layered soil is shown in Figure below. At a given time t = 0, a uniform load was applied at the
ground surface so as to increase the pore water pressure by 60kN/m2 at all depths. Divide the soil profile
into six equal layers. Using the numerical analysis method, find the excess pore water pressure at depths
of−3m, 6m,9m, 12m,15m, and −18m at t = 25 days. Use t = 5 days.
Given
Solution
For layer - 1
Cv∆t 1.1cm2/daysx5days
∆ t̅ (1) = = = 1.698x10-6
(zR)2 (1800)2
∆ t̅ 1.698x10−6
= = 6.088x10-5< 0.5 ……..ok!!!
(∆z̅ )2 (0.167)2
For layer - 2
Cv∆t 4.4cm2/days∗5days
∆ t̅ (1) =
(zR)2
= (1800)2
= 6.79x10-6
∆ t̅ 6.79x10−6
= = 2.435x10-4< 0.5 ……..ok!!!
(∆z̅ )2 (0.167)2
For t = 5days
At z̅ = 0, U̅0,t̅ +∆t = 0
∆𝑡
At z̅ = 0.167, U̅0,t̅ +∆t = (∆zR)2 (U̅1,t+ U̅3,t -2U̅0,t)+ U̅0,t = 6.088x10-5(0+100-2(100))+100 = 99.99
∆𝑡
At z̅ = 0.333, U̅0,t̅ +∆t = (U̅1,t+ U̅3,t -2U̅0,t)+ U̅0,t = 6.088x10-5(100+100-2(100)) +100 = 100
(∆zR)2
∆𝑡
At z̅ = 0.5, U̅0,t̅ +∆t = (∆zR)2 (U̅1,t+ U̅3,t -2U̅0,t)+ U̅0,t =2.435x10-4(100+100-2(100))+100 = 100
∆𝑡
At z̅ = 0.667, U̅0,t̅ +∆t = (U̅1,t+ U̅3,t -2U̅0,t)+ U̅0,t = 6.088x10-5 (100+100-2(100)) +100 = 100
(∆zR)2
∆𝑡
At z̅ = 0.834, U̅0,t̅ +∆t = (U̅1,t+ U̅3,t -2U̅0,t)+ U̅0,t = 6.088x10-5 (100+0-2(100)) +100 = 99.99
(∆zR)2
At z̅ = 1.0, U̅0,t̅ +∆t = 0
For t = 10 days
At z̅ = 0, U̅0,t̅ +∆t = 0
∆𝑡
At z̅ = 0.167, U̅0,t̅ +∆t = (U̅1,t+ U̅3,t -2U̅0,t)+ U̅0,t = 6.088x10-5x(0+100-2(99.99)) +99.99 = 99.99
(∆zR)2
∆𝑡
At z̅ = 0.333, U̅0,t̅ +∆t = (U̅1,t+ U̅3,t -2U̅0,t)+ U̅0,t = 6.088x10-5 x (99.99+100-2(100)) +100 = 100
(∆zR)2
∆𝑡
At z̅ = 0.5, U̅0,t̅ +∆t = (U̅1,t+ U̅3,t -2U̅0,t)+ U̅0,t = 2.435x10-4x (100+100-2(100)) +100 = 100
(∆zR)2
∆𝑡
At z̅ = 0.667, U̅0,t̅ +∆t = (U̅1,t+ U̅3,t -2U̅0,t)+ U̅0,t = 2.435x10-4x (100+99.99-2(100)) +100 = 100
(∆zR)2
∆𝑡
At z̅ = 0.834, U̅0,t̅ +∆t = (U̅1,t+ U̅3,t -2U̅0,t)+U̅0,t = 2.435x10-4x (99.99+100-2(99.99))+99.99 = 99.81
(∆zR)2
At z̅ = 1.0, U̅0,t̅ +∆t = 0
For t = 15 days
At z̅ = 0, U̅0,t̅ +∆t = 0
∆𝑡
At z̅ = 0.167, U̅0,t̅ +∆t = (U̅1,t+ U̅3,t -2U̅0,t)+ U̅0,t = 6.088x10-5x(0+100-2(99.99)) +99.99 = 99.99
(∆zR)2
∆𝑡
At z̅ = 0.333, U̅0,t̅ +∆t = (U̅1,t+ U̅3,t -2U̅0,t)+ U̅0,t = 6.088x10-5 x (99.99+100-2(100)) +100 = 100
(∆zR)2
∆𝑡
At z̅ = 0.5, U̅0,t̅ +∆t = (U̅1,t+ U̅3,t -2U̅0,t)+ U̅0,t = 2.435x10-4x (100+100-2(100)) +100 = 100
(∆zR)2
∆𝑡
At z̅ = 0.667, U̅0,t̅ +∆t = (U̅1,t+ U̅3,t -2U̅0,t)+ U̅0,t = 2.435x10-4x (100+99.99-2(100)) +100 = 100
(∆zR)2
∆𝑡
At z̅ = 0.834, U̅0,t̅ +∆t = (U̅1,t+ U̅3,t -2U̅0,t)+U̅0,t = 2.435x10-4 x(99.99+100-2(99.99))+99.99 = 99.81
(∆zR)2
At z̅ = 1.0, U̅0,t̅ +∆t = 0
For t = 20 days
At z̅ = 0, U̅0,t̅ +∆t = 0
∆𝑡
At z̅ = 0.167, U̅0,t̅ +∆t = (U̅1,t+ U̅3,t -2U̅0,t)+ U̅0,t = 6.088x10-5 x (0+100-2(99.99)) +99.99 = 99.99
(∆zR)2
∆𝑡
At z̅ = 0.333, U̅0,t̅ +∆t = (U̅1,t+ U̅3,t -2U̅0,t)+ U̅0,t = 6.088x10-5 x (99.99+100-2(100)) +100 = 100
(∆zR)2
∆𝑡
At z̅ = 0.5, U̅0,t̅ +∆t = (U̅1,t+ U̅3,t -2U̅0,t)+ U̅0,t = 2.435x10-4x (100+100-2(100)) +100 = 100
(∆zR)2
∆𝑡
At z̅ = 0.667, U̅0,t̅ +∆t = (U̅1,t+ U̅3,t -2U̅0,t)+ U̅0,t = 2.435x10-4x (100+99.99-2(100)) +100 = 100
(∆zR)2
∆𝑡
At z̅ = 0.834, U̅0,t̅ +∆t= (U̅1,t+ U̅3,t -2U̅0,t)+ U̅0,t = 2.435x10-4 x(99.99+100-2(99.99))+99.99 = 99.81
(∆zR)2
At z̅ = 1.0, U̅0,t̅ +∆t = 0
For t = 25 days
At z̅ = 0, U̅0,t̅ +∆t = 0
∆𝑡
At z̅ = 0.167, U̅0,t̅ +∆t = (U̅1,t+ U̅3,t -2U̅0,t)+ U̅0,t = 6.088x10-5 x (0+100-2(99.99)) +99.99 = 99.99
(∆zR)2
∆𝑡
At z̅ = 0.333, U̅0,t̅ +∆t = (U̅1,t+ U̅3,t -2U̅0,t)+ U̅0,t = 6.088x10-5 x (99.99+100-2(100)) +100 = 100
(∆zR)2
∆𝑡
At z̅ = 0.5, U̅0,t̅ +∆t = (U̅1,t+ U̅3,t -2U̅0,t)+ U̅0,t = 2.435x10-4x (100+100-2(100)) +100 = 100
(∆zR)2
∆𝑡
At z̅ = 0.667, U̅0,t̅ +∆t = (U̅1,t+ U̅3,t -2U̅0,t)+ U̅0,t = 2.435x10-4x (100+99.99-2(100)) +100 = 100
(∆zR)2
∆𝑡
At z̅ = 0.834, U̅0,t̅ +∆t= (U̅1,t+ U̅3,t -2U̅0,t)+ U̅0,t = 2.435x10-4 x(99.99+100-2(99.99))+99.99 = 99.81
(∆zR)2
At z̅ = 1.0, U̅0,t̅ +∆t = 0
6.9. Refer to Figure below. A uniform surcharge q is applied at the ground surface. The variation of q
with time is shown in Figure P6.5b. Divide the 10-m-thick clay layer into five layers, each 2m thick.
Determine the excess pore water pressure in the clay layer at t = 60 days by the numerical method.
Solution
Cv∆t
Let ∆z = 2m and ∆t = 10days ∆t̅ = = 2*10-210/102 = 0.002
(rR)2
∆z̅ = 2/10 = 0.2. ………. ∆t̅ /∆z̅2 = 0.02/0.22 = 0.05 < 0.5 ……………….. OK!!
For t = 10 days
At z = 0, U̅0,t̅ +∆t = 0
∆𝑡
At z = 2m, U̅0,t̅ +∆t = (U̅1,t+ U̅3,t -2U̅0,t)+ U̅0,t = 0.05x(0+110-2(110)) +110 = 104.5
(∆zR)2
∆𝑡
At z = 4m, U̅0,t̅ +∆t = (U̅1,t+ U̅3,t -2U̅0,t)+ U̅0,t = 0.05 x (110+110-2(110)) +110 = 110
(∆zR)2
∆𝑡
At z = 6m, U̅0,t̅ +∆t = (U̅1,t+ U̅3,t -2U̅0,t)+ U̅0,t = 0.05x (110+110-2(110)) +110 = 110
(∆zR)2
∆𝑡
At z = 8m, U̅0,t̅ +∆t = (U̅1,t+ U̅3,t -2U̅0,t)+ U̅0,t = 0.05x (110+0-2(110)) +110 = 104.5
(∆zR)2
At z̅ = 10m, U̅0,t̅ +∆t = 0
At z = 0, U̅0,t̅ +∆t = 0
∆𝑡
At z = 2m, U̅0,t̅ +∆t = (U̅1,t+ U̅3,t -2U̅0,t)+ U̅0,t = 0.05x(0+110-2(104.5)) +104.5 = 99.55
(∆zR)2
U̅0,t̅ +∆t = 99.55 + 26.67 = 126.22
∆𝑡
At z = 4m, U̅0,t̅ +∆t = (U̅1,t+ U̅3,t -2U̅0,t)+ U̅0,t = 0.05 x (104.5+110-2(110)) +110 = 109.72
(∆zR)2
U̅0,t̅ +∆t = 109.72 + 26.67 = 136.40
∆𝑡
At z = 6m, U̅0,t̅ +∆t = (U̅1,t+ U̅3,t -2U̅0,t)+ U̅0,t = 0.05x (104.5+110-2(110)) +110 = 109.72
(∆zR)2
U̅0,t̅ +∆t = 109.72 + 26.67 = 136.4
∆𝑡
At z = 8m, U̅0,t̅ +∆t = (U̅1,t+ U̅3,t -2U̅0,t)+ U̅0,t = 0.05x (110+0-2(104.5)) +104.5 = 99.55
(∆zR)2
U̅0,t̅ +∆t = 99.55 + 26.67 = 126.22
At z̅ = 10m, U̅0,t̅ +∆t = 0
At z = 0, U̅0,t̅ +∆t = 0
∆𝑡
At z = 2m, U̅0,t̅ +∆t = (U̅1,t+ U̅3,t -2U̅0,t)+ U̅0,t = 0.05x(0+136.4-2(126.22)) +126.22 = 120.42
(∆zR)2
U̅0,t̅ +∆t = 120.42 + 13.33 = 133.75
∆𝑡
At z = 4m, U̅0,t̅ +∆t = (U̅1,t+ U̅3,t -2U̅0,t)+ U̅0,t = 0.05 x (126.22+136.4-2(136.4)) + 136.4 = 135.89
(∆zR)2
U̅0,t̅ +∆t = 135.89 + 13.33 = 149.21
∆𝑡
At z = 6m, U̅0,t̅ +∆t = (U̅1,t+ U̅3,t -2U̅0,t)+ U̅0,t = 0.05x (136.4+126.22-2(136.4)) +136.4 = 135.89
(∆zR)2
U̅0,t̅ +∆t = 135.89 + 13.33 = 149.21
∆𝑡
At z = 8m, U̅0,t̅ +∆t = (U̅1,t+ U̅3,t -2U̅0,t)+ U̅0,t = 0.05x (136.4+0-2(126.22)) +126.22 = 120.42
(∆zR)2
U̅0,t̅ +∆t = 120.42 + 13.33 = 133.75
At z̅ = 10m, U̅0,t̅ +∆t = 0
At z = 0, U̅0,t̅ +∆t = 0
∆𝑡
At z = 2m, U̅0,t̅ +∆t = (U̅1,t+ U̅3,t -2U̅0,t)+ U̅0,t = 0.05x(0+149.21-2(133.75)) +133.75 = 127.84
(∆zR)2
U̅0,t̅ +∆t = 127.84 + 6.67 = 134.51
∆𝑡
At z = 4m, U̅0,t̅ +∆t= (U̅1,t+ U̅3,t -2U̅0,t)+ U̅0,t = 0.05x(133.75+133.75-2(149.21)) + 149.21 = 148.45
(∆zR)2
U̅0,t̅ +∆t = 148.45 + 6.67 = 155.12
∆𝑡
At z = 6m, U̅0,t̅ +∆t= (U̅1,t+ U̅3,t -2U̅0,t)+ U̅0,t = 0.05x(133.75+133.75-2(149.21)) + 149.21 = 148.45
(∆zR)2
For t = 50 days
At z = 0, U̅0,t̅ +∆t = 0
∆𝑡
At z = 2m, U̅0,t̅ +∆t = (U̅1,t+ U̅3,t -2U̅0,t)+ U̅0,t = 0.05x(0+155.12-2(134.51)) +134.51 = 128.81
(∆zR)2
∆𝑡
At z = 4m, U̅0,t̅ +∆t = (U̅1,t+ U̅3,t -2U̅0,t)+ U̅0,t = 0.05x(134.51+155.12-2(155.12))+155.12 = 154.01
(∆zR)2
∆𝑡
At z = 6m, U̅0,t̅ +∆t = (U̅1,t+ U̅3,t -2U̅0,t)+U̅0,t = 0.05x(155.12+134.51-2(155.12))+155.12 = 154.01
(∆zR)2
∆𝑡
At z = 8m, U̅0,t̅ +∆t = (U̅1,t+ U̅3,t -2U̅0,t)+ U̅0,t = 0.05x (155.12+0-2(134.51)) +134.51 = 128.81
(∆zR)2
At z̅ = 10m, U̅0,t̅ +∆t = 0
For t = 50 days
At z = 0, U̅0,t̅ +∆t = 0
∆𝑡
At z = 2m, U̅0,t̅ +∆t = (U̅1,t+ U̅3,t -2U̅0,t)+ U̅0,t = 0.05x(0+154.01-2(128.81)) +128.81 = 123.63
(∆zR)2
∆𝑡
At z = 4m, U̅0,t̅ +∆t = (U̅1,t+ U̅3,t -2U̅0,t)+ U̅0,t = 0.05x(128.81+154.01-2(154.01))+154.01 = 152.83
(∆zR)2
∆𝑡
At z = 6m, U̅0,t̅ +∆t = (U̅1,t+ U̅3,t -2U̅0,t)+U̅0,t = 0.05x(154.01+128.81-2(154.01))+154.01 = 152.83
(∆zR)2
∆𝑡
At z = 8m, U̅0,t̅ +∆t = (U̅1,t+ U̅3,t -2U̅0,t)+ U̅0,t = 0.05x (154.01+0-2(128.81)) +128.81 = 123.63
(∆zR)2
At z̅ = 10m, U̅0,t̅ +∆t = 0
6.10 Refer to Figure below. The uniform surcharge is time dependent. Given q (kN/m2)=2t (days)(for t≤
100 days), and q = 200kN/m2 (for t≥ 100 days), determine the average degree of consolidation for the
clay layer at t = 50 days and t= 1 year. Use Figure 6.8c.
Given
Required
Solution
𝐶𝑣𝑡𝑐
Tc = (H)2 = 0.02*100/102 = 0.02
Uav @ t = 50 days
𝐶𝑣𝑡
Tv = (H)2 = 0.02*50/102 = 0.01
From fig 6.8c for Tc = 0.02 and Tv = 0.01, Uav = 8% …..……………… (ANSWER)
Uav @ t = 1 years
𝐶𝑣𝑡
Tv = (H)2 = 0.02*365/102 = 0.073
From fig 6.8c for Tc = 0.02 and Tv = 0.073, Uav = 25%…..……………… (ANSWER)
Q2. The results of laboratory consolidation test on a clay sample are given below:
Draw
a. An e-log p plot
b. Determine the pre-consolidation pressure, pc
c. Find the compression index, Cc
Solution
a) An e-log p plot
Therefore, from the above table chart 𝛔’c ≈ 150 KN/m2 …..……………… (ANSWER)
From the above table, we have e1, e2, ’1, ’2…. Hence Cc is computed below as:
Δe (e1−e2) (0.90−0.78)
Cc = 𝜎2 = 𝜎2 = 520 = 0.5 …..……………… (ANSWER)
log( ) log( ) log( )
𝜎1 𝜎1 300
Q3. From Advanced Soil Mechanics, 3rd Edition, Braja Das (Solve Problem 8.3, 8.4,
8.7, 8.8, 8.9)
8.4. A rectangular foundation is shown in Figure below, given B = 2m_ L= 4m q = 240kN/m2_ H = 6m,
and Df= 2m.
(a) Assuming E = 3800KN/m2, calculate the average elastic settlement. Use Eq. (8.24).
(b) If the clay is normally consolidated, calculate the consolidation settlement.
Use Eq. (8.35) and sat = 17.5kN/m3, Cc = 0.12, and e0 = 1.1.
Given
Solution
240KN/m2x2m
Se(average)= 0.7x0.95x = 0.084m = 8.4cm …..……………… (ANSWER)
3800KN/m2
0.0928x6
Sc = = 0.265m = 26.5cm …..……………… (ANSWER)
1+1.1
8.7. A permanent surcharge of 100kN/m2 is to be applied on the ground surface of the soil profile shown
in Figure P8.3. It is required to eliminate all of the primary consolidation in 3 months. Estimate the total
surcharge 𝜎 = 𝜎s + 𝜎f needed to achieve the goal.
Given
Solution
tCv
Tv = H2
T 30𝑥3𝑥24𝑥60𝑥13𝑥10−3
v= = 0.7488
(150)2
From fig 8.3 for Tv=0.7488 and U(f+s) ≈0.78
σ’0= 17.3(1.5) + 1.5(19.5-9.81) + 1.5(17.3-9.81) = 51.72 KN/m2
σf 100
= = 1.933
σ’0 51.72
σf σs
From fig 8.25 for U (f+s) ≈0.78 and = 1.93 we get = 0.65
σ’0 σf
∴ σs = 0.65x 𝜎f= 0.65 x 100 = 65 KN/m2
σ = σs + σf = 100+65 = 165 KN/m2 …..……………… (ANSWER)
Q4. It is proposed to construct an overhead tank on a raft foundation of size 8 x 16 m with the
foundation at a depth of 2m below ground level. The subsoil at the site is stiff homogeneous clay
with the water table at the base of the foundation the subsoil is divided into 3 layers and the
properties of each layer are shown given in figure below. Estimate the consolidation settlement
by the Skempton-Bjerrun Method.
Given
Solution
Layer Log
Hi (m) Po(KN/m2) P(KN/m2) Cc eo Soed(cm)
No
1 5 58.725 123.22 0.18 0.85 0.0973 0.491 0.23
2 6 108.92 58.25 0.16 0.73 0.0925 0.186 0.103
3 5 163.62 39.175 0.13 0.68 0.0773 1.242 0.48
0.813
For H/B = 16/8 = 2, A = 0.72 using this value, from settlement coefficient versus pore pressure
coefficient chart we get 𝛽 = 0.8
Using the following equation fill the table for each layers
1
σb = 150(1- b )=
[( )2+1]3/2
z
1
σav= 6 (∆σt + 4∆σm + σb)
Cc Po+∆p
Soe = Hi Log
1+eo Po
Q5. A footing of size 10x10 m is founded at a depth of 2.5 m below ground level on sand
deposit. The water table is at the base of the foundation. The saturated unit weight of soil from
ground level to a depth of 22.5 m is 20 KN/m3. The compressible stratum of 20 m below the
foundation base is divided into three layers with corrected SPT values (N) and CPT values (qc)
constant in each layer as given below
From To
1 0 5 20 8
2 5 11 25 10
3 11 20 30 12
Assume the net contact pressure at the base of the foundation is equal to 70 KPa and t= 10 years
Solution
𝛾s=20KN/m2
0
s =20KN/m2
2.5
11
20
qn = 70 Kpa
4
B/2=5
6
10
12
14
16
18
2B= 20
0 0.1 0.2 0.3 0.4 0.5 0.6
𝑞0 2.5𝑥20
C1 = 1- 0.5 qn = 1- 0.5 = 0.643
70
𝑡 10
C2 = 1+0.2log0.1 = 1+0.2log0.1 = 1.4
𝐼𝑧∆𝑧
Layer No ∆z(cm) q(mpa) Es(mpa) Iz (av)
𝐸𝑠
1 5 8 32 0.35 0.0547
2 6 10 40 0.55 0.0825
3 9 12 44 0.45 0.0921
Total 0.229m
I ∆z
Se = C1C2qn ∑ zE = 0.643x1.4x0.07x22.9 = 1.443cm = 14.43mm …..……………… (ANSWER)
s
Q6. Square rigid footing of size 10x10m is founded at a depth of 2m below ground level. The
type of strata met at the site is
The water table is at the base level of the foundation. The saturated unit weight of soil above the
foundation base is 20 KN/m3. The coefficient of volume compressibility of clay, mv, is
0.0001m2/KN, and the coefficient of consolidation Cv is 1 m2/year. The total contact pressure qn
= 100KN/m2.
Given
Assignment-2
Mid Exam
Q1. Explain in detail the components of settlement and different methods to determine
settlements. Choose the best method for clay soils.
Components of settlement
Immediate Settlement: Occurs immediately after the construction. This is computed using elasticity
theory (Important for Granular soil)
Primary Consolidation: Due to gradual dissipation of pore pressure induced by external loading and
consequently expulsion of water from the soil mass, hence volume change.
(Important for Inorganic clays)
Secondary Consolidation: Occurs at constant effective stress with volume change due to rearrangement
of particles. (Important for Organic soils)
A. Immediate settlement
I. Elastic settlement: H H
s x s y dz
1
Se z dz z
0
Es 0
II. Strain Influence Factor Method for Sandy Soil: Schmertmann and Hartman (1978):
z2
Se C1C2 q D f
Iz
z
0 Es
III. Burland and Burbidges method for sandy soils:
Q2. Derive the basic differential equation for one dimensional consolidation which was
developed by Terzaghi's (1943)? Use all necessary steps
Solution
𝜕𝑣
Rate of change of volume of soil element is =(𝑞𝑧 + 𝑑𝑞𝑧 ) − 𝑞𝑧 = 𝜕𝑡
where 𝑣 = 𝑑𝑥 𝑑𝑦 𝑑𝑧
𝜕ℎ 𝜕2 ℎ 𝜕ℎ
Therefore (𝑞𝑧 + 𝑑𝑞𝑧 ) − 𝑞𝑧 = 𝑘 (𝜕𝑧 + 𝜕𝑧 2 𝑑𝑧 ) 𝑑𝑥 𝑑𝑦 − 𝑘 𝜕𝑧 𝑑𝑥 𝑑𝑦
𝜕𝑣 𝜕2 ℎ 𝑢
= 𝑘 𝜕𝑧 2
, but h- is pressure head = then
𝜕𝑡 𝛾𝑤
𝜕𝑣 𝜕2 𝑢 𝜕𝑣 𝜕𝑣𝑣
= 𝑘𝛾 𝜕𝑧 2
𝑑𝑥 𝑑𝑦 𝑑𝑧 , but during one dimensional consolidation or compressibility of soil, = ,
𝜕𝑡 𝑤 𝜕𝑡 𝜕𝑡
𝑣
but 𝑣𝑣 = 𝑣𝑠 𝑒 𝑎𝑛𝑑 𝑣𝑠 =
1+𝑒
𝜕𝑣𝑣 𝜕2 𝑢
= 𝑘 𝑑 𝑑 𝑑
𝜕𝑡 𝛾𝑤 𝜕𝑧2 𝑥 𝑦 𝑧
𝑣 𝜕𝑒 𝑘 𝜕2 𝑈
= 𝑑 𝑑 𝑑 but 𝑣 = 𝑑𝑥 𝑑𝑦 𝑑𝑧
1+𝑒 𝜕𝑡 𝛾𝑤 𝜕𝑧 2 𝑥 𝑦 𝑧
𝑑𝑥 𝑑𝑦 𝑑𝑧 𝜕𝑒 𝑘 𝜕2 𝑈
= 𝑑 𝑑 𝑑
1+𝑒 𝜕𝑡 𝛾 𝜕𝑧 2 𝑥 𝑦 𝑧
𝑤
1 𝜕𝑒 𝑘 𝜕2 𝑈
= 𝑏𝑢𝑡 𝜕𝑒 = −𝑎𝑣 𝜕(∆𝜎 ′ ) 𝑤ℎ𝑒𝑟𝑒 ∆𝜎 ′ = 𝑢
1+𝑒 𝜕𝑡 𝛾𝑤 𝜕𝑧 2
𝑎𝑣 𝜕𝑢 𝑘 𝜕2 𝑈 𝑎𝑣
= 𝑙𝑒𝑡 = 𝑚𝑣 then
1+𝑒 𝜕𝑡 𝛾𝑤 𝜕𝑧 2 1+𝑒
𝑘 𝜕2 𝑈 𝜕𝑢 𝜕𝑢 𝑘 𝜕2 𝑈 𝑘
= 𝑚𝑣 ↔ = but 𝑐𝑣 = then substitute 𝑐𝑣 in equation
𝛾𝑤 𝜕𝑧 2 𝜕𝑡 𝜕𝑡 𝑚𝑣 𝛾𝑤 𝜕𝑧 2 𝑚𝑣 𝛾𝑤
𝝏𝒖 𝝏𝟐 𝒖 𝒌𝝏𝟐 𝒖
→ = 𝒄𝒗 = ... is differential equation of 1D-Consolidation developed by Terzaghi
𝝏𝒕 𝝏𝒛𝟐 𝒎𝒗 𝜸𝒘 𝝏𝒛𝟐
Q3. Laboratory test on a 25mm thick clay specimen drained at both top and bottom show
that 45% consolidation (Tv=0.4) takes place in 8.5minutes. How long it takes for a similar
clay layer in the field, 4m thick but drained at the top only, to undergo 65% consolidation
(Tv=0.34)
Solution
From Terzaghi's suggestion the consolidation Time unit less is equal at the field and in the lab
8.5𝑚𝑖𝑛 ∗ (4000mm)2
𝑡𝑓𝑖𝑒𝑙𝑑 45% = = 8.704 ∗ 105 min
(12.5𝑚𝑚)2
0.34∗1.656
𝑡65% = 𝑦𝑒𝑎𝑟𝑠 = 3.754 𝑦𝑒𝑎𝑟𝑠
0.15
Q4. Consider the case of initial excess pore water that is constant with depth i.e. Ut=Uo. For
Tv=0.4. Determine the degree of consolidation at a depth H/3 measured from the top of the
layer.
Solution
Sin 𝟐 𝑴𝒁
𝟐𝑻 𝟐
Step Tv Z/H M M MZ/H 2/M (MZ/H 𝒆𝒙𝒑(−𝑴 𝒗)
𝑴
𝐬𝐢𝐧
𝑯
𝒆𝒙𝒑(−𝑴 𝑻𝒗)
)
1 0.4 1/3 0 1.6 0.52 1.27 0.50 0.3730809 0.237521883
2 0.4 1/3 1 4.7 1.57 0.42 1.00 0.00014 5.94615E-05
3 0.4 1/3 2 7.9 2.62 0.25 0.50 1.973E-11 2.51885E-12
𝟐 𝑴𝒁 (−𝑴𝟐 𝑻𝒗 )
∑∞
𝒎=𝟎 𝐬𝐢𝐧 𝒆𝒙𝒑 = 0.237581345
𝑴 𝑯
Note in the above table we need not go beyond m=3, since the expiration in step 3 is negligible for m ≥ 3
Uav = 0.7624
Q5. A square footing of size 8*8m at a depth of 2m below the ground surface in loose to
medium dense sand with qn =120KN/m2 (net contact pressure at the base of foundation ),
standard penetration tests conducted at the site give the following corrected N60 Values. The
water table is at the base of foundation. The saturated unit weight of soil from ground level
to depth of 18m is 16.5KN/m3.
Use the Equation Es = 250 (Avg Ncor +15) for computing the modulus of Elasticity of the sand. Assume
µ=0.3 and the depth of the compressible layer =2B= 16m (=H)
Estimate the elastic settlement by Schmetmann's method by making use of the relationship qc = static
cone penetration value in kg/cm2. Assume settlement is required at the end of 3 years.
Solution
𝑰
𝑺𝒆 = 𝑪𝟏 𝑪𝟐 (𝒒) ∑ 𝑬𝒛 ∆𝒁
𝒒 𝒕
Where 𝑪𝟏 = 𝟏 − 𝟎. 𝟓 ( 𝒒𝟎 ) 𝒂𝒏𝒅 𝑪𝟏 = 𝟏 + 𝟎. 𝟐 𝐥𝐨𝐠 (𝟎.𝟏)
First calculate the value of Iz at the middle of each layer and ∆Z
𝒒 𝟎.𝟓
𝑰𝒛(𝒑𝒆𝒂𝒌) = 𝟎. 𝟓 + 𝟎. 𝟏 (𝝈 ) q is net pressure =120KN/m3
𝟎
where 𝑍(𝑝𝑒𝑎𝑘) = 0.5𝐵 = 0.5 ∗ 8 = 4𝑚 then determine the stress at Z peak
𝜎𝑜(𝑝𝑒𝑎𝑘) = (2 + 4) ∗ 𝛾𝑠𝑎𝑡
𝐾𝑁
= (2 + 4) ∗ 16.5 𝑚3 = 6 ∗ 16.5𝐾𝑁/𝑚2
𝜎𝑜(𝑝𝑒𝑎𝑘) = 𝟗𝟗𝑲𝑵/𝒎𝟐 and 𝑞0 = 16.5 ∗ 2 = 33𝑘𝑛/𝑚2
𝐼𝑧 = 0.1 𝑎𝑡 𝑍 = 0
120 0.5
𝐼𝑧(𝑝𝑒𝑎𝑘) = 0.5 + 0.1 ( 99 ) = 0.647
𝑰𝒛(𝒑𝒆𝒂𝒌) = 𝟎. 𝟔𝟒𝟕
𝐼𝑧 = 0 𝑎𝑡 𝑍 = 𝑍𝑜 = 2𝐵
Using the above value of Iz and draw the diagram to determine the Iz at the middle of each layer
qn=120 KN/m2
Df =2m
IZ
E=6000Mpa 1
3
2
E=6750Mpa
4 B/2=5
3
E=6750Mpa
4
E=8000Mpa
16
0 0.1 0.647= Iz(peak)
2B=Z0=16m
Using the Tabular form calculate the value of E from the given equation (𝐸𝑠 = 250(Avg 𝑁𝑐𝑜𝑟 + 15) and
the value of Iz at the middle of each layer from the above diagram.
Assignment-3
Final Exam
Q1. A 5-m-thick clay layer, drained at the top only, has some sand drains. A uniform
surcharge is applied at the top of the clay layer. Calculate the average degree of
consolidation for combined vertical and radial drainage after 100 days of load application,
given Cvr= Cv= 4mm2/ min, de = 2m, and rw= 0.2m. Use the equal-strain solution.
Solution
Given
𝐻𝑑𝑟 = 5𝑚 ,𝑡 = 100 𝑑𝑎𝑦𝑠, 𝐶𝑣𝑟 = 𝐶𝑣 = 4𝑚𝑚2 /𝑚𝑖𝑛, 𝑑𝑒 = 2𝑚, 𝛾𝑤 = 0.2𝑚
𝑈𝑣𝑟 = 1 − (1 − 𝑈𝑟 )(1 − 𝑈𝑣 )
𝐶𝑣 𝑡
First calculate for Vertical drainage Tv , 𝑇𝑣 = 2
𝐻𝑑𝑟
4𝑚𝑚2 ∗24∗60∗100𝑑𝑎𝑦𝑠
𝑇𝑣 = (5000𝑚𝑚)2
= 0.02304
𝐶𝑣𝑟 𝑡
Calculate Radial drainage of Tr where 𝑇𝑟 = 2
𝑑𝑒
2
4𝑚𝑚 ∗ 24 ∗ 60 ∗ 100 𝑚𝑖𝑛
𝑇𝑟 = = 0.144
(2000𝑚𝑚)2
𝑻𝒓 = 0.144
Then calculate the radial consolidation and vertical degree of consolidation
Radial Degree of consolidation Ur
−8𝑇 𝑛2 3𝑛2 −1
𝑈𝑟 = 1 − 𝑒𝑥𝑝 ( 𝐹(𝑛)𝑟 ) where 𝐹(𝑛) = 𝑛2 −1 𝑙𝑛(𝑛) − 4𝑛2
𝑟 𝑑𝑒 2𝑚
but 𝑛 = 𝑟𝑒 𝑤ℎ𝑒𝑟𝑒 𝑟𝑒 = = = 1𝑚 𝑎𝑛𝑑 𝑟𝑤 = 0.2𝑚
𝑤 2 2
1𝑚
then 𝑛 = 0.2𝑚 = 5
52 3∗52 −1 25 74
Therefore 𝐹(𝑛) = 52 −1 𝑙𝑛(5) − = 𝑙𝑛(5) − 100
4∗52 24
𝑭(𝒏) = 𝟎. 𝟗𝟑𝟔𝟓
−8 ∗ 0.144
𝑈𝑟 = 1 − 𝑒𝑥𝑝 ( ) = 0.708
0.9365
𝑼𝒓 = 𝟎. 𝟕𝟎𝟖
Then calculate the vertical degree of consolidation using table 6.1 or the below formula
2
𝑈𝑧 = 1 − ∑∞ 2
𝑚=0 𝑀2 𝑒𝑥𝑝(−𝑀 𝑇𝑣 ) using the tabular form calculate Uz
M M 2 where 𝑀 = (2𝑚 + 1)𝜋/2 where m= 0,1,2,3,4...... ∞
𝑒𝑥𝑝(−𝑀2 𝑇𝑣 )
𝑀2
0 𝜋/2 0.766596
1 3𝜋/2 0.054077
2 5𝜋/2 0.007847 for m≥4 the value is almost negligible
2
3 7𝜋/2 0.001024 𝑈𝑧 = 1 − ∑∞ 2
𝑚=0 𝑀2 𝑒𝑥𝑝(−𝑀 𝑇𝑣 ) = 1 − 0.829645
4 9𝜋/2 0.000101
𝑼𝒛 = 𝟎. 𝟏𝟕
∑∞
𝒎=𝟎 = 0.829645
Now calculate the 𝑈𝑣𝑟
𝑈𝑣𝑟 = 1 − (1 − 𝑈𝑟 )(1 − 𝑈𝑣 )
𝑈𝑣𝑟 = 1 − (1 − 0.17)(1 − 0.708) = 0.758
𝑼𝒗𝒓 = 0.758 = 75.8% …..……………………………… (ANSWER)
Q2. Figure 1 represents a steady state one dimensional seepage situation in which the
upstream and downstream water levels are maintained constant. The container in which
the soil (permeability K=1.2*10-5m/sec, and porosity n=0.2) has been placed consists of two
sections having different diameters. The area of upper (AU) and Lower (AL) sections are
28cm2 and 14cm2 respectively.
a) Determine the rate of seepage flow through the soil.
b) Calculate the actual velocity of the flow through the upper section of the soil.
c) Plot the total head, pressure Head and elevation head along the tube.
(Hint; Firstly it is necessary to establish an arbitrary datum from which the elevation head may be
measured. Let this datum be located a distance of 4cm below the lower boundary of the soil.)
Solution
∆𝐻
= 𝐴𝑢𝑝 𝑘 𝐿
𝑢𝑝
but from continuity of equation the flow of rate are equal for inflow and outflow
∆𝐻𝑙𝑜𝑤 ∆𝐻𝑙𝑜𝑤
so, 𝑞𝑢𝑝 = 𝑞𝑙𝑜𝑤 → 𝐴𝑢𝑝 𝑘𝑢𝑝 = 𝐴𝑙𝑜𝑤 𝑘𝑙𝑜𝑤 but 𝒌𝒍𝒐𝒘 =
𝐿𝑢𝑝 𝐿𝑙𝑜𝑤
𝒌𝒖𝒑 𝑏𝑒𝑐𝑎𝑢𝑠𝑒 𝑡ℎ𝑒 𝑠𝑜𝑖𝑙 𝑝𝑟𝑜𝑝𝑒𝑟𝑡𝑖𝑒𝑠 𝑎𝑟𝑒 𝐻𝑜𝑚𝑜𝑔𝑒𝑛𝑒𝑜𝑢𝑠
∆𝐻𝑙𝑜𝑤
then from the above equation find ∆𝐻𝑢𝑝
∆𝐻𝑙𝑜𝑤
= 2.5 then ∆𝑯𝒍𝒐𝒘 = 𝟐. 𝟓 ∗ ∆𝑯𝒖𝒑 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 𝒆𝒒𝟏
∆𝐻𝑢𝑝
ℎ𝑒 = 44𝑐𝑚
ℎ𝑝 = 20𝑐𝑚
∆𝐻𝑙𝑜𝑤 + ∆𝐻𝑢𝑝 = 64𝑐𝑚 𝑡ℎ𝑒𝑛 𝑠𝑢𝑏𝑠𝑡𝑖𝑡𝑢𝑡𝑒 𝑒𝑞1 𝑛𝑜𝑤 where ∆𝐻𝑙𝑜𝑤 = 2.5∆𝐻𝑢𝑝
18.29𝑐𝑚
𝑞𝑢𝑝 = 1.2 ∗ 10−5 𝑚/𝑠𝑒𝑐 ∗ 28𝑐𝑚2 = 38.41 ∗ 10−3 𝑐𝑚3 /𝑠𝑒𝑐
16𝑐𝑚
∆𝐻𝑙𝑜𝑤 45.71𝑐𝑚
𝑞𝑙𝑜𝑤 = 𝑘𝐴𝑙𝑜𝑤 𝑖𝑙𝑜𝑤 , 𝑖𝑙𝑜𝑤 = =
𝐿𝑙𝑜𝑤 20𝑐𝑚
45.71𝑐𝑚
𝑞𝑙𝑜𝑤 = 1.2 ∗ 10−5 𝑚/𝑠𝑒𝑐 ∗ 14𝑐𝑚2 = 38.41 ∗ 10−3 𝑐𝑚3 /𝑠𝑒𝑐
20𝑐𝑚
18.29𝑐𝑚
𝑉𝑢𝑝𝑝 = 𝑘𝑖𝑢𝑝𝑝 = 1.2 ∗ 10−5 𝑚/𝑠𝑒𝑐 ∗ = 1.372 ∗ 10−5 𝑚/𝑠𝑒𝑐
16𝑐𝑚
𝑉𝑢𝑝𝑝 1.372𝑚/𝑠𝑒𝑐
𝑽𝒔(𝒖𝒑𝒑) = = = 6.86 ∗ 10−5 𝑚/𝑠𝑒𝑐
𝑛 0.2
ℎ𝑒 = 44𝑐𝑚
The head at the junction of upper and lower soil is, let it say B
ℎ𝐵 = ℎ𝑡𝑜𝑡 − ℎ𝑢𝑝𝑝
Q3. In a material with a Poisson ratio of µ=0.33, how much stiffer is material if its sides are
constrained (not allowed to move in or out)?
Solution
When the side is constrained means 𝑡ℎ𝑒 𝑠𝑡𝑟𝑎𝑖𝑛 𝑖𝑛 𝑥 𝑎𝑛𝑑 𝑦 𝑑𝑖𝑟𝑒𝑐𝑡𝑖𝑜𝑛 𝑎𝑟𝑒 𝑒𝑞𝑢𝑎𝑙 𝑡𝑜 𝑧𝑒𝑟𝑜
∈𝑥 =∈𝑦 = 0, 𝜎𝑥 = 𝜎𝑦 𝑏𝑢𝑡 ≠ 0
1
∈𝑥 = 𝐸 (𝜎𝑥 − 𝑣(𝜎𝑦 + 𝜎𝑧 ))
1
0 = 𝐸 [𝜎𝑥 − 𝑣𝜎𝑦 − 𝑣𝜎𝑧 ] but 𝜎𝑥 = 𝜎𝑦 , 𝑡ℎ𝑒𝑟𝑒𝑓𝑜𝑟𝑒
1
0 = 𝐸 [𝜎𝑥 − 𝑣𝜎𝑥 − 𝑣𝜎𝑧 ] → 0 = 𝜎𝑥 − 𝑣𝜎𝑥 − 𝑣𝜎𝑧
𝜎𝑥 𝑣
𝑣𝜎𝑧 = 𝜎𝑥 (1 − 𝑣) → = (1−𝑣) 𝑤ℎ𝑖𝑐ℎ 𝑚𝑒𝑎𝑛𝑠 𝑡ℎ𝑒 𝑠𝑡𝑖𝑓𝑓𝑛𝑒𝑠𝑠 𝑘0
𝜎𝑧
𝑣 0.33
Then calculate the stiffness using the above equation 𝑘0 = (1−𝑣) = 1−0.33
Q4. Two identical samples of clay are isotropically normally compressed to an all round effective
pressure of 200 Kpa and are then allowed to swell back to an effective isotropic pressure of 100
Kpa. The first sample is then subjected to standard drained compression test. What is the deviator
stress at failure and what is the volumetric strain experienced by the sample at failure? The second
sample is subjected to a standard undrained compression test. What are the deviator stress and
pore pressure at failure, if there is initially a back pressure of 100 Kpa?
Assume that the soil has the following critical state properties;
𝑴 = 𝟎. 𝟗𝟓, 𝝀 = 𝟎. 𝟎𝟗𝟓 , 𝜞 = 𝟐. 𝟎𝟔, 𝜿 = 𝟎. 𝟎𝟑𝟔, and N= 2.12.
Solution
𝑬
Q5. Derive the relationship for Bulk modulus (B); 𝑩 = , show all necessary steps and
𝟑(𝟏−𝟐𝝁)
assumptions.
Solution
𝜎
From initial bulk modulus 𝐵 = ∈ 0
𝑉𝑜𝑙
1 1
Where ∈𝑉𝑜𝑙 =∈𝑥 +∈𝑦 +∈𝑧 and ∈𝑥 = 𝐸 (𝜎𝑥 − 𝑣(𝜎𝑦 + 𝜎𝑧 )) , ∈𝑦 = 𝐸 (𝜎𝑦 − 𝑣(𝜎𝑥 + 𝜎𝑧 ))
1
𝑎𝑛𝑑 ∈𝑧 = (𝜎 − 𝑣(𝜎𝑦 + 𝜎𝑥 ))
𝐸 𝑧
𝜎0 𝜎 1
Therefore 𝐵 = ∈ = 3∈0 where ∈= 𝐸 (𝜎𝑥 − 𝑣(𝜎𝑦 + 𝜎𝑧 )) 𝑏𝑢𝑡 𝜎𝑥 = 𝜎𝑦 = 𝜎𝑧 = 𝜎0
𝑉𝑜𝑙
𝜎0 𝜎0
= 1 = 1
3 (𝜎0 −𝑣(𝜎0 +𝜎0 )) 3 (𝜎0 −𝑣(2𝜎0 ))
𝐸 𝐸
𝜎0 𝜎0 𝜎0
= 1 = 1 = 3
3 (𝜎0 −𝑣(2𝜎0 )) 3 (𝜎0 −𝑣2𝜎0 ) 𝜎 (1−2𝑣)
𝐸 𝐸 𝐸 0
𝑬
𝑩= ............................................................Answer
𝟑(𝟏−𝟐𝒗)
Q6. Traxial test data for the soil sample collected from Ayer Tena area given below in
Table. The cell pressure (sc) = 300KPa and it was zero before application. The initial height
of the sample (Lo) = 100cm.
Estimate:
a. The value of B (Skempton pore pressure parameter), state where the sample is saturated or not
b. Plot deviator stress Vs strain
c. Plot A Vs strain
Solution
Strain (L/Lo
Deviator stress =
1000
900
800
700
Deviatoric stress
600
500
400
300
200
100
0
0 0.025 0.05 0.075 0.1 0.125 0.15 0.175 0.2 0.225
Strain
c. “A” Vs Strain
A = A’/B, A’ = U
0.50
0.40
0.30
0.20
0.10
0.00
A
-0.10 0 0.025 0.05 0.075 0.1 0.125 0.15 0.175 0.2 0.225
-0.20
-0.30
-0.40
-0.50
-0.60
Strain